SA’ADIYAT ISLAND RESORT DEVLOPMENT CORE-DSC Technical Services L.L.C.

P.O Box 125830 - Dubai


Client: - SHEIKH SUROOR BIN MOH’D AL-NAHYAN Method Statement No:- DSC-SIRD-MS-29
Consultant - KHATIB & ALAMI Rev. No: 00 Date: 27-Mar-2017
Main Contractor - Ghantoot Tpt & Gen.Cont.Est.(Building Division)
Method Statement Title: APPLICATION OF FIRE PROOF PAINTING (CEMENTITIOUS PAINT)

Table of Contents
1. Introduction ............................................................................................................................. 3
2. Scope of Work ......................................................................................................................... 3
3. Materials. .................................................................................................................................. 4
4. Lifting equipment .................................................................................................................... 4
5. Roles and Responsibilities .................................................................................................... 4
6. Procedure For Applying PY15 / PY15HY .............................................................................. 6

ANNEXURES
Annexure – 1………………………………………………………………………….Material Inspection Request
Annexure – 2………………………………………………………………………..…Non – Conformance Report
Annexure – 3…………………………………………………………………………Dimension Inspection Report
Annexure – 4………………………………………………………………...….Welding Visual Inspection Report
Annexure – 5…………………………………………………………….….…….Final Inspection & Release Note
Annexure – 6……………………………………………………...……………….……………Inspection Test Plan
Annexure – 7……………………………………………………………………...………………..Risk Assessment
Annexure – 8…………………………………………………………………...………………….……Tool Box Talk
Annexure – 9………………………………………………………………………………Approved Shop Drawings
Annexure – 10…………………………………………………………………....Material Approval & Specification
Annexure – 11……………………………………………………………………………………...List of Structures

DSC-SIRD-MS-029 REV.0
SA’ADIYAT ISLAND RESORT DEVLOPMENT CORE-DSC Technical Services L.L.C.
P.O Box 125830 - Dubai
Client: - SHEIKH SUROOR BIN MOH’D AL-NAHYAN Method Statement No:- DSC-SIRD-MS-29
Consultant - KHATIB & ALAMI Rev. No: 00 Date: 27-Mar-2017
Main Contractor - Ghantoot Tpt & Gen.Cont.Est.(Building Division)
Method Statement Title: APPLICATION OF FIRE PROOF PAINTING (CEMENTITIOUS PAINT)

1. Introduction
This method statement is to explicitly state all the steps and procedure that will be applied and
adopted while carrying out the Application of Fire Proof Painting on structural Steel members
(Drawing Ref: GTGC-A086-SD-MB-STL-107, Material Ref: MT-CIV-346, List of Structure -
Annexure 11) for SA’ADIYAT ISLAND RESORT DEVELOPMENT PROJECT, ABU DHABI.

2. Scope of Work
This erection method statement covers all activities, precautions, safety requirements, qa qc
requirements and tools equipment used for Application of Fire Proof Painting on structural Steel
members (Drawing Ref: GTGC-A086-SD-MB-STL-107, Material Ref: MT-CIV-346, List of
Structure - Annexure 11) at SA’ADIYAT ISLAND RESORT DEVELOPMENT PROJECT site,
ABU DHABI.( Location map as illustrated below)

Overall Plan Layout

DSC-SIRD-MS-029 REV.0
SA’ADIYAT ISLAND RESORT DEVLOPMENT CORE-DSC Technical Services L.L.C.
P.O Box 125830 - Dubai
Client: - SHEIKH SUROOR BIN MOH’D AL-NAHYAN Method Statement No:- DSC-SIRD-MS-29
Consultant - KHATIB & ALAMI Rev. No: 00 Date: 27-Mar-2017
Main Contractor - Ghantoot Tpt & Gen.Cont.Est.(Building Division)
Method Statement Title: APPLICATION OF FIRE PROOF PAINTING (CEMENTITIOUS PAINT)

3. Materials.

3.1 Carboline – Pyrolite 15

4. Lifting equipment

Appropriate tools will be required for the safe Application of Fire Proof Painting on structural Steel
members. Below is the list of tools to be used:
4.1 Mobile Crane.
4.2 Lifting belts, pulley chain blocks and/or hydraulic pull cylinders of suitable capacity.
4.3 General tools for the application of paint .
.

5. Roles and Responsibilities


5.1 Project Manager
The Project Manager shall have the overall responsibility of the project. He shall be
responsible for the implementation of safety measures and procedures.
He will be the focal point for all interfaces and other communications as required during
execution of stair case installation activity at site between all the parties involved in the
operation.
5.2 Project Engineer
Project Engineer shall be responsible to ensure that all works and activities for stair case
installation are properly coordinated before and after execution. Shall be responsible for
informing and co-ordinating with all engineers, assisting the Project Manager in the daily
routine of works, Shall inform the DSC site quality engineer for the schedule of inspections,
execute all installation activities as per contract requirements, approved method statement,
applicable standards, and approved shop drawings.

5.3 Site Engineer


Shall ensure that site is ready for stair case installation. Shall supervise all installation
activities and will be reporting to the Project Engineer.

