Inspection of materials delivered to site

Date: 13 FEB.2023
Request no.: MIR-CSCEC-12-D01-ME-HD-0701-00
Project no. & title: E18066-0200S - The Central Business District of the New Administrative Capital of Egypt

Employer: Engineer: Contractor

1. Material / equipment
Description : Fabricated Galvanized Steel Duct (APRTMENT LINER & MISSING PARTS-8F-FCU-LOW)
Materials submittal ref. no. : MAT-CSCEC-12-ME-HD-0041-00 Date : 16/08/2021
Bill of quantities ref. no. : 233113-METAL DUCT
Quantity : Fabricated Galvanized Steel : AS PER ATTACHED DELIVERY NOTE ( 210 KG)

2. Manufacturer's details
Manufacturer : CSCEC
Model no.: Serial no. :
Country of origin: Egypt
Date of ARRIVAL on Site : 12/2/2023
STORAGE Location : DO1
Submitted by : LI JIAN MING Signature : LI JIAN MING

3. Inspection report
Yes/No Initials
Physical damage ? Yes No
Details given above correct ? Yes No
Conform with approved submission ? Yes No
Accessories/ spare parts included ? Yes No
Contractor shall follow manufacturer and SMACNA recommendations regarding the
Details :installation
procedures.
- storing and handling shall be as supplier recommendation and specs any damaging due
to bad storing is sole contractor responsibility to change without extra cost or time
Remarks:
--Final approval based on the quality of collecting duct and installation and leak test
-Final approval based on acoustic and noise criteria to be in acceptance limits
Ahmed Adel -Reda elsayed - 27/02/2023

4.Engineer's Representative comments


The above material has been inspected on site and found at time of inspection to be :

Satisfactory Unsatisfactory

for incorporation in the permanent works.

Signature Hassanein Ali Date : 27-02-2023


Above inspection shall not relieve Contractor of his responsibilities to incorporate in the Works only such materials that are in
conformity with the Contract.

S-PRC-SS-02(F36) Rev 1
Transmittal Of Documents
Date: 13 JUN. 2021
Request no: PRQ-CSCEC-12-D01-ME-HD-0001-02
Project No. & Title:E18066-0200S - The Central Business District of the New Administrative Capital of Egypt

Employer: Engineer: Contractor:

1. Document type

Material samples Catalogues Tests Technical sheets


Manufacturer certificates Schedules Other

2. Submittal details
Contract doc. Ref. &
Item no. Description of items submitted/ quantity Ref.
compliances
PRE-QULIFICATION DOCUMENTS FOR METAL DUCT
1
FABRICATION WORKSHOP

These are transmitted for:


Your information Approval Review & comment Other

Submitted by: AHMED ABOELFOTOUH Signature: AHMED ABOELFOTOUH

3. Engineeer's Representative comments:

Approved
HSE comments: The COSHH assessment for the
chemicals substances should be attached.
Approved as noted
CODE: Approved as noted
Mechanical: Refer to comments on the attached file.

Revise & resubmit


A.B Reda El sayed Tamer El beltagy 14/6/2021

Rejected

Others

Signature: M.N Date :


14-06-2021
Approval shall not relieve Contractor of his liabilities under the Contract or constitute authorization of any change to Contract Documents.

S-PRC-SS-02 (F43) Rev 2


Submittal For Approval Of Materials
Date: 16 AUG.2021
Request no: MAT-CSCEC-12-ME-HD-0041-00
Project No. & Title: E18066-0200S - The Central Business District of the New Administrative Capital of Egypt

Employer: Engineer: Contractor:

1. Material description (one item only on this form) :


Metal Duct Raw Material (without sample)

Area of application : Tower-D01

Drawing ref. : B.O.Q. ref. no.: 233113-METAL DUCT

Specification Ref. : 233113-METAL DUCT Standards: ASTM A 653/A653M, Z275(G90)


Attach all relevant technical literature marked to identify relevant description, current Test Certificates, samples as appropriate.

2. Manufacturer / supplier:
Company Name : Kandil(Galva&Kama)Coating
Address : Obour City - Industrial Zone Area # (5,6,9,8B) - Block 13035 Postal Code Cairo- Egypt
Local agent : Kandil(Galva&Kama)Coating

3. Delivery :
Country of origin :
Availability Egypt

Locally Manufactured Overseas

Delivery : Ex-works/ total duration [ ] [ ]


Estimated time of arrival on site [ ]

Program : Date material required on site [ ]


Latest date for order [ ]

We certify that the above submitted items have been reviewed in detail and are correct and in strict conformity with the contract drawings and specifications
except as otherwise stated; also that the material sources indicated above have been reviewed in detail and that they will supply the submitted items in conformity
with the above and deliver same timely.

