Government of India
Sanctione Release
Sl. Year of d d
Name of the Project Status
No. Sanction Cost Amount
(₹ in Cr.) (₹ in Cr.)
1 Development of
Under
Infrastructure for
2018-19 56.15 20.79 Implementatio
Pilgrimage Facilitation in
n
Badrinath Ji Dham
Installments & Refunds 1st Installment – 11.77 Cr. (Sept 18)
2nd Installment – 9.02 Cr. (Dec 20)
Actual Completion Date Apr 20
Total UC Received 19.15 Cr.
Physical Progress 62%
Financial Progress 37%
Major Components • Temple complex and surrounding area
(Illumination, Waste management, Storm water
drainage)
• Development at Aastha Path (Solar lights, Dust
bins, Benches)
• Pilgrimage Facilitation Centre
• Parking Complex, Tourist management
system, Tourist arrival plaza
Sanctione Release
Sl. Year of d d
Name of the Project Status
No. Sanction Cost Amount
(₹ in Cr.) (₹ in Cr.)
2 Augmentation of Pilgrimage 2021-22 54.36 14.06 Under
Infrastructure Facilities and Implementatio
Gangotri and Yamunotri n
Page 1 of 2
Dham
Installments 1st Installment – 14.06 Cr. (Dec 21)
Actual Completion Date Jun 24
Total UC Received 7.48 Cr.
Physical Progress 20%
Financial Progress 26%
Major Components • Development at Gangotri Temple (PFC,
Rejuvenation of temple verandah, Entry gate, LED
illumination, public amenities Pilgrimage
registration & dynamic crowd management system,
Alarm system at ghat, Parking)
• Development at Yamnotri (Entry gate, LED
illumination, Development of ghat, Pilgrimage
information centre, public convenience)
• Trek from Janki Chatti to Yamnotri (Rain
shelter & parademic centre, Publlic convenience,
Benches, Signage)
• Development at Kharsali (Approach Road, Entry
gate, Illumination, Landscaping)
Projects in pipeline
Page 2 of 2