5.4 Quality assurance Engineer


QA engineer shall ensure that inspections are conducted as per contract specifications and
ITP. He will ensure full compliance of all works as per quality requirements, approved shop
drawings and method statement.
5.5 Foreman
Foreman ensures that approved materials are available in adequate quantities to carry out the
stair case installation at various stages. Shall be aware of quality requirements and explain it
to the workforce. Shall promptly inform the Site Engineer of prepared areas for inspection and
coordinate with Surveyor for relevant references and setting out.

DSC-SIRD-MS-029 REV.0
SA’ADIYAT ISLAND RESORT DEVLOPMENT CORE-DSC Technical Services L.L.C.
P.O Box 125830 - Dubai
Client: - SHEIKH SUROOR BIN MOH’D AL-NAHYAN Method Statement No:- DSC-SIRD-MS-29
Consultant - KHATIB & ALAMI Rev. No: 00 Date: 27-Mar-2017
Main Contractor - Ghantoot Tpt & Gen.Cont.Est.(Building Division)
Method Statement Title: APPLICATION OF FIRE PROOF PAINTING (CEMENTITIOUS PAINT)

5.6 Surveyor
Surveyor shall carry out all kinds of surveying activity at site. Assist the site engineer in
identifying the locations and giving co-ordinates for the installation of stair case.
He shall monitor any deflection and mismatches and advice the site engineer for corrections.
He shall co-ordinate with the main contractor surveyor for identifying and solving any
discrepancies with regards to the location of Stair Case installation.
5.7 Riggers
Riggers will be thoroughly trained and experienced in installing stair case. They are fully
aware of all safety procedures and will compulsorily attend all the safety briefings like tools
box talks, inductions and other safety meetings and shall carryout the Stair Case installation
as per the instructions of site foreman and site engineer.

5.8 Safety Engineer


Safety Engineer shall ensure that all work activities are conducted as per approved safety
plan. Shall obtain all necessary permits for work. Ensure all work personals are following the
safety requirements and also ensures whether the place of work is clean and safe for
personnel to work. Safety Engineer shall be responsible for the implementation of safety
measures and procedures and will be reporting to CEO of CORE-DSC.

DSC-SIRD-MS-029 REV.0
SA’ADIYAT ISLAND RESORT DEVLOPMENT CORE-DSC Technical Services L.L.C.
P.O Box 125830 - Dubai
Client: - SHEIKH SUROOR BIN MOH’D AL-NAHYAN Method Statement No:- DSC-SIRD-MS-29
Consultant - KHATIB & ALAMI Rev. No: 00 Date: 27-Mar-2017
Main Contractor - Ghantoot Tpt & Gen.Cont.Est.(Building Division)
Method Statement Title: APPLICATION OF FIRE PROOF PAINTING (CEMENTITIOUS PAINT)

6. Procedure For Applying PY15 / PY15HY

1.0 Purpose

The purpose of this procedure is to ensure the detailed control for surface preparation and application
of Pyrolite 15 over steel substrates (primed / unprimed)

2.0 Responsibilities

2.1 The Contractors QC Inspector shall be responsible for final inspection prior to submitting a
request for inspection by Client Representative.

2.2 In case dispute regarding the materials and its application, manufacturer’s recommendation
shall apply

3.0 Access

3.1 Proper access to be provided by the main contractor to prepare the surface and apply Pyrolite
15.

4.0 Environmental Protection

4.1 All works will be carried out in dry and atmospherically correct conditions.

4.2 The working area will be kept clean at all times.

4.3 Spillage of all materials will be cleaned immediately to prevent contamination.

5.0 Surface Preparation

5.1 If the steel is primed, do a cross hatch or an X-cut as per ASTM D 3359 for the adhesion of
the primer to the surface.

5.2 If the steel is not primed, it can either be blasted to have a profile or can be mechanically
prepared (free from mill-scale, loose rust etc.

5.3 If the steel is primed, do a cross hatch or an X-cut as per ASTM D 3359 for the adhesion of
the primer to the surface.

5.4 If the steel is not primed, it can either be blasted to have a profile or can be mechanically
prepared (free from mill-scale, loose rust etc.

DSC-SIRD-MS-029 REV.0
SA’ADIYAT ISLAND RESORT DEVLOPMENT CORE-DSC Technical Services L.L.C.
P.O Box 125830 - Dubai
Client: - SHEIKH SUROOR BIN MOH’D AL-NAHYAN Method Statement No:- DSC-SIRD-MS-29
Consultant - KHATIB & ALAMI Rev. No: 00 Date: 27-Mar-2017
Main Contractor - Ghantoot Tpt & Gen.Cont.Est.(Building Division)
Method Statement Title: APPLICATION OF FIRE PROOF PAINTING (CEMENTITIOUS PAINT)

6.0 Mixing And Application

1. Following the inspection of the prepared surface, the next step is to mix the materials as follows

2. Check the application conditions, ambient temperature, humidity etc and record it.

3. Use a suitable pump, for e.g. Putzmeiser’s SP 11 for mixing and spraying.

4. Mix one bag of Pyrolite 15 in the mixer, add 30 +/- 4 ltrs of water to the dry powder and start
the mixer. Allow it to mix for 2minutes. Do not allow running for more. Depending on the size
of the mixing chamber/ pot two bags can be added.