Submitted by : LIU JUNBO Signature: LIU JUNBO

4. Engineer's Representative comments: Approved


Approved as noted
Previous comments in material submittal reference (MAT-CSCEC-00-ME- Revise and
HD-0111-00) , still valid until covering all comments resubmit
Rejected
Sample required
R-Elsayed 19/8/2021 Tests required
Additional
information
required

Hassanein Ali 19-08-2021


Manufacturer's
Signature: Date: guarantee
required
Approval shall not relieve Contractor of his liabilities under the Contract or constitute authorization of any change to Contract Documents.
AM-1
S-PRC-SS-02(F26) Rev 2
Project no. & title: E18066-0200S - The Central Business District of the New Administrative Capital of Egypt
Employer Consultant Contractor

Delivered Material Quantities "MIR"


Galvanized Duct
PK Tower
Quantity (Kg)
Country of Total Quantity Area of
No. MIR Ref. Date of MIR Status Approved Material Submittal Ref. Manufacturer Supplier
Origin Thickness - 0.6mm Thickness - 0.8mm Thickness - 1.0mm Thickness - 1.25mm Thickness - 1.5mm Thickness - 1.6mm (Kg) Application
Weight Weight Weight Weight Weight Weight
Coil No. Coil No. Coil No. Coil No. Coil No. Coil No.
Kg Kg Kg Kg Kg Kg
Kandil (Galva&Cama)
428 MIR-CSCEC-12-D01-ME-HD-0696-00 7/Feb/23 PRQ-CSCEC-12-D01-ME-HD-0001-05 CSCEC
coating
EGYPT 709 359609E 810 388103B 1519
Kandil (Galva&Cama)
429 MIR-CSCEC-12-D01-ME-HD-0698-00 12/Feb/23 PRQ-CSCEC-12-D01-ME-HD-0001-05 CSCEC
coating
EGYPT 64 359609D 65 388103A 129
Kandil (Galva&Cama)
430 MIR-CSCEC-12-D01-ME-HD-0699-00 12/Feb/23 PRQ-CSCEC-12-D01-ME-HD-0001-05 CSCEC
coating
EGYPT 68 359609D 54 388103A 122
Kandil (Galva&Cama)
431 MIR-CSCEC-12-D01-ME-HD-0700-00 12/Feb/23 PRQ-CSCEC-12-D01-ME-HD-0001-05 CSCEC
coating
EGYPT 73 359609D 53 388103A 126
Kandil (Galva&Cama)
432 MIR-CSCEC-12-D01-ME-HD-0701-00 12/Feb/23 PRQ-CSCEC-12-D01-ME-HD-0001-05 CSCEC
coating
EGYPT 101 359609D 109 388103A 210
Kandil (Galva&Cama)
433 MIR-CSCEC-12-D01-ME-HD-0702-00 12/Feb/23 PRQ-CSCEC-12-D01-ME-HD-0001-05 CSCEC
coating
EGYPT 26 362357E 28 388104C 54
Kandil (Galva&Cama)
434 MIR-CSCEC-12-D01-ME-HD-0703-00 12/Feb/23 PRQ-CSCEC-12-D01-ME-HD-0001-05 CSCEC
coating
EGYPT 591 362357E 739 388104C 1330
Kandil (Galva&Cama)
435 MIR-CSCEC-12-D01-ME-HD-0704-00 12/Feb/23 PRQ-CSCEC-12-D01-ME-HD-0001-05 CSCEC
coating
EGYPT 67 362357E 39 388104C 106
Kandil (Galva&Cama)
436 PRQ-CSCEC-12-D01-ME-HD-0001-05 CSCEC
coating
EGYPT 0
Kandil (Galva&Cama)
437 PRQ-CSCEC-12-D01-ME-HD-0001-05 CSCEC
coating
EGYPT 0
Kandil (Galva&Cama)
438 . PRQ-CSCEC-12-D01-ME-HD-0001-05 CSCEC
coating
EGYPT 0
Kandil (Galva&Cama)
439 PRQ-CSCEC-12-D01-ME-HD-0001-05 CSCEC
coating
EGYPT 0
Total 101019 116412.5 7245.7 20886.8 10048 9038 264650
Zinc
Origin of Coating Salt
Coil No. of Coil No.
the Hot Heat no. Steel ADH Gravimetr Spray
finished of Hot Dimensions (mm) Weight Chemical Composition (%) Mechanical Properties ic Triple
Roll of HRC grade Test Test
product Roll Spot Test
material (hrs)
Gm/m2
Yield Ultimate Hardn
Thickn Elongat
ess
width length Net Grs C SI Mn P S Al Strength Tensile (N/
ion (%)
ess
(N/mm2) mm2) (HRB)

