Resource Listing

This section identifies the types and numbers of resources required to complete the project. A ‘resource’
is typically defined as the labour, equipment and materials used to complete the activities in the Project.

Equipment
List all of the items of equipment required to undertake the project, including computers, furniture,
building facilities, machinery and vehicles. Each item of equipment should be defined by outlining its
purpose, specification and period required by completing the following table.

Note:
• All major equipment Items within the project should be listed here
• The No. represents the number of equipment items required to undertake the project
• The Start-Date and End-Date provides the timeframe for which the equipment is required by the
project.

Item No. Purpose© Specification Start End Date


Date

COMPUTER/PC 5 To enable the project team High processing speed xx/yy/zz xx/yy/zz
to plan, monitor and 60 gig disk space19 inch
control the project monitor

EXCAVATOR 2 It is a construction vehicle Made up of 2 parts: a


used to excavate or move driving base associated a
large objects. powerful boom arm with
an attachment designed
for excavating.

GRADER 1 Used to prepare the base A grader is a


course to create a wide flat construction machine
surface for the asphalt to with a long blade used to
be placed on. create a flat surface.

LOADER 1 Laying pipe, Clearing The Loader has a large


rubble, of Construction bucket with a shorter
waste and other materials moving arm.
4. Small excavations.

BACKHOE 2 Used in excavating Consists of a digging


equipment or digger. bucket on the end of a
two-part articulated arm.
They are typically
mounted on the back of a
tractor or front loader.
BULLDOZER 1 Used to loosen densely- A crawler with a
compacted materials. substantial metal plate
fitted to push large
amounts of soil, sand,
dirt or other materials.
CONSTRUCTION VEHICLES

Item No. Purpose© Specification Start Date End Date