5. After mixing the material for 2-3 minutes, drop it to the hopper for spraying.

6. Do not allow the mix material to stand for more than one hour in the hopper (begins to get
hard in time).

7. Apply 8-9mm of key coat on the substrate with the suitable nozzle. Adjust the pressure so that
the over-spray is minimum.

8. Build up the thickness in subsequent coats. Allow enough time between the coats to dry. Do
not apply thick to sag.

9. On the edges and corners, make sure the thickness is correct.

10. All application will be carried out by suitable trained / experienced operatives.

11. The selection of materials, mixing, application and achieved thickness will be overseen and
monitored by the foreman, client QC. Refer to respective technical data sheets for details on
mixing and application.

12. When dry, thickness and film integrity shall be checked by the Inspector

13. The information given in the data sheet is for guidance only. If in doubt consult Carboline for
advice.

14. Repairs on the surface to be done as follows

6.14.1 Clean the damaged area and remove all delaminated materials. Prepare a V cut
wherever possible.

6.14.2 Touch up with primer if required by brush and allow it to cure.

6.14.3 Apply by manually if the area is small and gradually build up the thickness. Allow it to
cure properly. If the damaged area is large, spray application is necessary. Typically
if an area more than 0.25Sq.mtr, spray is advisable.
DSC-SIRD-MS-029 REV.0
SA’ADIYAT ISLAND RESORT DEVLOPMENT CORE-DSC Technical Services L.L.C.
P.O Box 125830 - Dubai
Client: - SHEIKH SUROOR BIN MOH’D AL-NAHYAN Method Statement No:- DSC-SIRD-MS-29
Consultant - KHATIB & ALAMI Rev. No: 00 Date: 27-Mar-2017
Main Contractor - Ghantoot Tpt & Gen.Cont.Est.(Building Division)
Method Statement Title: APPLICATION OF FIRE PROOF PAINTING (CEMENTITIOUS PAINT)

7.0 Specification Control

1. The Supervisor will have full access to the relevant quality documents and project specifications.

2. All employees when in doubt shall ask their superior for clarification or guidance.

3. If in doubt consult Carboline.

DSC-SIRD-MS-029 REV.0
ANNEXURES
ANNEXURE - 1

Saadiyat Island Resort Development Project (SIRD) - ABU DHABI

MATERIAL INSPECTION REQUEST

PROJECT # DOCUMENT TYPE TRADE CODE RUNNING NUMBER REV. DATE AUTHOR
DOCUMENT CODE

Issued By: To :

Spec.
No. Material Description Unit Quantity Material Submittal No. Inspection Result
Section

Engineer's comments
A- Approved AAN - Approved As Noted NA - Not Approved

For The Engineer Received by The Contractor

Name : Name :
Sign. : Sign. :
Date : Date :
ANNEXURE-2

Saadiyat Island Resort Development Project (SIRD) - ABU DHABI


NON-CONFORMANCE REPORT
IDENTIFICATION
1. Project Name : 2. Supplier :
3. Date : 4. NCR No. :
5. Contract No : 6. Part description :
7. Part ID : 8. Quantity :
9. Drawing No. : 10. Originator Name :
11. Found during what activity
[ ] Incoming inspection [ ] In‐process inspection [ ] Final inspection [ ] Other :

12. Description of Non‐Conformance : Received By


Name :
Date :
13. Root Causes:

DISPOSITION
14 . [ ] Use‐as‐is [ ] Return to supplier Responsible Person
[ ] Reject [ ] Rework Name:
[ ] Repair
Date:
15. Approval of disposition: Production Engineer QA Inspector
[ ] Minor Name : Name :
[ ] Major Signed: Signed:
16. Approval of repair, rework, return to supplier, rejection disposition:
QA/QC Name: Date:
PROPOSED ACTION
Corrective Action Preventive Action

18. Approval of corrective / preventive action


Quality Engineer Name: Date:
CLOSING THE NON-CONFORMANCE
19. Planned disposition has been completed and preventive action has been initiated
NCR Status :
Signed by QA Inspector: Date:
ANNEXURE – 6
Inspection Test Plan for the
Application of Fire Proof Painting
(Cementitious Paint)

REFERENCE: - DSC-SIRD-MS-029-R.0
CORE-DSC Technical Services L.L.C.
SA’ADIYAT ISLAND RESORT DEVLOPMENT, ABUDHABI. P.O Box 125830 - Dubai
Client: - SHEIKH SUROOR BIN MOH’D AL-NAHYAN Document No:- DSC-SIRD-MS-029
Consultant - KHATIB & ALAMI ` Rev. No: 00 Date:27-Mar-2017
Main Contractor - Ghantoot Tpt & Gen.Cont.Est.(Building Division) Page 2 of 4
INSPECTION TEST PLAN FOR THE APPLICATION OF FIRE PROOF PAINTING (CEMETITIOUS PAINT)

SA’ADIYAT ISLAND RESORT DEVELOPMENT ABUDHABI.


