Bottom of the raft slab is at -22.385 m and top of D-Wall is at -20.11 m.

Hence, the wall structure above the


D-wall top level is exposed to backfilling or other works.
Bottom of the raft slab is at -30.535 m and top of D-Wall/Contiguous piles is at -20.11 m. Hence, the wall above the
structure D-wall/Contiguous pile level is exposed to backfilling or other works.

Bottom of the raft slab is at -32.215 m, D-Wall is far away from permanent structure wall and excavation is open-cut.
Hence, the wall from raft slab level is exposed to backfilling or other works.

Bottom of the raft slab is at -29.535 m, D-Wall is far away from permanent structure wall and excavation is
open-cut. Hence, the wall from raft slab level is exposed to backfilling or other works.

Bottom of the raft slab is at -30.805 m and top of D-Wall/Contiguous piles is at -22.00 m.
Hence, the wall structure above D-Wall/Contiguous piles top level is exposed to backfilling or other works.

Bottom of the raft slab is at -22.385/-30.535 m, D-Wall is far away from permanent structure wall
and excavation is open-cut. Hence, the wall from raft slab level is exposed to backfilling or other works.