359018MB 02112926 DX51D 0.600 1,250 4.01 4.05 0.045 0.021 0.26 0.001 0.001 0.033 238 320 27.0 47 Pass 286 Pass

359018MC 02112926 DX51D 0.600 1,250 4.075 4.115 0.045 0.021 0.26 0.001 0.001 0.033 238 320 27.0 63 Pass 290 Pass

359018MD 02112926 DX51D 0.600 1,250 3.44 3.48 0.045 0.021 0.26 0.001 0.001 0.033 238 320 27.0 59 Pass 285 Pass

359490A 16656 DX51D 0.800 1,250 4.1 4.14 0.105 0.013 0.291 0.012 0.018 0.030 327 383 31.9 58 Pass 286 Pass

359490B 16656 DX51D 0.800 1,250 4.28 4.32 0.105 0.013 0.291 0.012 0.018 0.030 327 383 31.9 56 Pass 286 Pass

359526A 2151925 DX51D 0.800 1,250 4.335 4.375 0.050 0.009 0.163 0.004 0.012 0.033 311 362 33.3 48 Pass 288 Pass

359526B 2151925 DX51D 0.800 1,250 4.34 4.38 0.050 0.009 0.163 0.004 0.012 0.033 311 362 33.3 48 Pass 287 Pass

359526C 2151925 DX51D 0.800 1,250 4.39 4.43 0.050 0.009 0.163 0.004 0.012 0.033 311 362 33.3 46 Pass 287 Pass

359526E 2151925 DX51D 0.800 1,250 3.7 3.74 0.050 0.009 0.163 0.004 0.012 0.033 311 362 33.3 47 Pass 288 Pass

359609A 2112925 DX51D 0.600 1,250 4.13 4.17 0.047 0.021 0.12 0.003 0.006 0.044 300 358 31.5 63 Pass 290 Pass

359609B 2112925 DX51D 0.600 1,250 4.08 4.12 0.047 0.021 0.12 0.003 0.006 0.044 300 358 31.5 61 Pass 289 Pass

359609C 2112925 DX51D 0.600 1,250 4.045 4.085 0.047 0.021 0.12 0.003 0.006 0.044 300 358 31.5 59 Pass 284 Pass

359609D 2112925 DX51D 0.600 1,250 3.935 3.975 0.047 0.021 0.12 0.003 0.006 0.044 300 358 31.5 58 Pass 282 Pass

359609E 2112925 DX51D 0.600 1,250 3.84 3.88 0.047 0.021 0.12 0.003 0.006 0.044 300 358 31.5 59 Pass 283 Pass

361141A 21224766 DX51D 0.600 1,250 4.035 4.075 0.040 0.006 0.213 0.007 0.011 0.042 287 343 36.5 45 Pass 286 Pass
Production schedule of air ducts
Project: CBD APRTMENT LINER & MISSING PARTS-8F-FCU-LOW
Package/Bdg/Lev: P2/D01/L-8 2B-M-B4
Draw No:SHD-CSCEC-12-D01-ME-HD-04-GL-00-0807-0000-00 Static pressure:LOW ; 2/12/2023

Length(m GALVANIZATI
No. Type Thick(m Specification Connectio Coil NO. Quantity Area(m2) Density(k Weight(kg Tag No.
m) ON
m) n Type g/m2) )