REVIEW STATUS
Rev Date Description CORE DSC GTGC STATUS
No Checked & Approved by
Prepared Checked
Approved by
by by Constr. Qa/Qc Safety
Application of Fire Proof Painting A.A.M. Krishna
00 27-03-2017 C.R. Kannan
(Cementitious Paint) Maran Kumar

Distribution List :
(Following Approval)

LEGEND: K&A - Khatib & Alami CEC OHS - Occupational Health & Safety A - Approval
GTGC - Main Contractor (GHANTOOT) PE - Project Engineer H - Hold Point (signature required to proceed)
C - Client / Architect (SSPD) PM - Project Manager P - Preparation and submittal
CORE DSC - Subcontractor (CORE DSC QCE - Quality Control Engineer R - Review record
TP - Third Party Inspection & Verification Agency MIR - Material Inspection Report S - Surveillance (random attendance, no signature required)
ITR – Inspection Test Request MTC - Mill Test Certificate W - Witness (attendance expected, signature on check sheet)
CORE-DSC Technical Services L.L.C.
SA’ADIYAT ISLAND RESORT DEVLOPMENT, ABUDHABI. P.O Box 125830 - Dubai
Client: - SHEIKH SUROOR BIN MOH’D AL-NAHYAN Document No:- DSC-SIRD-MS-029
Consultant - KHATIB & ALAMI ` Rev. No: 00 Date:27-Mar-2017
Main Contractor - Ghantoot Tpt & Gen.Cont.Est.(Building Division) Page 3 of 4
INSPECTION TEST PLAN FOR THE APPLICATION OF FIRE PROOF PAINTING (CEMETITIOUS PAINT)

No. Activity Specification Survey, Test Acceptance Frequency Verification Action Record
Description and/or Drawing No. or Inspection Criteria Responsibility CORE
Method TP GTGC K&A ADM
DSC
1. PROJECT DOCUMENT
1.1 Method Statement Project’s Specification: Visual Approved Method One time PM P - R A - Quality Plan
Statement Shop Drawing
DSC Method Statement
Third paty
DSC-SIRD-MS-023
certificate Where
applicable
Shop Drawings
GTGC-A086-SD-VL-STL-
107

2. CONSUMABLES
2.1 Material Receipts & Storage Project’s Specification Visual Specification of Paint One time PM/ PE/ R/A - R H -
05120 Structural steel QCE MIR, MTC

3. SURFACE PREPARATION & COATING APPLICATION


3.1 Ambient Condition Method Statement Visual Approved method One time PM/ PE/ P - W W - MIR, MTC
DSC-SIRD-MS-029 Statement QCE

3.2 Pre-Inspection Method Statement Visual Approved method One time PM/ PE/ P - W W - MIR, MTC
DSC-SIRD-MS-029 Statement QCE

3.3 Paint Application Method Statement Visual Approved method One time PE/ P - W W - MIR, MTC
DSC-SIRD-MS-029 Statement QCE

LEGEND: K&A - Khatib & Alami CEC OHS - Occupational Health & Safety A - Approval
GTGC - Main Contractor (GHANTOOT) PE - Project Engineer H - Hold Point (signature required to proceed)
C - Client / Architect (SSPD) PM - Project Manager P - Preparation and submittal
CORE DSC - Subcontractor (CORE DSC QCE - Quality Control Engineer R - Review record
TP - Third Party Inspection & Verification Agency MIR - Material Inspection Report S - Surveillance (random attendance, no signature required)
ITR – Inspection Test Request MTC - Mill Test Certificate W - Witness (attendance expected, signature on check sheet)
CORE-DSC Technical Services L.L.C.
SA’ADIYAT ISLAND RESORT DEVLOPMENT, ABUDHABI. P.O Box 125830 - Dubai
Client: - SHEIKH SUROOR BIN MOH’D AL-NAHYAN Document No:- DSC-SIRD-MS-029
Consultant - KHATIB & ALAMI ` Rev. No: 00 Date:27-Mar-2017
Main Contractor - Ghantoot Tpt & Gen.Cont.Est.(Building Division) Page 4 of 4
INSPECTION TEST PLAN FOR THE APPLICATION OF FIRE PROOF PAINTING (CEMETITIOUS PAINT)

No. Activity Specification Survey, Test Acceptance Frequency Verification Action Record
Description and/or Drawing No. or Inspection Criteria Responsibility CORE
Method TP GTGC K&A ADM
DSC
3.4 Fire Proof Coating Final DFT Method Statement Visual Approved method One time PE/ P -- W W - MIR,MTC,TP
DSC-SIRD-MS-029 Statement QCE

3.5 Dry Filim Thickness Inspection Method Statement Visual Approved method One time PE / P A W W - MIR,MTC,TP
DSC-SIRD-MS-029 Statement QCE

