You are on page 1of 54

NATIONAL HIGH SPEED RAIL CORPORATION LIMITED (NHSRCL)

CONSTRUCTION OF
MUMBAI – AHMEDABAD HIGH SPEED RAIL
Package No. MAHSR-C-4

O20361-S-VIA-001-ME-01506

Date: 06 January 2021

Sensitivity: LNT Construction Internal Use


NATIONAL HIGH SPEED RAIL CORPORATION LIMITED

Larsen & Toubro Limited

CONSTRUCTION OF
MUMBAI-AHMEDABAD HIGH SPEED RAIL
Package No. MAHSR – C – 4

METHOD STATEMENT FOR PLATE LOAD TEST


AT CH. KM-205.447 AS PER JGS 1521-2012

Document No.
O20361-S-VIA-001-ME-01506
00 06-01-2021 SRI RRK/CAJ BDS

Initial Sign Initial Sign Initial Sign


RAJA RAJAN K B DHANA
Name A SRINIVAS Name ANBURAJ C Name SEKARAN
Rev Date SENIOR CHIEF
ENGINEERING
Designation DESIGN Designation Designation ENGINEERING
MANAGER
ENGINEER MANAGER
Prepared By Reviewed By Approved By
TABLE OF CONTENTS

1 INTRODUCTION ........................................................................................................................4
2 SCOPE OF THE REPORT ...........................................................................................................5
3 CONTRACTUAL REQUIREMENTS .........................................................................................5
4 REFERENCES .............................................................................................................................5
5 RESOURCES ...............................................................................................................................6
5.1 Equipment’s for Setting up test Arrangement ...............................................................................6
5.2 Manpower ......................................................................................................................................6
6 AUTHORITY AND RESPONSIBILITY.....................................................................................7
7 APPARATUS REQUIRED ..........................................................................................................9
7.1 Loading Plate ................................................................................................................................9
7.2 Hydraulic Jack...............................................................................................................................9
7.3 Support post .................................................................................................................................10
7.4 Reaction force components..........................................................................................................10
7.5 Loading/Pressure Gauges ...........................................................................................................11
7.6 Displacement Gauges ..................................................................................................................11
7.7 Stopwatch ....................................................................................................................................12
8 TEST DETAILS .........................................................................................................................12
8.1 Test location ................................................................................................................................12
8.2 Test load/Pressure .......................................................................................................................12
8.3 Size and shape of loading plate ...................................................................................................12
8.4 Loading method ...........................................................................................................................12
9 TEST PROCEDURE ..................................................................................................................13
9.1 General ........................................................................................................................................13
9.2 Excavation for test setup .............................................................................................................14
9.2.1 Excavation in Soil ...........................................................................................................15
9.2.2 Excavation in Rock .........................................................................................................15
9.3 Dewatering ..................................................................................................................................15
9.3.1 Sump Pumping ................................................................................................................15
9.4 Detailed Procedure for conducting plate load test .....................................................................16
9.4.1 In case bearing stratum is Rock ......................................................................................17
10 TEST COMPLETION ................................................................................................................19
11 INTERPRETATION OF TEST RESULTS................................................................................19
11.1 Method of processing test results for determining UBC of the ground .................................19
12 BACKFILL .................................................................................................................................20
13 MANDATORY SAFETY REQUIREMENTS ..........................................................................21
13.1 Preventive Measures to Control the spread of COVID-19 is attached as Annexure II .........21
CONSTRUCTION OF MUMBAI-AHMEDABAD HIGH O20361-S-VIA-001-ME-01506
SPEED RAIL
Package No. MAHSR – C – 4 QUALITY MANAGEMENT SYSTEM

METHOD STATEMENT FOR PLATE LOAD TEST


Rev No: 0 Date: 06-01-2021
AT CH. KM-205.447 AS PER JGS 1521-2012

ANNEXURE I – PLATE LOAD TEST DATA FORMAT


ANNEXURE II – PREVENTIVE MEASURES TO CONTROL SPREAD OF COVID-19
ANNEXURE III – BORELOGS
ANNEXURE IV – PLATE LOAD TEST DRAWINGS

Sensitivity: LNT Construction Internal Use


CONSTRUCTION OF MUMBAI-AHMEDABAD HIGH O20361-S-VIA-001-ME-01506
SPEED RAIL
Package No. MAHSR – C – 4 QUALITY MANAGEMENT SYSTEM

METHOD STATEMENT FOR PLATE LOAD TEST


Rev No: 0 Date: 06-01-2021
AT CH. KM-205.447 AS PER JGS 1521-2012

1 INTRODUCTION

The Mumbai – Ahmedabad High Speed Rail (MAHSR) Project is the first High Speed Rail (HSR)

network planned to be constructed in India. The MAHSR Project line connects Mumbai, located in

Maharashtra State with Ahmedabad in Gujarat State, passing through one Union Territory, Dadra and

Nagar Haveli (refer Figure 1). The entire stretch is divided into 8 packages from C1 to C8.

C4 Package of High Speed Rail Project is awarded to L&T Construction. This package consists of four

stations namely, Vapi, Billimora, Surat and Bharuch and other structures viz viaducts, SMD, Ramp,

etc. C4 package starts from Ch. 156.6 km at Zaroli village to Ch. 393.7 km which ends near Vadadora.

It covers approximately 237.1 km in this package. The alignment of the MAHSR C4 package is shown

in Figure 2.

Figure 1 Figure 2
(Complete Alignment of Mumbai- (Package C-4 Location Map)
Ahmedabad High Speed Rail Project)

Sensitivity: LNT Construction Internal Use


CONSTRUCTION OF MUMBAI-AHMEDABAD HIGH O20361-S-VIA-001-ME-01506
SPEED RAIL
Package No. MAHSR – C – 4 QUALITY MANAGEMENT SYSTEM

METHOD STATEMENT FOR PLATE LOAD TEST


Rev No: 0 Date: 06-01-2021
AT CH. KM-205.447 AS PER JGS 1521-2012

2 SCOPE OF THE REPORT

This reports briefly describes the test methodology for carrying out Plate load test to determine the
ultimate bearing capacity and deformation characteristics of the ground based on the relationship
between load applied on the loading plate and the displacement observed. This method statement of
Plate load test as per JGS 1521-2012 is applicable for the test location at Ch km. 205.447. In addition,
for the specific locations and drawings providing the details of location, Test levels, Ultimate Bearing
Capacity (UBC) etc. are attached for Engineer’s approval as Annexure IV -Plate Load test drawings.

3 CONTRACTUAL REQUIREMENTS

The following clauses are considered for preparation of this method statement,
Employer’ Requirements (Design Requirements and Criteria)
• Cl 1.1.4 of Section VI-2 Division 02000: Viaduct and Bridges (followed as per Addendum 22)
• Cl 1.5.3 of Section VI-2 Division 02000: Viaduct and Bridges (followed as per Addendum 22)
• Cl 2.4.1 of Section VI-2 Division 02000: Viaduct and Bridges

Employer’ Requirements (Technical Specifications)


• Cl 2.1.6 of Section VI-3 Division 02000: Viaduct and Bridges.
• Cl 2.3 (d) of Section VI-3 Division 02000: Viaduct and Bridges.
• Cl 2.3 (f) of Section VI-3 Division 02000: Viaduct and Bridges (followed as per Addendum 22)
• Cl 2.5 of Section VI-3 Division 02000: Viaduct and Bridges.

4 REFERENCES

• JGS 1521-2012 – Japanese Geotechnical Society Standard – Method for Plate Load Test
• IS:1888 – 1982: Reaffirmed-2016) Method of Load test on Soils
• Bidding Documents-Part 2 – Section VI-3 Employer’s Requirements (Technical Specifications)
• Bidding Documents-Part 2 – Section VI-3 Employer’s Requirements (Design requirements and
Criteria)
• Addendums No 1 to 26 of Bidding Documents

Sensitivity: LNT Construction Internal Use


CONSTRUCTION OF MUMBAI-AHMEDABAD HIGH O20361-S-VIA-001-ME-01506
SPEED RAIL
Package No. MAHSR – C – 4 QUALITY MANAGEMENT SYSTEM

METHOD STATEMENT FOR PLATE LOAD TEST


Rev No: 0 Date: 06-01-2021
AT CH. KM-205.447 AS PER JGS 1521-2012

5 RESOURCES

5.1 Equipment’s for Setting up test Arrangement

• Excavator
• Dewatering Pump 5hp
• Tyre mounted Hydraulic Crane (Capacity as required)
• Level measuring Instrument
• Rock breakers

5.2 Manpower

As per Employer’s Requirements, the qualifications of the following personnel to be adhered to Clause
1.5.3.

