You are on page 1of 1

AIN TSILA DEVELOPMENT PROJECT

Ain Tsila export condensate pipeline Part-2

STATUS OF FINAL CONSTRUCTION DOSSIER HANDOVER

ACTUAL STATUS (October 24.2023)


BOOK No BOOK TITLE

At GCB Side At PIUL Side

Reason Date of last receipt Reason Date of last receipt

BOOK No.K01 QUALITY CONTROL PROCEDURE (QCP) Accepted (To be recovered by GCB for scanning) September 17. 2023

BOOK No.K02 INSPECTION AND TEST PLAN (ITP) Closed October 10. 2023
BOOK No.K03 CONSTRUCTION METHOD STATEMENT (CMS) For Review & Comment September 17. 2023
PROCEDURE QUALIFICATION RECORD/WELDING
BOOK No.K04 September 06. 2023
PROCEDURE SPECIFICATION (PQR/WPS) For Review & Comment
WELDERS QUALIFICATION REGISTER/CERTIFUCATE
BOOK No.K05 September 06. 2023
& COATING INSULATION CERTIFICATE For Review & Comment
QC/NDE PERSONNEL QUALIFICATION CERTIFICATES
BOOK No.K06 Closed
& AUTHORISED SIGNATURE October 10. 2023
BOOK No.K07 CALIBRATION CERTIFICATES For Review & Comment September 06. 2023

BOOK No.K08 CONSUMABLES CERTIFICATES For Review & Comment September 21. 2023

BOOK No.K09 VISUAL INSPECTION REPORTS (VT) Closed October 10. 2023
BOOK No.K10 RADIOGRAPHY REPOPRTS (RT) Closed October 10. 2023
MAGNETIC PARTICLE (MT) & LIQUID PENETRANT
BOOK No.K11 Closed
INSPECTION REPORTS October 10. 2023
BOOK No.K12 OTHER NDT REPORTS Closed October 10. 2023
COLD BEND & COLD BENDING PQT INSPECTION
BOOK No.K13 Closed
REPORTS October 10. 2023
COATING,HSS PQT REPORTS & PAINTING & PQT OF
BOOK No.K14 September 06. 2023
PAINTING SYSTEMS REPORTS Accepted (To be recovered by GCB for scanning)
BOOK No.K15 HOLIDAY TEST REPORT Accepted (To be recovered by GCB for scanning) September 06. 2023

BOOK No.K16 ASBUILT SURVEY REPORTS Closed October 10. 2023


BOOK No.K17 PIPELINE TRENCHING REPORTS Closed October 10. 2023
BOOK No.K18 BEDDING/PADDING/BACKFILLING/ BERMING REPORTS Closed October 10. 2023
PIPE CLEANING/ GAUGING/SWEEPING & DRYING
BOOK No.K19 Closed
REPORTS October 10. 2023
BOOK No.K20 CONCRETE REPORTS Closed October 15. 2023
ELICTRICAL & CATHODIC PROTECTION INSTALLATION
BOOK No.K21 AND INSPECTION REPORTS
Returned to GCB With Comments October 15. 2023
INSTRUMENTATION INSTALLATION,CALLIBRATION
BOOK No.K22 CERTIFICATES AND INSPECTION REPORTS
Closed
October 10. 2023
BOOK No.K23 TELECOM INSTALLATION AND INSPECTION REPORTS Returned to GCB With Comments October 15. 2023
BOOK No.K24 MATERIAL APPROVAL REQUEST (MAR) Closed October 10. 2023
BOOK No.K25 FLANGE MANAGEMENT Closed October 10. 2023
BOOK No.K26 STEEL STRUCTURE INSPECTION REPORTS Closed October 10. 2023
BOOK No.K27 ROAD CROSSING ACTIVITY Closed October 15. 2023
BOOK No.K28 SITE TECHNICAL QUERY For Review & Comment September 06. 2023

BOOK No.K29 PIPING / PIPELINE TEST PACKAGE For Review & Comment September 17. 2023

BOOK No.K30 ARH PV & PRESSURE TEST CHART For Review & Comment October 10. 2023
BOOK No.K31 COMPACTION TEST / CTC REPORTS Accepted (To be recovered by GCB for scanning) October 10. 2023
BOOK No.K32 RADIOGRAPHY FILMS For Review & Comment October 10. 2023
BOOK No.K33 PIG RECEIVER INSPECTION REPORTS (MECHANICAL) For Review & Comment October 10. 2023
BOOK No.K34 MECHANICAL COMPLETION CERTIFICATES For Review & Comment October 10. 2023