5. DOCUMENTATION
5.1 Painting Reports Visual Approved method One time PE / R - - - -
Statement QCE

5.2 Final Job Completion Reports Visual Approved method One time PE / R - - - -
Statement QCE

LEGEND: K&A - Khatib & Alami CEC OHS - Occupational Health & Safety A - Approval
GTGC - Main Contractor (GHANTOOT) PE - Project Engineer H - Hold Point (signature required to proceed)
C - Client / Architect (SSPD) PM - Project Manager P - Preparation and submittal
CORE DSC - Subcontractor (CORE DSC QCE - Quality Control Engineer R - Review record
TP - Third Party Inspection & Verification Agency MIR - Material Inspection Report S - Surveillance (random attendance, no signature required)
ITR – Inspection Test Request MTC - Mill Test Certificate W - Witness (attendance expected, signature on check sheet)
ANNEXURE-7
RISK ASSESSMENT FOR THE APPLICATION OF
FIRE PROOF PAINTING
(CEMENTITIOUS PAINT)
PROJECT: SAADIYAAT ISLAND RESORT DEVELOPMENT PROJECT ( NO: A086) Prepared DATE:27.03.2017

TITLE: RISK ASESSMENT FOR THE APPLICATION OF FIRE PROOF PAINTING (CEMENTITIOUS PAINT)

APPLICATION OF FIRE PROOF Prepared/ Checked By VIMALKUMAR Sign


PAINTING (CEMENTITIOUS PAINT)
Activity Reviewed By ( PM, CM ) STALIN MATHEW Sign
( SE ) GOPAL Sign

Project SIRDP Purpose of Preparation APPLICATION OF FIRE PROOF PAINTING


(CEMENTITIOUS PAINT)

Risk level Risk level


(Pre control) (Post control)
Hazard Hazard Effect RISK Control Measures Action by RISK Monitoring
P S P S
1 1 RATING 2 2 RATING
Ensure safe passage way with adequate
lighting PI,PM,C
Check for over head obstructions M,PE,SE,S
1.Manual handling Back pain Ensure no chances of slips ,trips and fall
And lifting hazard while shifting
Prior to work daily
Limb injuries Report any near miss and accident If
pre task briefing /TBT
( COP 14.0 ) happen
to be conducted
Strains ,cuts & bruises Ensure appropriate hand protection
3 3 9 H 1 3 L
always while shifting ( PPE) Hand gloves
Damage to property All the personnel will lift the load
manually only if it is within 25 kg
Trip / slip All the activity will be carried out under
qualified supervision
Mechanical lifting shifting components
to be considered wherever practical

Trained employees and supervisor to be


deployed during erection and dismantling
2. working on time
scaffolding Fatality sufficient ties and bracing(support) from
( COP 23.0 ) continuous
the permanent structure as per the PI,PM,C
1.falling of person monitoring
Major injury Standards M,PE,SE,S,
TBT
Periodic scaffolding inspection and SO
2.falling ofmaterial Training
Minorinjury maintain records to be maintained.
records
Ground condition should be ensure good.
3.collapse of First aid Daily inspection of scaffolds from base to
platform platform prior to start of work and during
3 4 12 H 1 4 4 M
Property damage the close of shift
Wind speed ( 38 km ph as per OSHAD
Environmental COP 35.0 )and adverse weather
occupation( dust air conditions to considered and complied
pollution ,noise during and working above the platforms
pollution) Modifications and repairs should be
carried out by authorized and certified
scaffold inspector.
Load calculations to be carried out prior
to start of work and to be classified as
heavy duty or light duty scaffold
Work must be suspended during adverse
weather conditions such as wind speed
2 3 6 M 1 2 2 L Weather forecast
Fatality and rain PI,PM,C
3.Adverse weather reports from local
Personal injury During summer time, heat stress risk shall M,PE,SE,S,
condition authorities or
Property damage be considered and drinking water facilities SO
information
and shaded ventilated area to be
centers
provided.
Training records
Wind speed, Rain and Fog weather should
be considered

TBT to be conducted housekeeping TBT records


PI,PM,C
4.Housekeeping Slip/trip/fall,fire and All chemical empty containers and observation
M,PE,SE,
may lead to 3 4 12 H chemical wastes to be disposed to records
S,SO
1.poor house environmental chemical waste disposing area 1 4 4
keeping and pollution Emergency exits, stairway, roadways and
generation of fire points must be identified and kept
waste free of obstruction
. Proper supervision to be ensured
Personal injury, Proper illumination if working in
5.Illumination property 3 4 12 H night shift shall be ensured PI,PM,C 1 4 4 M Continuous
damage Certified electricians to be M,PE,SE, monitoring and
deployed on night shift. S, supervision
Close monitoring and supervision
to be ensured

