PT CIPTA DIMENSI BAJA NUSANTARA

Pulogadung Trade Center


Bekasi Raya Blok 8H No. 2-5
Cakung, Jakarta Timur 13920
Main +6221 4683 3951
www.ciptadimensi.co.id
WEEKLY REPORT (Steelwork at Workshop)
No. WR/CDBN-WS/001

To : Ibu Hani Fatin Siregar PO No. :-


Prepared by : Gian Dwi Putra Project Number : 485
Checked by : A. Wildan Customer : PT. Decorient Partaya Indonesia
Distribution : Project Name : Sampoerna RRP Phase 4
PT. Decorient Partaya Indonesia
Building Items :
PT. Cipta Dimensi Baja Nusantara 1. Ingredient
2. Waste Dock B3
3. Waste Dock Non B3
4. Canopy KR.09 Lot 17
5. Daily Canteen
6. Dust Collector
Status Checked on 26 Septembre 2023 is as follows

1. Overall Project Status - "On Schedule"


1. Contract/PO : N/A
2. Down Payment : N/A
3. Engineering Drawings : On Process
4. Shop Drawing Steel Structures : On Process
5. Fabrication : Embeded
6. Progress of Fabrication
a. Ingredient : 25 %
b. Waste Dock B3 :0%
c. Waste Dock Non B3 :0%
c. Canopy KR.09 Lot 17 :0%
d. Daily Canteen :0%
e. Dust Collector :0%
7. Outstanding Works : Outstanding terlampir dalam Monitoring
Shop Drawing

ACTIVITIES THIS WEEK


Cutting Raw Material For Ingredient
2. Project Update
Progress
Description Remarks
%

Shop Drawing
a. Ingredient 100%
b. Waste Dock B3 30%
c. Waste Dock Non B3 30%
c. Canopy KR.09 Lot 17 30%
d. Daily Canteen 20%
e. Dust Collector 30%

Fabrication
a. Ingredient 25%
b. Waste Dock B3 0%
c. Waste Dock Non B3 0%
c. Canopy KR.09 Lot 17 0%
d. Daily Canteen 0%
e. Dust Collector 0%

3. Next Report : 27-09-23


FM/PRJ-1/03 Rev : 0

BELUM SHOP DRAWING


TUNGGU APPROVED
PROSES REVISI APPROVED
FINISH
9-Nov-23

SHOP DRAWING APPROVED / REVISED


DESIGN DRAWING
PROJECT PIC
KETERANGAN ENG SUBMIT RECEIVED
R0 R1 R0 R1 R2 R3 R4 R0 R1 R2 R3 R4 R5 R6 R7

485 SAMPOERNA 26-Sep-23

485 PACKAGE 1

485 Production Building

485 STAIR PB

485 New Waste Dock Septa TUNGGU DATA SURVEY 10-Oct-23 10-Oct-23 12-Oct-23

485 New Waste Dock (Non-Hazardous) ANSHORI REVISI REFRENSI EXCISTING 30-Oct-23 31-Oct-23 02-Nov-23

485 Dust Collector PROSES PRINSIP DWG 09-Nov-23

485 PACKAGE 2

485 Warehouse

485 Logistic Office

485 TAX STAMP SUDAH MADDING

485 Ingredient Extension Building ANSHORI FABRICATION 11-Oct-23 16-Oct-23 25-Oct-23 02-Nov-23 13-Oct-23 20-Oct-23 31-Oct-23 02-Nov-23

485 Convert KR-08 WAIT APPROVED 27-Oct-23

485 CANOPY LOT 17/CANOPY KR-09 ANSHORI REVISI WAIT NEW DESIGN 13-Oct-23 30-Oct-23 08-Nov-23 09-Nov-23

485 DAILY CANTEEN 14-Oct-23

485 AHU SUDAH MODELING TUNGU DATA SURVEY

485 SAFETY POOL FABRICATION

Page 1