When the machine is in packed condition, it should be lifted and moved to the
transport vehicle by means of a lifting equipment of more than 4 t capacity, being
gripped at the place indicated on the packing / Fig.27 /.
When the machine is in unpacked condition or is in a packing, suitable for truck
transportation (just on a pallet), it should be lifted and moved as slings are fixed
on the yoke. Protection pads 10 / Fig.1 / are put under the slings to protect the
finished surfaces. The yoke should be locked.
UNPACKING
During unpacking the availability of all parts and accessories should be established
according to the packing list. Claims, related to shortages and condition of the
machine and its accessories, made after putting it into operation, are not accepted.
CLEANING
Before machine installation, it should be cleaned from the rust-preventing oil with
pure diesel oil. For removal of protective oil film, do not use solid objects and
diluents that can damage the metal surfaces, paint and label marking.
The following water-soluble alkaline degreasing materials are recommended:
- Flexiclean and Techniclean, manufactured by CASTROL;
- Cimclean PC 410 and Cimclean PC 430, manufactured by CIMCOOL
Unpainted surfaces should be dried with rags and then lubricated with "Mobil
Vactra oil No.2". The machine mechanisms shall be lubricated after installation and
foundation as specified in section "Lubrication".
FOUNDATION
B
Точка заземления M8
100
M22
250
95
20
B
300
H
100 x 100
1300
125 1050
100
250
50
560
930
300
300
А А
50
140
175
А-A
250
Фиг. 2