6.Electrical hazards Electrical cables and other power supplies Continuous


Workforce involved
( COP 15.0 ) 3 4 12 H to be protected and secured with cable monitoring
in the activity
Damaged cables, stands and hangers PI,PM,C Traing records
wet surface, ELCB/ RCCB to be provided on all M,PE,SE,S,SO 1 4 4 M Observation
 Fatality
electrical DB’s reports
 Major Injury Lead cables used to be double insulated Colourcoding
 Minor Injury with industrial sockets. inspection
 Fire Overhead power lines and supply to be checklist
 propertydamag considered and isolated Prior to start of
e erection Training records
Adequate and appropriate PPE to be used Observation
during activity reports
Cable ties, hangers or hooks to be in place
to hand the electrical cables above human
heights or in a restricted areas.
Wet surface area to be eliminated
Flag man will lead the vehicle to the
location
Vehicle will not exceed the speed
7, Traffic Collision of the
limit of 15 km per hr
managemEnt vehicle
The items on the vehicle will be
properly secured
Vehicle driver to be physically fit and
( COP 44.0 ) Fatality
in good health and eye vision
Close
Reverse horn for the vehicle
Major injury monitoring and
operating supervision
Clear access without obstruction Observation
Minor injury PI,PM,C M,
should be provided to the vehicle M records
PE, SE, S, 1 4
3 4 12 H moving area 4 Regular
Property
Ensure safety induction traing for all inspections
damage
operators
Driver should have valid drving
First aid
licence
Segregate the vehicle and pedestrian
route
8. Power tools Work force involved All power tools should be trained on the
in the activity activity
All power tools assigned for job must be
 Major Injury in proper working condition
 Minor injury PAT test and colour code inspection PI,PM.CM.,
system to be ensured prior to start of work PE,SE,S,SO
 Property
2 3 6 H Double insulation on lead cables to be
Damage
ensured on all power tools
DB’ s used to be inspected and approved
by competent electrician
Guard system on all rotating parts must
be ensured prior to start of using tool
Abrasive wheels used power tools should
be with complied with required rpm rate
and condition of the wheels to be ensured
safe prior to start of work
Adequate and work specific PPE to be
ensured by the supervisor prior to start of
work

PI: Plant in charge PM: Project Manager, CM: Construction Manager, PE: Project Engineer, SE: Site Engineer, S: Supervisor, TS: Technical supervisor, SO: Safety
officer.

GTGC PHSEM GTGC PM GTGC QA/QCM


RISK MATRIX:
Risk = Probability(Likelihood) x Severity

PROBABILITY CONSEQUENCE

INSIGNIFICANT(1) MINOR(2) MODERATE(3)


MAJOR(4) CATASTROPHIC(5)

LOW
RARE(1) 1 2 3 4 5
6
HIGH
POSSIBLE(2) 2 4 8 10
MEDIUM

LIKELY(3) 3 6 9 12 15

EXTREME
OFTEN(4) 4 8 12 16 20
FREQUENT/

5 10 15 20 25
ALMOST CERTAIN(5)

15-25 EXTREME RISK Activity or industry shoud not proceed in current form

8-12 HIGH RISK Activity or Industry should be modified to include remedial planning and action and be subject to detailed EHS assessment.

4-6 MODERATE RISK Activity or industry can operate subject to management and / or modification.

1-3 LOW RISK No action required, unless escalation of risk is possible.


ANNEXURE -8

ToolBox Talk Form

DATE___________ LOCATION_________________

NAME IN FULL SIGNATURE NAME IN FULL SIGNATURE


1. ................................................................ 2. ................................................................

3. ................................................................ 4. ................................................................

5. ................................................................ 6. ................................................................

7. ................................................................ 8. ................................................................

9. ................................................................ 10. ................................................................

Toolbox Talk – Topic of discussion

NAME AND SIGNATURE OF SITE NAME AND SIGNATURE OF


SUPERVISOR SAFETY IN CHARGE
ANNEXURE- 9
APPROVED SHOP DRAWING
ST- 1 COATING ON STEEL STRUCTURE
~---~----
~-~--

KEY PLAk-

--- ----------~='~;c-----------
S

/
ew, t18 I I ,--- ~- UdSSO I\1
97Cx 1O/ S OOx6 . ~--------------L7 0 0 x 100,5rnm THli RHS.
l
;' __ J

r-
Iii- - - + -- - - - 40x40x5 -nrn THKSHS
GENERAL I'IOTES -
STII FN:R TH 6miF-~. t-::.,_
....!'_:" . ~:. '~ .__" . .'__~ .~ ~~._~__.
=,-=: : W ' I ~ ~ ~e-- - _ _~_;"_""_'' '' l1ll' -
L
d 6'- :Y- ~~ [1 j--
, ~ n.
~:
- - -
. tt
----- -::Etl!-.---.---- ---- ----- u- iJ";;-'
'~' ~ :- !ie: ~~ : -~
II" ...".....~? /
.. ~ ~ _ _ _ __~)l"'- '"''" :jllR!
fa CLADDING.
I. f<LL DIMENSIONS ARE II, I/ILLEMETERS, ALL LEVELS ARE 1101 IA ETERS
UIH;; flOTEO
2 THE OR'Wli,GS, ~~ o BE READ N C::HJUNCTION IVITH OTHER RE_El/ANT
I' L~_ ACP C:L~CCI~G AK HITECTL ,AL, STRUCTUC(,AL DRAW~GS AM) ALL Rt:LEVANT :;ECTIONS
' TTrl~rTn--'~-,Hi
' -,._,-_---..,_
, II
OF :;JECI FICATIOfIS,

/
?N II
! I
' -Proof
Cementatious Fire -
System on Steel Beams
,
I
! 3. STR UCTURAL [CION NIDANALYS S ARE BASED 0101 cHE AISC 360,
i AL PRIMARY CO ,NECTIOI, BOLTS ePE MII,lliUM 8 S 3RADE
/ : I S AU MMERAL NilLD STEEL MIN YIELD 275N/mm'.
6 WELD E..ECTRODE SFECIFICATIO I'I IS E7015
I
II f. WELij,IIG THICKi\ESS Sr/\LL BE MINi lm\1 o.a TI NIES TH IC I\fJ ESS
! or THII,NER SECeIO N.
i
I
j - ------ ~ S E L E CTEO STCNE FI\IISH TC W~LL
LEGEfl[3 -

