This document outlines the tasks and schedule to renovate three rooms - a master toilet and bath, master bedroom, and powder room. It lists the tasks needed for ceilings, walls, floors, lighting, and accessories for each room. The tasks are scheduled over a 20 day period, with numbers indicating the planned working day for each task in each room.
This document outlines the tasks and schedule to renovate three rooms - a master toilet and bath, master bedroom, and powder room. It lists the tasks needed for ceilings, walls, floors, lighting, and accessories for each room. The tasks are scheduled over a 20 day period, with numbers indicating the planned working day for each task in each room.
This document outlines the tasks and schedule to renovate three rooms - a master toilet and bath, master bedroom, and powder room. It lists the tasks needed for ceilings, walls, floors, lighting, and accessories for each room. The tasks are scheduled over a 20 day period, with numbers indicating the planned working day for each task in each room.
No. Working of Day TASK 1 2 3 4 5 6 7 8 9 10 11 CEILING Installation of Purrings Installation of Boards Locate Fixtures Finishing WALL TILES Chipping Works Tiling Works Grout FLOOR TILES Chipping Works Tiling Works Grout LIGHTING FIXTURES & ACCESSORIES Locating Fixtures and Accessories Installation of Lighting Fixtures Installation of Accessories
Master bedroom ( 3 meters x 4 meters )
No. Working of Day TASK 1 2 3 4 5 6 7 8 9 10 11 CEILING Installation of Purrings Installation of Boards Installation of Cornice Locate Fixtures Finishing WALL PAPER Wall Preparation Installation of Wallpaper Finishing ENGINEERED WOOD FLOORING Preparation Installation of Wood Flooring Finishing Lighting Fixtures&Pieces of Furniture Locating Fixtures and Accessories Installation of Lighting Fixtures Pieces of Furniture Assemby
Powder room ( 1.5 meters x 2 meters)
No. Working of Day TASK 1 2 3 4 5 6 7 8 9 10 11 CEILING Installation of Purrings Installation of Boards Locate Fixtures Finishing WALL PAINT Skimcoat Sanding Painting FLOOR TILES Chipping Works Tiling Works Grout LIGHTING FIXTURES & ACCESSORIES Locating Fixtures and Accessories Installation of Lighting Fixtures Installation of Accessories by 3 meters) No. Working of Days 12 13 14 15 16 17 18 19 20
meters ) No. Working of Days 12 13 14 15 16 17 18 19 20 meters) No. Working of Days 12 13 14 15 16 17 18 19 20