• Construction Manager
• Engineering Manager (Geotechnical)
• Geotechnical Engineer
• Safety Engineer
• Surveyor

Sensitivity: LNT Construction Internal Use


CONSTRUCTION OF MUMBAI-AHMEDABAD HIGH O20361-S-VIA-001-ME-01506
SPEED RAIL
Package No. MAHSR – C – 4 QUALITY MANAGEMENT SYSTEM

METHOD STATEMENT FOR PLATE LOAD TEST


Rev No: 0 Date: 06-01-2021
AT CH. KM-205.447 AS PER JGS 1521-2012

6 AUTHORITY AND RESPONSIBILITY

Table 1 Authority & Responsibility for conducting Plate load test


Department/ Role & Responsibility
Position
• Overall management of the Plate load test team
• Draw the resources for the requirement for the assigned area/ scope of work
Construction Assuring that all facilities, equipment, and personnel are adequate to perform the
Manager required work, and those personnel should be trained and qualified to perform
their assigned jobs
• Review and control of the quality assurance and test procedures
• Overall management of testing and provide technical support t
Engineering
Manager • Interact with client representative, HQ design team and site team for geotechnical
related clearances
(Geotechnical)
• Prepare work schedule base on test schedule and monitor the same
• Ensure requirements as per technical specification.
Geotechnical • Carry out the field activities as per approved work methods with the required
Engineer Quality and EHS
• Report preparation and submission of document.
Safety
• Ensure for safe work at site.
Engineer • Ensure the work as per approved work method
• Establish control points and marking co-ordinates at test location.
Surveyor • Responsible for the survey activities and maintain records.
• Directly supervises the work activity on the site and has full control over the use
of the workers and equipment.
Foreman • Ensures that the work is carried out in all full compliance with the approved method
statement, and in a manner that confirms to the safety requirements. Reports to the
engineer when the works is complete and ready for inspection.

Sensitivity: LNT Construction Internal Use


CONSTRUCTION OF MUMBAI-AHMEDABAD HIGH O20361-S-VIA-001-ME-01506
SPEED RAIL
Package No. MAHSR – C – 4 QUALITY MANAGEMENT SYSTEM

METHOD STATEMENT FOR PLATE LOAD TEST


Rev No: 0 Date: 06-01-2021
AT CH. KM-205.447 AS PER JGS 1521-2012

CONSTRUCTION
MANAGER

ENGINEERING SAFETY
MANAGER ENGINEER

GEOTECHNICAL
SURVEYOR FOREMAN
ENGINEER

Figure 3
(Functional Organization Chart for Plate load test)

Sensitivity: LNT Construction Internal Use


CONSTRUCTION OF MUMBAI-AHMEDABAD HIGH O20361-S-VIA-001-ME-01506
SPEED RAIL
Package No. MAHSR – C – 4 QUALITY MANAGEMENT SYSTEM

METHOD STATEMENT FOR PLATE LOAD TEST


Rev No: 0 Date: 06-01-2021
AT CH. KM-205.447 AS PER JGS 1521-2012

7 APPARATUS REQUIRED

All the apparatus used for conducting plate load test shall conform to JGS 1521-2012. The major
apparatus required for conducting plate load test as per JGS 1521-2012 is shown in Figure 4. The
description of the apparatus as per JGS 1521-2012 is explained in the next section.

Figure 4
(Typical Test set-up for Plate load test with Apparatus)
7.1 Loading Plate

Loading plate of minimum 300 mm diameter and minimum 25 mm thickness as per Clause 4.2 of JGS
1521-2012. However, the contractor is proposing the loading plate of 300 mm diameter with 25 mm
thickness for conducting plate load test. The loading plate is provided with reinforcing ribs as per JGS
1521-2012.

7.2 Hydraulic Jack

The jack is the device that gives the actual load applied to the loading plate. In general, the jack loading
capacity should be 1.2 times the maximum test load as per Clause 4.3.2 of JGS 1521-2012. The jack
shall also be capable of smooth loading and unloading, and it shall be able to maintain a specified load
during testing.

Sensitivity: LNT Construction Internal Use


CONSTRUCTION OF MUMBAI-AHMEDABAD HIGH O20361-S-VIA-001-ME-01506
SPEED RAIL
Package No. MAHSR – C – 4 QUALITY MANAGEMENT SYSTEM

METHOD STATEMENT FOR PLATE LOAD TEST


Rev No: 0 Date: 06-01-2021
AT CH. KM-205.447 AS PER JGS 1521-2012

Figure 5
(Typical Set-up of Hydraulic Jack along with Loading plate and dial gauges)

7.3 Support post

The support post is the component that transmits the load produced by the jack against the reaction
members (Excavator 210) to the loading plate. It shall have sufficient load-bearing capacity and
stiffness with respect to the maximum test load. The support post may be provided depending up on the
site requirement.

7.4 Reaction force components

The reaction force for jacks shall be supported by reaction force components. When the test is
conducted outdoors, anchors or an actual load shall be used to form the reaction structure. The reaction
force components by actual load shall be sufficiently stable with respect to movement and toppling
under such a load. Excavator 210 is used as the actual load and its capacity shall be at least 1.2 times
the maximum test load as per Clause 4.3.5 of JGS 1521-2012. Reaction is offered through stand in
excavator.

As per clause 5.3.5 of JGS 1521-2012 and as per site conditions, if the real load pedestal cannot be
placed at a distance of five or more times the diameter of the loading plate from the center of the loading
plate, displacement gauges should ideally be placed near the loading plate and the reference point to
enable the status of the ground shall also be checked. As the proposed plate load test is being carried
out on rock surface for which no disturbance or movement of ground is anticipated the above method
is proposed at this particular location at Ch. Km -205.447.

Sensitivity: LNT Construction Internal Use


CONSTRUCTION OF MUMBAI-AHMEDABAD HIGH O20361-S-VIA-001-ME-01506
SPEED RAIL
Package No. MAHSR – C – 4 QUALITY MANAGEMENT SYSTEM

METHOD STATEMENT FOR PLATE LOAD TEST


Rev No: 0 Date: 06-01-2021
AT CH. KM-205.447 AS PER JGS 1521-2012

7.5 Loading/Pressure Gauges

The loading gauge shall have capacity at least equal to the maximum test load. As per Clause 4.4.2 of
JGS 1521-2012, the accuracy of the loading gauge shall be within ± 2.5 % of the maximum test load.
The pressure gauge or loading gauge shall ideally have capacity in the range of 1.2 times to 5 times the
maximum test load. Either load cell or proving ring or the like is often used a loading gauge. The loading
gauge or pressure gauge shall be capable of measuring with a precision of 1%.

Figure 6
(Typical Pressure/Loading gauge)
7.6 Displacement Gauges

Minimum four number of dial gauges shall be used as displacement gauges installed at regular intervals
around the edge of the plate. Displacement gauges shall have sufficient range with respect to the
anticipated displacement in response to the maximum test load. It shall have a precision that enables
readings to be displayed down to 0.01 mm or less. It shall be able to withstand vibration and
temperature variation, etc. The displacement gauges shall ideally have a range of at least 30 mm as per
Clause 4.4.3 of JGS 1521-2012.

Sensitivity: LNT Construction Internal Use


CONSTRUCTION OF MUMBAI-AHMEDABAD HIGH O20361-S-VIA-001-ME-01506
SPEED RAIL
Package No. MAHSR – C – 4 QUALITY MANAGEMENT SYSTEM

METHOD STATEMENT FOR PLATE LOAD TEST


Rev No: 0 Date: 06-01-2021
AT CH. KM-205.447 AS PER JGS 1521-2012

Figure 7
(Typical Dial gauge with stand)
7.7 Stopwatch

The stopwatch shall be capable of measuring the duration at the test.

