UNIT: CU.M
OUTPUT: 20 CU.M PER HOUR
A. LABOR
DESIGNATION: # OF PERSON # HRS HOURLY RATE
1. UNSKILLED LABORER 3 1 76.25
SUBTOTAL A.
B. EQUIPMENT
AMOUNT
1537
2840
22.875
4399.875
4628.625
231.43125
SCOPE OF WORK:
UNIT: CU.M
OUTPUT: 1.20 CU.M PER HOUR
A. LABOR
DESIGNATION: # OF PERSON # HRS HOURLY RATE
1. UNSKILLED LABORER 3 1 76.25
SUBTOTAL A
B. EQUIPMENT
DIRECT COST
DIRECT COST PER CU.M
AMOUNT
228.75
228.75
AMOUNT
61.5
22.875
84.375
AMOUNT
2612.28
2612.28
2925.405
2437.8375
SCOPE OF WORK:
UNIT: CU.M
OUTPUT: 3.72 CU.M PER HOUR
A. LABOR
DESIGNATION: # OF PERSON # HRS
1. UNSKILLED LABORER 6 1
2. SKILLED LABORER 2 1
SUBTOTAL A
B. EQUIPMENT
NAME AND CAPACITY # OF UNITS # OF HOURS
1. CONCRETE VIBRATOR 2 1
2. PUMPCRETE 1 0.27
3. MINOR TOOLS (.10XLABORCOST)
SUBTOTAL B
C. MATERIALS
B. EQUIPMENTS
C. MATERIAL
B. EQUIPMENT
C. MATERIAL
B. EQUIPMENT
C. MATERIAL