I I

I I

! I I
I ,i I ', I I ~ 0iR I " joon:.
I---_ _ ~,.L.LLL._LL-LLJ ~ ,
--
- f'J~~ ' I-t-
- - j--
. - - -.- ~' -.
-~ ' . -:r""- l' h. i 4tJl:-'-::tI1L1==-=--==;._ -- -,-
''1;,* "
- • - - -. . _ .JL£'Fll
'" ,
5,fjjl) SSL R3 ___ ~ L._-'-=-'-"---
/ 'II ~ ~ "" .< ,I L - R2 FOR APPROVA_
/ '.~ ''If J J -l- ~ R1 FOR ePPROVP,c
;'
1 4COxJ OOx20rn rn THK ,B/\SE PiAE
RO 15 08 2015 FOR APPROVA_
;' W/\I;J4 '!,NCHOR BOLT 6No s. -' RE'/IS IO\ O,'o,TE DEsc r,PTIO N DRAWl' B\
/ PROdECT TITLE:-

;'
/ SA'ADIYAT ISLAN D RESORT
DEVELOPMENT
PLO T # 1.0 .58- 10. SA'AD IYA T ISLAN D

L ~ L J IJAST ER DEVELOFER :-
Tou rism Developme nt and Investm ent co mpany.

8 --r
<-p l l...J,.J, l II )l..o...iJJu lJl C") J.)( I..b.i Jt n ";:"'l j .!lJ "

<>.\ SITIO\j -8 8
L.!i.
)tc,-_
AflCHDR SO LTLAYDIIl ~ O BO:< 1263813, ABU [ HABI, UAE
TEL: +S71-2- LD6 -1400
- SIAL: -1 50 \ . ) SCA LE-1 40 FAX +C171- 2- 4~,6 -150 1J
<c.:>
CLI ENT AND

- PROJECT OEVE LOp oR ~ -


b~ JI '= QS> Q ~ )~>W ~1
SHEIKH SUWOII mx \1011'1) AI.· \;AIIYA\;

P.O. BO>: 22:" ABU DHASI , UAE


I'lill\ r> TEL: +; 71-2- 644 600 0
\J...7~ \lb)
,- - - -- - - - -- - - - - - - - 200x200, c, 3Inm T- K ~ R H S ,
S .S.P.D
-.
TEL: +971- 2- 644 8783
PROPIl'RTY tlEVIH.OPwrNT
~·-------------- - 2JOx 100x5mrn TH I< RHS.
PROJECT MANACEM ENT CO i-SULTANl
<, , - - -- - - - - --- - - -5RP GUDER CONSTRlICTIOH SJPERVIS-ICr. CONS ULTAI~ T
"- ~gl,I _!h 'l
- - GRP . i f t CP CLADDING. -_. --_ . -
I
I / Vhat;b & Alo rni - Coosa l'ooled Eng1eering Com pany
F'.O.Bax: 2732 A.b u Dhabi . UAE
/ .mail: I b · " hi rn ~ M c·h ; dd e e n @ k h a ti b a la rn · . c o m
;' Cementatious Fire Proof V'iebsite: 'sww,k hat;ba!om i.com
System on Steel Beams
-,- - - LEAD CCIIS ULIANI-
r--- .-

~zj
,B !J . - ' . ' ~b......3"
~... _~l ""'~ ::t l iJ ~
K ." 't !:> .1\' f .. .:.. 1 A
,/ ~
C ~h n l!tl "'t lj t l'! II1rtt' !HIM lI Ciltttli,Il V
~ ""1 - .... " . ~- _ ... _. • $" .. _ _

Q.g~~D
/
/ .. ", ,, prlOII ED A m n .!J
L _l TO l! ~ S,-, gMlne o ~ ~l ~ i:lr f"lto VLL
D E s
~"" "" ' JlW
G
,~"""'''"'. ' ''''' • . '''''_'r''.''"
N
, , ,
.. 0' "'"'" ' "
,""o,t...., . co.. " .LT,.,.¥m
O
or,.....,;,o"'f<" ' " O l~ '2" >.''''''''' r." ' '''"''''
.. _ _ l. _ _
C :J "~J ~ CT E D I ." .. "' , .G"""'OR."""" i " ~OJ'C»f<Y"'
0" ,
..." .' " a.o " oo "" """ "'" c... ,,,,,,_,,