8 TEST DETAILS

8.1 Test location

The test shall be conducted at chainage km 205.447 km at an elevation of proposed foundation level of
the pier.
8.2 Test load/Pressure

The maximum test load that is applied is equal to the ultimate bearing capacity required for the
particular test location. The UBC is checked for 1500 kN/m2 at this test location as per Standard
drawings of Employer’s Requirements.

8.3 Size and shape of loading plate

The proposed loading plate size is 300 mm diameter with 25 mm thickness. The loading plate is
provided with reinforcing ribs as per JGS 1521-2012.

8.4 Loading method

The proposed loading platform for conducting plate load test is Excavator 210 to provide reaction to
the hydraulic jack.

Sensitivity: LNT Construction Internal Use


CONSTRUCTION OF MUMBAI-AHMEDABAD HIGH O20361-S-VIA-001-ME-01506
SPEED RAIL
Package No. MAHSR – C – 4 QUALITY MANAGEMENT SYSTEM

METHOD STATEMENT FOR PLATE LOAD TEST


Rev No: 0 Date: 06-01-2021
AT CH. KM-205.447 AS PER JGS 1521-2012

9 TEST PROCEDURE

9.1 General

For conducting plate load test, the loading plate shall be placed at the foundation level and the load is
applied by means of hydraulic jack. The reaction to the jack is provided by the Excavator 210. The
Excavator 210 (as loading platform) is used to provide reaction. The settlement of the plate is measured
by four dial gauges which are placed at the ends of the plate. The dial gauges are fixed to the reference
beam which remain undisturbed during the test. The generalized procedure for conducting plate load
test is presented in the flow chart in Figure 8.

Figure 8
(Flowchart for generalized procedure for conducting plate load test)

Sensitivity: LNT Construction Internal Use


CONSTRUCTION OF MUMBAI-AHMEDABAD HIGH O20361-S-VIA-001-ME-01506
SPEED RAIL
Package No. MAHSR – C – 4 QUALITY MANAGEMENT SYSTEM

METHOD STATEMENT FOR PLATE LOAD TEST


Rev No: 0 Date: 06-01-2021
AT CH. KM-205.447 AS PER JGS 1521-2012

9.2 Excavation for test setup

This section describes the process of open excavation for plate load test.
➢ Before the excavation for the plate load test is commenced, the site shall be cleared of
vegetation, brushwood, stumps of trees etc. The working area is thus established on the site and
the levels from nearest benchmark shall be transferred to particular location, establishing
temporary benchmark.
➢ Open excavation method shall be carried out using excavators for soil strata and rock breakers
for rocky strata. Open excavation shall facilitate the conduction of plate load test which is used
to ensure the ultimate bearing capacity.
➢ Detailed site survey shall be conducted to record existing ground level conditions and to mark
the area required and the obstructions. All the required equipment, manpower and supervisory
staff shall be mobilized.
➢ Excavation shall be carried out as per the design profile using Excavators/Rock breakers (if
required). At locations where the water table is above the founding level of excavation,
dewatering shall be carried out. Dewatering shall be carried out according to the scheme suitable
for the existing soil profile, soil strata and discharge. The excavated materials suitable for
backfilling shall be carried out at the designated locations.
➢ Excavation inside/near any part of the existing services, structures shall always be properly
fenced and marked with suitable warning boards or lights. Measures shall be taken to safeguard
the utilities encountered during excavation. Material shall not be stacked near the edge of the
excavation or opening in the ground.
➢ Movement of equipment, trucks, and storage of excavated materials shall be such that it will not
obstruct any construction activities of adjacent structures. Wherever required, safety barriers
during excavation shall be provided.

Sensitivity: LNT Construction Internal Use


CONSTRUCTION OF MUMBAI-AHMEDABAD HIGH O20361-S-VIA-001-ME-01506
SPEED RAIL
Package No. MAHSR – C – 4 QUALITY MANAGEMENT SYSTEM

METHOD STATEMENT FOR PLATE LOAD TEST


Rev No: 0 Date: 06-01-2021
AT CH. KM-205.447 AS PER JGS 1521-2012

Figure 9
(Typical Cross section showing the sloped arrangement to reach test level)
9.2.1 Excavation in Soil

The soil profile as mentioned in the borelog shall be referred for excavation depth. The Borelogs are
attached as Annexure -III and open excavation is possible for shallow depth as per Borelogs. Safe slope
shall be maintained during excavation in soil. Soil properties and layer thickness shall be chosen from
the nearest available bore log.
9.2.2 Excavation in Rock

Rock breakers shall be used for carrying out excavation in rocks. Boulders shall be handled carefully
while disposing the excavated rock mass. Water seepage if any shall be controlled by sump pumping.

9.3 Dewatering

9.3.1 Sump Pumping

This is the most common method of dewatering as gravity is the main playing force.
i. Sump is created in the excavated area into which the surrounding water converges and
accumulates facilitating easy discharge of water through robust solid handling pumps.

Sensitivity: LNT Construction Internal Use


CONSTRUCTION OF MUMBAI-AHMEDABAD HIGH O20361-S-VIA-001-ME-01506
SPEED RAIL
Package No. MAHSR – C – 4 QUALITY MANAGEMENT SYSTEM

METHOD STATEMENT FOR PLATE LOAD TEST


Rev No: 0 Date: 06-01-2021
AT CH. KM-205.447 AS PER JGS 1521-2012

ii. Since the bottom of the sump is situated at a level lower than that of the excavation bottom, it
will abridge the seepage way along which groundwater from outside seeps into the excavation
zone and as a result the exit gradient of the sump bottom will be larger than that on the
excavation surface.
iii. If the excavation area is large, several sumps may be placed along the longer side or simply use
a long narrow sump which is called a ditch. Whereas in our case excavation area for plate load
test is very minimal, dewatering shall be carried out with single sump system. The water
collected in the sump shall be pumped out periodically using submersible pump.

The typical arrangement of sump pumping method is shown in Figure 10.

Figure 10
(Typical arrangement of sump pumping method)
9.4 Detailed Procedure for conducting plate load test

1. The identified test location shall be sealed and barricading to be provided. The test is conducted
at the proposed founding level. To reach the founding level sloped arrangement is made from
the ground level. Safety to be ensured for the slope provided during execution.
2. The surface area of the test ground shall be levelled over an area at least three times the diameter
of the loading plate from the centre of the plate as per Clause 5.2.1 of JGS 1521-2012. A final
levelling operation shall be carried out prior to the test. The bottom of the test location shall be
coinciding with the level of the foundation.
3. If in case water table is above the level of foundation, water level to be lowered. The water level
shall be lowered below the level of foundation.
4. The ground shall be levelled and the loading plate shall be placed over it.

Sensitivity: LNT Construction Internal Use


CONSTRUCTION OF MUMBAI-AHMEDABAD HIGH O20361-S-VIA-001-ME-01506
SPEED RAIL
Package No. MAHSR – C – 4 QUALITY MANAGEMENT SYSTEM

METHOD STATEMENT FOR PLATE LOAD TEST


Rev No: 0 Date: 06-01-2021
AT CH. KM-205.447 AS PER JGS 1521-2012

5. At the proposed test location, stand in Excavator 210 is used as the loading platform.
6. The CG of the loading plate shall coincide with the CG of the Excavator 210 platform.
7. An initial seating pressure of 7 kPa is applied as a preliminary loading to improve the contact
between the ground and the loading plate. The seating pressure is released before starting the
test. In order to increase contact between the loading plate and the test ground, a thin layer of
dry sand may be spread over the test ground.
8. The load for first stage is then placed on plate and settlements are recorded by means of dial
gauges.
9. The load increments shall be one-eighth of the ultimate bearing capacity
10. Displacement measurements at every loading step shall be recorded at 0, 1, 2 and 5 minutes and
thereafter for every 5 minutes up to 30 minutes as per Clause 5.4.4 of JGS 1521-2012.
11. The load at every step during loading is maintained for 30 minutes approximately.
12. After reaching the maximum test load, the unloading shall be carried out in stages with holding
time of 5 minutes for every stage.

9.4.1 In case bearing stratum is Rock

1. During the preparation of test surface, any parts of the rock that have been loosened by
excavation or any damaged rock shall be removed. The surface shall be levelled to eliminate
significant irregularities. The minimum extent to be finished is around 1.5 to 2 times larger than
the diameter of the loading plate as per Clause 5.2.2 of JGS 1521-2012.
2. In order to ensure proper contact between loading plate and test rock surface, a cement paste or
other facing material shall be applied to the test ground before placing the loading plate
3. The load at every step during loading is maintained for 5 minutes approximately instead of 30
minutes.