1 Straight 0.6 785*400 TDF Liner 359609D 450 1 1.07 5.64 6.62 FCU-D03-02 277

2 Shoe 0.6 350*350/350*350 TDF 359609D 473 1 0.66 5.64 4.11 FCU-D03-02 278

3 Offset 0.6 350*350 TDF 359609D 490 1 0.69 5.64 4.26 FCU-D03-02 275

4 Reducer 0.8 800*255/350*350 TDF Liner 388103B 310 1 0.65 6.86 4.94 FCU-D03-02 275

5 Elbow 0.6 350*350 TDF Liner 359609D 650 1 0.91 5.64 5.65 FCU-D03-01 275

6 Straight 0.6 350*350 TDF Liner 359609D 320 1 0.45 5.64 2.78 FCU-D03-01 277

7 Straight 0.6 785*350 TDF Liner 359609D 500 1 1.14 5.64 7.04 FCU-D03-01 275

8 Shoe 0.6 400*300/400*300 TDF 359609D 443 1 0.62 5.64 3.85 FCU-D03-01 275

9 Offset 0.6 300*400 TDF 359609D 600 1 0.84 5.64 5.21 FCU-D03-01 276

10 Reducer 0.8 800*250/500*350 TDF Liner 388103B 600 1 1.26 6.86 9.51 FCU-D03-01 278

11 Straight 0.6 450*300 TDF 359609D 1100 1 1.65 5.64 10.24 FCU-D03-01 276

12 Offset 0.6 200*200 TDF 359609D 610 2 0.98 5.64 6.06 FCU-D03-01 275

13 Straight 0.6 200*200 TDF 359609D 500 1 0.40 5.64 2.48 FCU-D03-01 278

14 Shoe 0.6 300*150/200*150 TDF 359609D 360 1 0.32 5.64 2.01 FCU-D03-01 275

15 Offset 0.6 200*200 TDF 359609D 870 1 0.70 5.64 4.32 FCU-D03-01 275

16 Straight 0.6 785*400 TDF Liner 359609D 450 1 1.07 5.64 6.62 FCU-D03-01 277

17 Shoe 0.6 350*350/350*350 TDF 359609D 473 1 0.66 5.64 4.11 FCU-D03-01 275

18 Offset 0.6 350*350 TDF 359609D 450 1 0.63 5.64 3.91 FCU-D03-01 276

19 Reducer 0.8 800*255/350*400 TDF Liner 388103B 420 1 0.89 6.86 6.69 FCU-D03-01 275

20 Elbow 0.6 350*400 TDF Liner 359609D 650 1 0.98 5.64 6.05 FCU-D03-01 276

21 Straight 0.6 850*235 TDF Liner 359609D 400 1 0.87 5.64 5.39 FCU-D03-01 277

22 Shoe 0.6 350*150/350*150 TDF 359609D 625 1 0.63 5.64 3.88 FCU-D03-01 276

23 Elbow 0.6 350*150 TDF 359609D 650 1 0.65 5.64 4.03 FCU-D03-01 276

24 Straight 0.6 350*150 TDF 359609D 390 1 0.39 5.64 2.42 FCU-D03-01 276

25 Reducer 0.8 865*200/400*200 TDF Liner 388103B 250 1 0.53 6.86 4.02 FCU-D03-01 276

26 Straight 0.6 400*200 TDF Liner 359609D 450 1 0.54 5.64 3.35 FCU-D03-01 277
Project No. P2&P6 Date 2/12/2023

Computed by Checked by

Subject Total Air Conditioning System


Galvanised Steel Rectangular Low Pressure Fresh Air Duct

Results

Gross Weight Duct Area Insulation Area


(kg) m2 m2
210 21 23

Weight Area
Strait Duct 105 11
Elbow 15 2
Reducer 56 3
Take Off 34 5
Plenum 0
Ring 0 0
End Cap 0 0
R-Elsayed 26/9/2020

Comments - General -
1-Vibration and seismic controls calculations to be submitted.
2-Supports calculations to be submitted,hanger type and spacing will be according to approved hanger calculations.
3-Provide fire dampers at fire walls penetrations.
4-Fire dampers and cleaning filter must be accessible properly for maintenance.
5-For general notes refer to (D01-MH-0-00-01).
6-Duct routing location / level, HVAC equipment and accessories must be coordinated with other trades (contractor's responsibility).
7-Air balancing study by specialist (third party) to be submitted.
8-Air outlets locations to be coordinated with reflected ceiling drawings.
9-Separate composite shop drawings for mechanical shafts to be submitted (elevations and plans) showing risers distribution, fixation
and accessibility.
10-Provide aluminum screen for all duct opening.
11-Thermostat location/level to be coordinated with Arch. & Elec. Drawings.
12-Duct branches dimensions and locations per each apartment shall be according to approved shop drawings per each apartment.
13-Penetration details by specialist for fire/non-fire walls to be submitted.
14-The contractor is responsible for achieving specified noise criteria.
15-

hanger type and spacing will be according to


approved hanger calculations.