Cementatious Fire Proof NQf .tr s _ r~ 10~ 1 ('n ~ICI ILT 1 r~ T --


,
'- __
,
I.- • _ _
,
L _
o t lo/I S: I\ I=' ...... Q V~L "lO fiili H . ~f~ !i, S E' f "" ",
, , System on Steel Beams G P1;j n1 A c 'f ~~ l":! F': I~ M ,", l ~ 4 F. lfI,l GNFllgll.l llri S
/ I 1' (-;' 'r/ 1ll; ~1 t1 ! t Ho l":! ;l • T
r-
/1 ,, , (2) MA Tl; i:ti AL Ap i VA L _ • A l,.l., rj /J Q Y f A tN!: D
,
,
, N H"' ,!iA'r r:;"
'- - - '- - - ,. . --,~-,"'- LI BERT' TOWER, FLAT 30]4, I<HAL FA S-TRE ET
PO BOX 45153, ABU I:HABI, ~ I\ E
TEL - ']71 - 2- 1.27 7531~
FA':< : +37' ~ 2 - C72 7533

GHANTOOT
,~-- - - ~I
Transport and General Contracting LLC.
( Building Division)
r.o.sox 110652, ABU Dr ABI, LJ , H~
TEL: +9 71- 2- 6-1 ' 4151
FAX: + 9 71- 2 ~- 6 4 1 20I 0
EMAIL. : gbd@gh']1tootgrc,up.ce
WEB SITE : www.ghantooqlO up .com

<:, CORE -DSC L.L.C


~\ .,
. Technccl Services
Excellence in enqireered structoree
Dubni lrverstrr ent Pnrc 1,
Eurcpeot Justness Ceuer.Ottice vo 252,
C- - - - - - - ,6Cp CLAD NC. p O.Box - 12583C.Dlcai,U.A,[.
TlO'l - ~ 7 1- 4 - 8 B 5 5923
F(Jx : ... ~} i - 4-- 835 J;]24

- - - - - -- '--- - - (; RP ,

L L REF DRG NO:-


A- R-414 Re\i - 02
37870 Rev -02
(-~
~ j' \'," S [U IO I~-A A.
DRG rw: - REVISIO,
GTGC-A0 86-SD-MB -STL -10 7 R3
--- - -~ --- - - _ ._--_.__ ._ -- - ~ - -

I
ANNEXURE-10
MATERIAL APPROVAL & SPECIFICATION
ANNEXURE- 11
LIST OF STRUCTURES
ANNEXURE -11

SL.NO LIST OF STEEL STRUCTURE


1 SF 2 LOBBY PORTE COCHERE - LVL 2
2 SF 4 END WINGS ROOF AWNINGS A - LVL 7
3 SF 5 END WINGS ROOF AWNINGS D - LVL 7
4 SF 6 END WINGS ROOF AWNINGS B - LVL 7
5 SF 7 END WINGS ROOF AWNINGS C - LVL 7
6 SF 8 WEST POD LVL 7
7 SF 9 EAST POD LVL 7
8 SF 10 BALL ROOM ROOF - LVL 4
9 ST 1 BALL ROOM MAIN ENTRANCE AWNING LVL-3
10 ST 5 (1-2) STAIRCASE AT WEST POD [1-2]
11 ST 5 (2-3) STAIRCASE AT WEST POD [2-3]
12 ST 6 (1-2) STAIRCASE AT EAST POD [1-2]
13 ST 6 (2-3) STAIRCASE AT EAST POD [2-3]
14 ST 7 A AWNINGS AT WING END A - LVL 2
15 ST 7 B AWNINGS AT WING END B - LVL 2
16 ST 7 C AWNINGS AT WING END C - LVL 2
17 ST 7 D AWNINGS AT WING END D - LVL 2
18 ST 10 AWNINGS AT WING D-VIP ENTRY- LVL 2
19 ST 12 (1-2) EAST ATRIUM - STAIR- LVL [1-2]
20 ST 12 (2-3) EAST ATRIUM - STAIR- LVL [2-3]
21 ST 12 (3-4) EAST ATRIUM - STAIR- LVL [3-4]
22 ST 12 (4-5) EAST ATRIUM - STAIR- LVL [4-5]
23 ST 12 (5-6) EAST ATRIUM - STAIR- LVL [5-6]
24 ST 12 ROOF EAST ATRIUM -ROOF
25 ST 13 (0-1) WEST ATRIUM - STAIR- LVL [BASE-1]
26 ST 13 (1-2) WEST ATRIUM - STAIR- LVL [1-2]
27 ST 13 (2-3) WEST ATRIUM - STAIR- LVL [2-3]
28 ST 13 (3-4) WEST ATRIUM - STAIR- LVL [3-4]
29 ST 13 (4-5) WEST ATRIUM - STAIR- LVL [4-5]
30 ST 13 (5-6) WEST ATRIUM - STAIR- LVL [5-6]
31 ST 13 ROOF WEST ATRIUM - ROOF
32 ST 38 GUARD HOUSE 1 TYPE -A
33 ST 39 GUARD HOUSE 2 TYPE -B
34 ST 40 GUARD HOUSE 3 TYPE -B
35 ST 41 GUARD HOUSE 4 TYPE -A
36 ST 42 GUARD HOUSE 5 TYPE -B
37 ST 43 VILLA 1- STAIR CASE
38 ST 44 VILLA 2- STAIR CASE
39 ST 45 VILLA 3- STAIR CASE
40 ST 46 VILLA 4- STAIR CASE
41 SS01 GUARD HOUSE 6 TYPE C
42 SS03 EXTENSION SLAB -WESTPOD LVL 6