The loading steps, rate of loading & unloading and holding time for loading & unloading step is
mentioned in the Table 2.

Sensitivity: LNT Construction Internal Use


CONSTRUCTION OF MUMBAI-AHMEDABAD HIGH O20361-S-VIA-001-ME-01506
SPEED RAIL
Package No. MAHSR – C – 4 QUALITY MANAGEMENT SYSTEM

METHOD STATEMENT FOR PLATE LOAD TEST


Rev No: 0 Date: 06-01-2021
AT CH. KM-205.447 AS PER JGS 1521-2012

Table 2 Recommended loading and unloading procedure as per JGS 1521-2012

Number of steps 8 steps


Rate of loading and Soil and soft rock 0.2 MN/m2/min
unloading Hard rock 0.5 MN/m2/min
Holding time for each New loading steps 30 minutes for soil & 5 minutes for rock
loading step Unloading steps 5 minutes

Figure 11
(Typical Loading pattern for loading in stages (JGS 1521-2012))

As indicated in Table 2, the maximum test load is applied in eight stages. The loading pattern is
indicated in the Figure 11. The load increment for every step is presented in Table 3.

Table 3 Load increment to be followed as per JGS 1512-2012


Step number Load Increment Remarks
0 Seating pressure -
1 12.5% -
2 25.0% -
If settlement at 33.3% of UBC exceeds 1% of plate width, it has
- 33.3%
to bring it to the notice of Engineer
3 37.5% -
4 50.0% -
5 67.5% -
6 75.0% -
7 87.5% -
If settlement at UBC exceeds 10% of the plate width. it has to
8 100.0%
bring it to the notice of Engineer

The Plate load test data format is attached as Annexure -I

Sensitivity: LNT Construction Internal Use


CONSTRUCTION OF MUMBAI-AHMEDABAD HIGH O20361-S-VIA-001-ME-01506
SPEED RAIL
Package No. MAHSR – C – 4 QUALITY MANAGEMENT SYSTEM

METHOD STATEMENT FOR PLATE LOAD TEST


Rev No: 0 Date: 06-01-2021
AT CH. KM-205.447 AS PER JGS 1521-2012

10 TEST COMPLETION

As per Cl 5.4.5 of JGS 1521-2012, when one of the following conditions is met, the final unloading
step of the test shall begin and the test shall then be concluded.

1. When the final stage in the set loading pattern has been reached and the prescribed time of load
maintenance has expired.
2. If the displacement suddenly increases drastically and when it becomes difficult to maintain the
load or apply new loading.
3. If cracks appear in the surrounding ground and the loading plate has tilted significantly, or
otherwise if the ground has been judged to have reached the fracture point.

11 INTERPRETATION OF TEST RESULTS

The interpretation of plate load test results based on the recorded data shall be as per clause 6 and 7 of
JGS 1521-2012. A separate report shall be submitted to Engineer after completion of the test.

11.1 Method of processing test results for determining UBC of the ground

Interpretation of test results shall be done as per Clause 6 of JGS 1521-2012. For the determination of
bearing characteristics of ground, loading pressure versus settlement (P v/s S) curves shall be prepared.
As per clause 6.1.3, UBC is taken as the loading pressure corresponding to the failure state of the
ground. If no failure of ground is confirmed even after reaching maximum test load, the maximum test
load is taken as UBC.

If multiple failure states are confirmed, smallest of the loading pressure values shall be taken as the
UBC.

a) Loading pressure at the point at which settlement increases dramatically until it becomes
generally parallel to settlement axis in ‘P v/s S’ curve (Figure 13 curve A).
b) If (a) cannot be clearly determined and as long as the settlement of the plate does not exceed
10% of the plate diameter, UBC shall be interpreted to be the smaller of below
i. Loading pressure at which settlement linearly increases on ‘P v/s S’ curve (Figure 13
curve B)
ii. Loading pressure at which settlement becomes parallel to settlement axis on ‘log P v/s
S’ curve (Figure 14)

Sensitivity: LNT Construction Internal Use


CONSTRUCTION OF MUMBAI-AHMEDABAD HIGH O20361-S-VIA-001-ME-01506
SPEED RAIL
Package No. MAHSR – C – 4 QUALITY MANAGEMENT SYSTEM

METHOD STATEMENT FOR PLATE LOAD TEST


Rev No: 0 Date: 06-01-2021
AT CH. KM-205.447 AS PER JGS 1521-2012

Figure 12: P versus S curve Figure 13: Log P versus S curve

c) If it is difficult to determine either (a) or (b) and it is confirmed that settlement of the plate
exceeds 10% of the plate diameter, loading pressure corresponding to the point at which
settlement is equal to 10% of plate diameter is considered as UBC.
d) If there is a sudden and dramatic change in state of loading plate and surrounding ground and it
begins to be difficult to maintain the load or apply a new staged load, the corresponding loading
pressure is taken as UBC.

12 BACKFILL

1. Material of backfill shall confirm to the provisions of IS 1498:1970 Reaffirmed 2016.


Backfilling shall be done with inorganic materials, obtained from the excavation or borrow pits,
if suitable, and subject to approval by the Engineer.
2. After completion of foundation works and prior to backfilling. All forms, temporary shoring,
timber etc. shall be removed and excavation shall be cleaned of all trash, debris and perishable
materials. Backfilling shall begin only after the approval of Engineer,
3. Backfill shall not be dropped directly upon or against any structure or facility where there is
danger of displacement or damage

Sensitivity: LNT Construction Internal Use


CONSTRUCTION OF MUMBAI-AHMEDABAD HIGH O20361-S-VIA-001-ME-01506
SPEED RAIL
Package No. MAHSR – C – 4 QUALITY MANAGEMENT SYSTEM

METHOD STATEMENT FOR PLATE LOAD TEST


Rev No: 0 Date: 06-01-2021
AT CH. KM-205.447 AS PER JGS 1521-2012

4. On completion of structures, the earth surrounding them shall be accurately finished to line and
grade as shown in the drawings. Finished surface shall be free of irregularities and depressions
and shall be within 50mm of the specified level.

13 MANDATORY SAFETY REQUIREMENTS

• Every workman must be engaged after Screening, Safety induction & medical test.
• Every workman shall be allowed to work with Personal Protective Equipment (safety shoes,
Safety Helmet, Reflective Jackets, hand gloves, nose musk, ear plug, safety goggles).
• Area of work shall be barricaded with Boards with proper anchoring, bolting and weight to be
kept for stability of barricades.
• While planning excavation of test pit, it is important to plan against the following:
o Collapse of the sides,
o Material falling on the people working in the excavation,
o People and vehicles falling into the excavation,
o People being stuck by plant and machinery,
o Access to the excavation,
o Fumes, Toxic gas
o Underground utilities
o Incidents to members of the public.
• Certified crane & vehicle shall only be deployed for the job
• Operator of valid license shall be permitted to operate the crane.
• Proper access and working platform should be provided to reach the work spot.
• Safety warning signs shall be places to provide adequate warning.
• Where natural lighting is not adequate, working light fittings or portable hand-lamps shall be
provided at workplace on the construction site. In the working spot illumination shall be 110
lux.

