Project: 1-STOREY HILL SIDE COMMUNITY CHURCH OF SDA

Location: Poblacion,Banga,Aklan
Date Begun: 24-Apr-23

WEEKLY ACCOMPLISHMENT REPORT

WEEK NO.13(July 17-22,2023)


Date Manpower ACTION TAKEN PROGRESS PHOTOS REMARKS

Ongoing installation of reinforcement


and formworks at beam and columns.
July
10 Ongoing installation of Steel Rafter Ongoing
17,2023
for roof framing
Ongoing Masonry works;laying of
concrete hollow blocks
Ongoing installation of reinforcement
and formworks at beam and columns.

Ongoing installation of Steel Rafter


for roof framing

July
12 Ongoing
18,2023

Ongoing Masonry works;laying of


concrete hollow blocks

July Ongoing Masonry works;laying of


12
18,2023 concrete hollow blocks

Page 1 of 4
July Ongoing installation of Steel Rafter
12 Ongoing
18,2023 for roof framing

Ongoing fabrication of formworks and


rebars for concrete stair

July
14 Ongoing
19,2023

Ongoing fabrication of formworks for


Slanting beam and columns

Page 2 of 4
Ongoing Masonry works;laying of
concrete hollow blocks

July
14 Ongoing
20,2023

Stair Concrete Pouring

Installation of C-Purlins for roof


Ongoing
framing.

July
13
21,2023

Ongoing plastering and masonry


works

Ongoing

Page 3 of 4
July Ongoing plastering and masonry
13
21,2023 works

July
15 Ongoing plastering works Ongoing
22,2023

Note:
* Roof framing materials delivered on site.
* Roofing scheduled to deliver on site on July 26,2023.
* Target to complete roof framing and roofing works on July 29,2023 when good wheather permits.