13.1 Preventive Measures to Control the spread of COVID-19 is attached as Annexure II

Sensitivity: LNT Construction Internal Use


CONSTRUCTION OF MUMBAI-AHMEDABAD HIGH O20361-S-VIA-001-ME-01506
SPEED RAIL
Package No. MAHSR – C – 4 QUALITY MANAGEMENT SYSTEM

METHOD STATEMENT FOR PLATE LOAD TEST


Rev No: 0 Date: 06-01-2021
AT CH. KM-205.447 AS PER JGS 1521-2012

ANNEXURE I – PLATE LOAD TEST DATA FORMAT

Sensitivity: LNT Construction Internal Use


O20361-S-VIA-000-ME-01501
CONSTRUCTION OF MUMBAI-AHMEDABAD HIGH SPEED RAIL
Package No. MAHSR – C – 4 QUALITY MANAGEMENT SYSTEM

METHOD STATEMENT FOR PLATE LOAD TEST AS PER JGS 1521-2012


Rev No: 01 Date: 23-12-2020

PLATE LOAD TEST


Client
Date:
Project
Test no Plate shape
Location Plate size (mm)
Co-ordinates Plate thickness (mm)
Test level (m) Area of plate (mm2)
Water table (m) Least count of Dial gauge
Type of Strata Ram Area (mm2)

Applied Pressure Actual pressure Dial gauge reading (mm) Average Dial gauge Absolute settlement Total settlement
Step no Load (T) Time (min) Remarks
(kg/cm2) below plate (kg/cm2) reading (mm) (mm) (mm)
DG-1 DG-2 DG-3 DG-4
0 0
0
1
2
5
1 10
15
20
25
30
0
1
2
5
2 10
15
20
25
30
0
1
3 2
5
10

Sensitivity: LNT Construction Internal Use


O20361-S-VIA-000-ME-01501
CONSTRUCTION OF MUMBAI-AHMEDABAD HIGH SPEED RAIL
Package No. MAHSR – C – 4 QUALITY MANAGEMENT SYSTEM

METHOD STATEMENT FOR PLATE LOAD TEST AS PER JGS 1521-2012


Rev No: 01 Date: 23-12-2020

15
20
25
30
0
1
2
5
4 10
15
20
25
30
0
1
2
5
5 10
15
20
25
30
0
1
2
5
6 10
15
20
25
30
0
1
2
5
7 10
15
20
25
30
0
8
1

Sensitivity: LNT Construction Internal Use


O20361-S-VIA-000-ME-01501
CONSTRUCTION OF MUMBAI-AHMEDABAD HIGH SPEED RAIL
Package No. MAHSR – C – 4 QUALITY MANAGEMENT SYSTEM

METHOD STATEMENT FOR PLATE LOAD TEST AS PER JGS 1521-2012


Rev No: 01 Date: 23-12-2020

2
5
10
15
20
25
30

Sensitivity: LNT Construction Internal Use


CONSTRUCTION OF MUMBAI-AHMEDABAD HIGH O20361-S-VIA-000-ME-01501
SPEED RAIL
Package No. MAHSR – C – 4 QUALITY MANAGEMENT SYSTEM

METHOD STATEMENT FOR PLATE LOAD TEST


Rev No: 01 Date: 26-12-2020
AT CH. KM 205.447 AS PER JGS 1521-2012

ANNEXURE II – PREVENTIVE MEASURES TO CONTROL SPREAD OF COVID-19

Sensitivity: LNT Construction Internal Use


CONSTRUCTION OF MUMBAI-AHMEDABAD HIGH O20361-S-VIA-000-ME-01501
SPEED RAIL
Package No. MAHSR – C – 4 QUALITY MANAGEMENT SYSTEM

METHOD STATEMENT FOR PLATE LOAD TEST


Rev No: 01 Date: 26-12-2020
AT CH. KM 205.447 AS PER JGS 1521-2012

COVID 19– SOP CHECKLIST

Name of the Project : MAHSR C-4


Location :
Date :
Yes No NA Remarks
S. No Details

1 Barricading done for the work area with one entry/exit point
Workers transported from camp to work site in disinfected company
2
exclusive vehicle
3 Workers only from Labour camp deployed for work

4 Photo Identity card have been issued to all workers

5 Thermal scanning done for all Workers/Supervisors/Engineers

6 Soap/Hand sanitizers available at entry/exit point


7 Designated area and timing allocated to labours for food consumption.
8 (i) Trash bin available to dispose food waste
8 (ii) Trash bin cleaned frequently

9 Sanitization with disinfectant done for work sites, offices on a daily basis

10 Ambulance available in site for 24 X 7

11 Medical check-up for all people present in site at least once in a week

List of nearby hospitals identified to treat COVID 19 patients should be


12
displayed at the entry / exit points
13 Strict ban on non-essential visitors to work site
All vehicles and equipment’s present in site are being sanitized by
14
spraying disinfectant
15 Hard copy of SOP displayed at the entry/exit point
16 Posters with Do’s & Don’ts during this situation displayed in worksite
Tool box meeting to be done covering general guidelines for workers
such as
(a)Wearing of face cover/mask (b) Avoid shaking of hands (c) consumption
of Liquor, Gutkha, Tambaku, Paan etc is strictly prohibited (d) Spitting in
17 public places is prohibited (e) gathering in groups to be avoided (f) clean
their hands with soap/hand sanitizer frequently (g) Avoid touching mouth,
eyes and nose (h)Avoid sharing of food, water, utensils, mobile phones etc
(i) Maintain social distancing while travelling inside the vehicle (j) maintain
safe distance from each other

Section In-charge EHS Personal

Project Manager Time Office


Representative

Sensitivity: LNT Construction Internal Use


CONSTRUCTION OF MUMBAI-AHMEDABAD HIGH O20361-S-VIA-000-ME-01501
SPEED RAIL
Package No. MAHSR – C – 4 QUALITY MANAGEMENT SYSTEM

METHOD STATEMENT FOR PLATE LOAD TEST


Rev No: 01 Date: 26-12-2020
AT CH. KM 205.447 AS PER JGS 1521-2012

ANNEXURE III – BORELOGS

Sensitivity: LNT Construction Internal Use


MUMBAI AHMEDABAD HIGH SPEED
RAIL PROJECT PACKAGE NO. MAHSR-C-4

BORELOG

PROJECT : MUMBAI-AHMEDABAD HIGH SPEED RAIL PROJECTPACKAGE NO. - MAHSR -C-4


Coordinate :
Chainage:
Boring method : ROTARY DRILLING WITH MUD CIRCULATION N: 2286103.415 BH No. BH - 514
205.400 Km
E: 290377.863

Boring diameter : SX upto 3.00mtrs, Nx upto 40.00mtrs. Section : 1 Sheet : 1/5

Orientation :
Casing diameter : SX upto 3.00mtrs EGL : (+) 17.04 m
Vertical

Ground Water level Date Commenced: 17.12.2020


Boring equipment : HYDRAULIC CORE DRILLING MACHINE - MI 3-2422
: (+) 15.95 m
Date Completed : 20.12.2020
Samples and In-situ test
Water Casing
Sample Type & SPT N Date &
TCR RQD Depth depth Depth From EGL
Value Depth, Description of Strata
RL (m) Depth(m) % % (Level,m) (Level,m) (m)
(Level,m)
N1 N2 N3 N*

17.04 GL 17.12.20
(+)17.04

16.04 1.00 1 1 2 3

Soft to Stiff Brownish Buff silty CLAY

15.04 2.00 4 7 4 13

14.04 3.00 9 8 8 16 (+)14.04


SX 3.50
13.54 3.50

13.04 4.00 Core 80 Nil

Highly Weathered to Moderately


Weathered, Brownish Buff, Very weak,
12.04 5.00 Core 56 14 18.12.20 Volcanic BRECCIA
(+)12.04

11.04 6.00 Core 74 15 6.00

Moderately Weathered, Brownish grey,


Moderately strong, Volcanic BRECCIA

9.54 7.50 Core 90 34

7.50
Remarks :* Final SPT N value DS - Disturbed Samples 3 Nos
Bore hole terminated at 40.00 mtrs
UDS - Undisturded Samples

#
MUMBAI AHMEDABAD HIGH SPEED
RAIL PROJECT PACKAGE NO. MAHSR-C-4

BORELOG

PROJECT : MUMBAI-AHMEDABAD HIGH SPEED RAIL PROJECTPACKAGE NO. - MAHSR -C-4


Coordinate :
Chainage:
Boring method : ROTARY DRILLING WITH MUD CIRCULATION N: 2286103.415 BH No. BH - 514
205.400 Km
E: 290377.863

Boring diameter : SX upto 3.00mtrs, Nx upto 40.00mtrs. Section : 1 Sheet : 2/5

Orientation :
Casing diameter : SX upto 3.00mtrs EGL : (+) 17.04 m
Vertical

Ground Water level Date Commenced: 17.12.2020


Boring equipment : HYDRAULIC CORE DRILLING MACHINE - MI 3-2422
: (+) 15.95 m
Date Completed : 20.12.2020
Samples and In-situ test
Water Casing
Sample Type & SPT N Date &
TCR RQD Depth depth Depth From EGL
Value Depth, Description of Strata
RL (m) Depth(m) % % (Level,m) (Level,m) (m)
(Level,m)
N1 N2 N3 N*

8.04 9.00 Core 97 55

6.54 10.50 Core 93 61

Slightly Weathered, Brownish grey,


Moderately strong, Volcanic BRECCIA

5.04 12.00 Core 89 63

3.54 13.50 Core 100 60 13.50

2.54 14.50 Core 91 30 Moderately Weathered, Brownish grey,


Moderately strong, Volcanic BRECCIA

1.54 15.50 Core 89 29 15.50

Highly Weathered to Moderately


Weathered, Brownish Buff, Very weak,
Volcanic BRECCIA
16.00
Remarks :* Final SPT N value DS - Disturbed Samples 3 Nos
Bore hole terminated at 40.00 mtrs
UDS - Undisturded Samples

#
MUMBAI AHMEDABAD HIGH SPEED
RAIL PROJECT PACKAGE NO. MAHSR-C-4

BORELOG

PROJECT : MUMBAI-AHMEDABAD HIGH SPEED RAIL PROJECTPACKAGE NO. - MAHSR -C-4


Coordinate :
Chainage:
Boring method : ROTARY DRILLING WITH MUD CIRCULATION N: 2286103.415 BH No. BH - 514
205.400 Km
E: 290377.863

Boring diameter : SX upto 3.00mtrs, Nx upto 40.00mtrs. Section : 1 Sheet : 3/5

Orientation :
Casing diameter : SX upto 3.00mtrs EGL : (+) 17.04 m
Vertical

Ground Water level Date Commenced: 17.12.2020


Boring equipment : HYDRAULIC CORE DRILLING MACHINE - MI 3-2422
: (+) 15.95 m
Date Completed : 20.12.2020
Samples and In-situ test
Water Casing
Sample Type & SPT N Date &
TCR RQD Depth depth Depth From EGL
Value Depth, Description of Strata
RL (m) Depth(m) % % (Level,m) (Level,m) (m)
(Level,m)
N1 N2 N3 N*

0.04 17.00 Core 100 30

Slightly Weathered, Brownish grey,


Moderately strong, Volcanic BRECCIA
-1.47 18.50 Core 100 45

-2.97 20.00 Core 100 25 19.12.20 20.00


(-)2.97

-4.47 21.50 Core 73 13

Moderately Weathered, Brownish grey,


Moderately strong, Volcanic BRECCIA

-5.97 23.00 Core 100 8

-7.47 24.50 Core 100 27 24.50


Remarks :* Final SPT N value DS - Disturbed Samples 3 Nos
Bore hole terminated at 40.00 mtrs
UDS - Undisturded Samples

#
MUMBAI AHMEDABAD HIGH SPEED
RAIL PROJECT PACKAGE NO. MAHSR-C-4

BORELOG

PROJECT : MUMBAI-AHMEDABAD HIGH SPEED RAIL PROJECTPACKAGE NO. - MAHSR -C-4


Coordinate :
Chainage:
Boring method : ROTARY DRILLING WITH MUD CIRCULATION N: 2286103.415 BH No. BH - 514
205.400 Km
E: 290377.863

Boring diameter : SX upto 3.00mtrs, Nx upto 40.00mtrs. Section : 1 Sheet : 4/5

Orientation :
Casing diameter : SX upto 3.00mtrs EGL : (+) 17.04 m
Vertical

Ground Water level Date Commenced: 17.12.2020


Boring equipment : HYDRAULIC CORE DRILLING MACHINE - MI 3-2422
: (+) 15.95 m
Date Completed : 20.12.2020
Samples and In-situ test
Water Casing
Sample Type & SPT N Date &
TCR RQD Depth depth Depth From EGL
Value Depth, Description of Strata
RL (m) Depth(m) % % (Level,m) (Level,m) (m)
(Level,m)
N1 N2 N3 N*

Slightly Weathered, Brownish grey,


Strong, Volcanic BRECCIA

-8.97 26.00 Core 100 37 26.00

Moderately Weathered, Brownish grey,


Moderately strong, Volcanic BRECCIA

-10.47 27.50 Core 100 41 27.50

Slightly Weathered, Brownish grey,


Strong, Volcanic BRECCIA

-11.97 29.00 Core 100 18 29.00

Slightly Weathered, Brownish grey,


Strong, Volcanic BRECCIA

-13.47 30.50 Core 97 36 30.50

Slightly Weathered, Brownish grey,


Strong, Volcanic BRECCIA

-14.97 32.00 Core 87 69 32.00

Remarks :* Final SPT N value DS - Disturbed Samples 3 Nos


Bore hole terminated at 40.00 mtrs
UDS - Undisturded Samples

#
MUMBAI AHMEDABAD HIGH SPEED
RAIL PROJECT PACKAGE NO. MAHSR-C-4

BORELOG

PROJECT : MUMBAI-AHMEDABAD HIGH SPEED RAIL PROJECTPACKAGE NO. - MAHSR -C-4


Coordinate :
Chainage:
Boring method : ROTARY DRILLING WITH MUD CIRCULATION N: 2286103.415 BH No. BH - 514
205.400 Km
E: 290377.863

Boring diameter : SX upto 3.00mtrs, Nx upto 40.00mtrs. Section : 1 Sheet : 5/5

Orientation :
Casing diameter : SX upto 3.00mtrs EGL : (+) 17.04 m
Vertical

Ground Water level Date Commenced: 17.12.2020


Boring equipment : HYDRAULIC CORE DRILLING MACHINE - MI 3-2422
: (+) 15.95 m
Date Completed : 20.12.2020
Samples and In-situ test
Water Casing
Sample Type & SPT N Date &
TCR RQD Depth depth Depth From EGL
Value Depth, Description of Strata
RL (m) Depth(m) % % (Level,m) (Level,m) (m)
(Level,m)
N1 N2 N3 N*

Moderately Weathered, Brownish grey,


Moderately strong, BASALT
-16.47 33.50 Core 100 78 20.12.20 33.50
(-)16.47

Fresh, Strong, Discloured BASALT

-17.97 35.00 Core 79 53 35.00

-19.47 36.50 Core 100 73

Fresh, Strong, Discloured BASALT

-20.97 38.00 Core 87 52

-22.47 39.50 Core 100 52

-22.97 40.00 Core 100 86 40.00

Remarks :* Final SPT N value DS - Disturbed Samples 3 Nos


Bore hole terminated at 40.00mtrs
UDS - Undisturded Samples

#
MUMBAI AHMEDABAD HIGH SPEED RAIL PROJECT
PACKAGE NO. MAHSR-C-4

FIELD DRILL LOG

Project : HSR Project Coordinates: N: 2286103.415 E: 290377.863 Bearing of hole Drill No.& Type Starting Date: 12/17/2020

BH No: BH-514 EGL: (+)17.035 m Size of hole NX Pump No & Type Completion Date: 12/20/2020

Location: CH 205.400 KM Collar elevation Ground water level (+) 15.95 m Pressure Used Drilling Agency
Length of Core Pieces Percentage Drill
Time Depth Drilled (m) Total Penetration Colour of
Borehole Recovered Total of Core RQD Fracture water
Date Depth Rate Return Core Nos. Structural Conditions Remarks
ID Recovery (cm) Recovery( (%) Index loss
Drilled (m) (mm/min) water
From To From To < 10 cm 10 -25 cm >25 cm %) (%)

17-12-2020 3:36 1:12 3.50 4.00 0.50 40 40 80 0 9 Color less Nil 1 to 6 Highy Fractured, Closely
spaced joints with slickenside
23.00 0.00 4.00 5.00 1.00 42 14 56 56 14 9 16.67 " " 7 to 12 soft gauge matrix infilling
18-12-2020 0.45 1.30 5.00 6.00 1.00 59 15 74 74 15 6 22.22 " " 13-16 Dripping

Horizantal to subhorizantal
2.15 3.20 6.00 7.50 1.50 84 51 135 90 34 8 23.08 " " 17 -29
open continues planar rough

7.00 8.05 7.50 9.00 1.50 63 82 145 97 55 8 23.08 " Partial 30-38
8.30 9.10 9.00 10.50 1.50 47 35 57 139 93 61 5 37.50 " " 39-44 Horizantal to subhorizantal
open continuous, Widely
10.10 10.55 10.50 12.00 1.50 40 38 56 134 89 63 4 33.33 " " 45-50 Spaced Joints planar rough
11.15 11.50 12.00 13.50 1.50 60 33 57 150 100 60 6 42.85 " " 51-58
Closely Spaced Joints with
12.15 12.55 13.50 14.60 1.10 67 33 100 91 30 7 27.50 " 100% 59-65 Clay and Iron Oxide Infilling
Planar Rough with
13.40 14.40 14.60 15.50 0.90 54 26 80 89 29 5 15.00 " " 66-68
Slickenslide Soft Gague,

16.40 17.45 15.50 17.00 1.50 105 18 27 150 100 30 9 23.07 " " 69-77
Fractured and discoloured
random set of joints
18.40 19.40 17.00 18.50 1.50 83 37 30 150 100 45 5 25.00 " " 78-84
22.10 23.35 18.50 20.00 1.50 113 37 150 100 25 10 17.65 " " 85-99
Sub horizantal/ two sets of
joints infilled with Iron stain
19-12-2020 1.07 3.00 20.00 21.50 1.50 90 20 110 73 13 11 13.27 " " 100-113
Moderately widely Spaced
Plannar Rough dry
Two set of joint infilled with
4.25 5.40 21.5 23 1.50 138 12 150 100 8 11 20.00 " " 114-125 soft gauge and iron stained
and Calcite
BH - 514 Two set of joint with Calcite
8.30 10.50 23 24.5 1.50 109 15 26 150 100 27 5 10.71 " " 126-131
and Iron oxide infilling
Discoloured planar smooth
11.20 13.25 24.5 26 1.50 94 30 26 150 100 37 9 12.00 " " 132-142
tight joint continuously
Rough undulating filled with
14.10 15.42 26 27.5 1.50 89 35 26 150 100 41 8 16.30 " " 143-152 silty clay and iron oxide
discoloured
Rough undulating strong
calcite infilling joint or jointly,
16.05 17.30 27.5 29 1.50 123 27 150 100 18 10 17.65 " " 153-164
discoloured, Dry ground water
condition
Strong sub horizontal
steppped three set of joint
Rough undulating strong
18.20 19.55 29 30.5 1.50 91 54 145 97 36 9 15.79 White " 165-174
calcite infilling joint or jointly,
discoloured, Dry ground water
condition
Horizontal joint plane and
rough with lakite and iron
21.25 22.45 30.5 32 1.50 27 54 49 130 87 69 7 18.75 " " 175-180
stained tight continues one set
of joint

#
MUMBAI AHMEDABAD HIGH SPEED RAIL PROJECT
PACKAGE NO. MAHSR-C-4

FIELD DRILL LOG

Project : HSR Project Coordinates: N: 2286103.415 E: 290377.863 Bearing of hole Drill No.& Type Starting Date: 12/17/2020

BH No: BH-514 EGL: (+)17.035 m Size of hole NX Pump No & Type Completion Date: 12/20/2020

Location: CH 205.400 KM Collar elevation Ground water level (+) 15.95 m Pressure Used Drilling Agency
Length of Core Pieces Percentage Drill
Time Depth Drilled (m) Total Penetration Colour of
Borehole Recovered Total of Core RQD Fracture water
Date Depth Rate Return Core Nos. Structural Conditions Remarks
ID Recovery (cm) Recovery( (%) Index loss
Drilled (m) (mm/min) water
From To From To < 10 cm 10 -25 cm >25 cm %) (%)
strong sub horizontal joints
23.40 0.30 32 33.5 1.50 33 30 87 150 100 78 9 30.00 " " 181-189
with micro cloan infilling
Planar rough open with Iron
20-12-2020 1.20 2.25 33.5 35 1.50 39 79 118 79 53 7 23.08 " " 190-196 stained and Calcite porphyritic
flow opaque
3.20 4.25 35 36.5 1.50 41 69 40 150 100 73 6 23.08 " " 197-203
6.00 7.15 36.5 38 1.50 75 19 36 130 87 37 5 20.00 Color less " 204-213
Planar rough Tight Joint
10.10 11.00 38 39.5 1.50 72 37 41 150 100 52 6 30.00 " " 214-223
11.30 12:00 39.5 40 0.50 7 43 50 100 86 5 16.67 " " 224-225

#
MUMBAI AHMEDABAD HIGH SPEED
RAIL PROJECT PACKAGE NO. MAHSR-C-4

BORELOG

PROJECT : MUMBAI-AHMEDABAD HIGH SPEED RAIL PROJECTPACKAGE NO. - MAHSR -C-4


Coordinate :
Chainage: 205.5
Boring method : ROTARY DRILLING WITH MUD CIRCULATION N: 2286201.502 BH No: BH- 515
Km
E: 290397.331

Boring diameter : SX upto 7.00mtrs, Nx upto 33.00mtrs. Section : 1 Sheet : 1/4

Orientation :
Casing diameter : SX upto 3.00mtrs, NX upto 7.00 mtrs EGL : (+) 20.720 m
Vertical

Ground Water Date Commenced: 14.12.20


Boring equipment : HYDRAULIC CORE DRILLING MACHINE - MI 3-2422
level : (+) 16.51 m
Date Completed : 17.12.20
Samples and In-situ test
Water Casing
Sample Type & SPT N Date &
TCR RQD Depth depth Depth From EGL
Value Depth, Description of Strata
RL (m) Depth(m) % % (Level,m) (Level,m) (m)
(Level,m)
N1 N2 N3 N*

20.72 GL 14.12.20
(+)20.72

19.72 1.00 2 4 5 9

18.72 2.00 3 7 9 16

Stiff to Very stiff, Brownish black silty


17.72 3.00 4 7 9 16 CLAY with traces of gravels

SX
(+)17.72

16.72 4.00 UDS

(+)16.51m
15.72 5.00 2 4 5 9

6.00
14.72 6.00 12 22 for 8 cm N>100
N>100

Very dense, Brownish black clayey


SAND with traces of gravels

13.72 7.00 Core 57 30 NX 15.12.20 7.11


(+)13.72 (+)13.72

Highly Weathered, Buffish brown,


Weak, TUFFACEOUS BRECCIA

Remarks :* Final SPT N value DS - Disturbed Samples 6 Nos


Bore hole terminated at 33.00 mtrs
UDS - Undisturded Samples 1 Nos
MUMBAI AHMEDABAD HIGH SPEED
RAIL PROJECT PACKAGE NO. MAHSR-C-4

BORELOG

PROJECT : MUMBAI-AHMEDABAD HIGH SPEED RAIL PROJECTPACKAGE NO. - MAHSR -C-4


Coordinate :
Chainage:
Boring method : ROTARY DRILLING WITH MUD CIRCULATION N: 2286201.502 BH No: BH- 515
205.5 KM
E: 290397.331

Boring diameter : SX upto 7.00mtrs, Nx upto 33.00mtrs. Section : 1 Sheet : 2/4

Orientation :
Casing diameter : SX upto 3.00mtrs, NX upto 7.00 mtrs EGL : (+) 20.720 m
Vertical

Ground Water Date Commenced: 14.12.20


Boring equipment : HYDRAULIC CORE DRILLING MACHINE - MI 3-2422
level : (+) 16.51 m
Date Completed : 17.12.20
Samples and In-situ test
Water Casing
Sample Type & SPT N Date &
TCR RQD Depth depth Depth From EGL
Value Depth, Description of Strata
RL (m) Depth(m) % % (Level,m) (Level,m) (m)
(Level,m)
N1 N2 N3 N*

12.22 8.50 Core 60 Nil Highly Weathered, buffish brown,


Weak,TUFFACEOUS BRECCIA

11.72 9.00 Core 97 70 9.00

10.22 10.50 Core 88 69 Moderately weathered,buffish brown,


Moderately weak, TUFFCEOUS
BRECCIA

8.72 12.00 Core 98 72 12.00

Moderately weathered to Highly


Weathered,Moderately weak

7.22 13.50 Core 91 30 13.50

Highly Weathered,Very weak, FELSIC


BRECCIA

5.72 15.00 Core 100 21 15.00

Moderately weathered, Moderately


strong,FELSIC BRECCIA

Remarks :* Final SPT N value DS - Disturbed Samples 6 Nos


Bore hole terminated at 33.00 mtrs
UDS - Undisturded Samples 1 Nos
MUMBAI AHMEDABAD HIGH SPEED
RAIL PROJECT PACKAGE NO. MAHSR-C-4

BORELOG

PROJECT : MUMBAI-AHMEDABAD HIGH SPEED RAIL PROJECTPACKAGE NO. - MAHSR -C-4


Coordinate :
Chainage:
Boring method : ROTARY DRILLING WITH MUD CIRCULATION N: 2286201.502 BH No: BH- 515
205.5 KM
E: 290397.331

Boring diameter : SX upto 7.00mtrs, Nx upto 33.00mtrs. Section : 1 Sheet : 3/4

Orientation :
Casing diameter : SX upto 3.00mtrs, NX upto 7.00 mtrs EGL : (+) 20.720 m
Vertical

Ground Water Date Commenced: 14.12.20


Boring equipment : HYDRAULIC CORE DRILLING MACHINE - MI 3-2422
level : (+) 16.51 m
Date Completed : 17.12.20
Samples and In-situ test
Water Casing
Sample Type & SPT N Date &
TCR RQD Depth depth Depth From EGL
Value Depth, Description of Strata
RL (m) Depth(m) % % (Level,m) (Level,m) (m)
(Level,m)
N1 N2 N3 N*

4.22 16.50 Core 80 41

2.72 18.00 Core 100 71 16.12.20


(+)2.72

Moderately weathered, Moderately


strong, FELSIC BRECCIA

1.22 19.50 Core 87 67

-0.28 21.00 Core 100 51 21.00

-1.28 22.00 Core 100 45

Highly weathered,Very weak,FELSIC


BRECCIA

-2.78 23.50 Core 100 53

-3.78 24.50 Core 100 100


Remarks :* Final SPT N value DS - Disturbed Samples 6 Nos
Bore hole terminated at 33.00 mtrs
UDS - Undisturded Samples 1 Nos
MUMBAI AHMEDABAD HIGH SPEED
RAIL PROJECT PACKAGE NO. MAHSR-C-4

BORELOG

PROJECT : MUMBAI-AHMEDABAD HIGH SPEED RAIL PROJECTPACKAGE NO. - MAHSR -C-4


Coordinate :
Chainage:
Boring method : ROTARY DRILLING WITH MUD CIRCULATION N: 2286201.502 BH No: BH- 515
205.5 Km
E: 290397.331

Boring diameter : SX upto 7.00mtrs, Nx upto 33.00mtrs. Section : 1 Sheet : 4/4

Orientation :
Casing diameter : SX upto 3.00mtrs, NX upto 7.00 mtrs EGL : (+) 20.720 m
Vertical

Ground Water Date Commenced: 14.12.20


Boring equipment : HYDRAULIC CORE DRILLING MACHINE - MI 3-2422
level : (+) 16.51 m
Date Completed : 17.12.20
Samples and In-situ test
Water Casing
Sample Type & SPT N Date &
TCR RQD Depth depth Depth From EGL
Value Depth, Description of Strata
RL (m) Depth(m) % % (Level,m) (Level,m) (m)
(Level,m)
N1 N2 N3 N*

-4.28 25.00 Core 95 90

Highly weathered,Very weak,FELSIC


BRECCIA

-5.28 26.00 Core 99 99 26.00

-6.28 27.00 Core 77 75

-7.78 28.50 Core 100 96 17.12.20


(-)7.78

Slightly Weathered,Strong FELSIC


BRECCIA

-9.28 30.00 Core 96 73

-10.78 31.50 Core 95 89

-12.28 33.00 33.00


Remarks :* Final SPT N value DS - Disturbed Samples 6 Nos
Bore hole terminated at 33.00 mtrs
UDS - Undisturded Samples 1 Nos
MUMBAI AHMEDABAD HIGH SPEED RAIL PROJECT
PACKAGE NO. MAHSR-C-4

DRILL LOG
Project : MAHSR -C-4 Coordinates: N: 2286201.502; E: 290397.331 Bearing of hole Drill No.& Type Core drilling Starting Date: 12/15/2020
BH No: BH-515 EGL: (+) 20.720 m Size of hole NX Pump No & Type Completion Date: 12/17/2020
Location: CH : 205.500 Km Collar elevation Ground water level (+) 16.51 m Pressure Used Drilling Agency
Borehole ID Time Depth Drilled (m) Length of Core Pieces
Total Total Percentage Penetration Colour of Drill
RQD Fracture Structural
Date Depth Recovery of Core Rate Return water Core Nos. Remarks
From To From To < 10 cm 10 -25 cm >25 cm (%) Index Conditions
Drilled (m) (cm) Recovery (mm/min) water loss (%)

Porphyritic flow
15-12-2020 10.09 11.10 7.00 8.50 1.5 40 45 0 8 24.59 Nil 1-8
texture, Highly
85 57 30 Colour less
Fractured
random set of
11.30 12.10 8.50 9.00 0.5 30 0 0 3 12.52 Nil 9-12
30 60 0 Colour less joints.
Very closely
12.30 13.25 9.00 10.50 1.5 41 41 64 6 27.27 Partial 13-19 spaced
146 97 70 Colour less discontinuities,
continuous open
14.00 15.45 10.50 12.00 1.5 28 12 92 8 14.28 " 20-28 joints,1 to 5mm
132 88 69 Colour less thick wide
Highly
weathered joint
15.47 16.45 12.00 13.50 1.5 39 14 94 14 25.86 " 29 - 35 wall with clay
and iron stain
147 98 72 White filling, dripping
Joints are filled
16.50 18.15 13.50 15.00 1.5 92 0 45 14 17.64 " 36-48 with clay and
137 91 30 White silt, Dripping
BH-515 Vertical set of
joints, iron oxide
18.55 19.45 15.00 16.50 1.5 119 31 0 5 30.00 " 49 - 59 stained,
discoared,
150 100 21 White smooth, planar
22.30 0.08 16.50 18.00 1.5 58 62 0 120 80 41 12 15.30 Colour less " 60 - 70 Vertical set of
8.55 10.00 18.00 19.50 1.5 44 81 25 10 23.07 " 71 -83 joints, iron oxide
16-12-2020 150 100 71 Colour less
stained,
2.20 3.15 19.50 21.00 1.5 30 21 79 130 87 67 8 27.27 Colour less 100 84- 91 discolored,
10.00 10.50 21.00 22.00 1 49 0 51 100 100 51 4 20.00 Colour less 100 92- 93
11.00 12.40 22.00 23.50 1.5 82 31 37 6 15.00 100 94-100 Joints are filled
150 100 45 Colour less
with clay and
14.15 15.50 23.50 24.50 1 47 0 53 100 100 53 3 20.00 Colour less 100 101 - 104
silt and dripping
16.00 16.40 24.50 25.00 0.5 0 0 50 50 100 100 0 12.50 Colour less 100 105
18.55 19.30 25.00 26.00 1 5 0 90 95 95 90 1 28.57 Colour less 100 106 - 107
20.55 21.45 26.00 27.00 1 0 29 70 99 99 99 1 20.00 Colour less 100 108 - 110
27.00 28.50 1.5 4 21 91 100 111 - 112 2 sets of
22.40 23.20 116 77 75 1 37.50 Colour less
joints,Undulatin
17-12-2020 0.23 1.10 28.50 30.00 1.5 6 30 114 150 100 96 5 31.90 Colour less 100 113 - 119
g Rough
10.15 11.10 30.00 31.50 1.5 36 109 145 97 73 7 27.27 Colour less 100 120 - 127
11.30 12.20 31.50 33.00 1.5 9 104 30 143 95 89 11 30.00 Colour less 100 128 - 134
CONSTRUCTION OF MUMBAI-AHMEDABAD HIGH O20361-S-VIA-000-ME-01501
SPEED RAIL
Package No. MAHSR – C – 4 QUALITY MANAGEMENT SYSTEM

METHOD STATEMENT FOR PLATE LOAD TEST


Rev No: 01 Date: 26-12-2020
AT CH. KM 205.447 AS PER JGS 1521-2012

ANNEXURE IV – PLATE LOAD TEST DRAWINGS

Sensitivity: LNT Construction Internal Use

You might also like