This document is a test report for a current transformer used in a wind power plant. It summarizes the results of insulation resistance testing, winding resistance measurement, ratio testing, protection checks through primary injection, and functional checks. The current transformer was found to meet specifications and protection circuits operated correctly under testing.
This document is a test report for a current transformer used in a wind power plant. It summarizes the results of insulation resistance testing, winding resistance measurement, ratio testing, protection checks through primary injection, and functional checks. The current transformer was found to meet specifications and protection circuits operated correctly under testing.
This document is a test report for a current transformer used in a wind power plant. It summarizes the results of insulation resistance testing, winding resistance measurement, ratio testing, protection checks through primary injection, and functional checks. The current transformer was found to meet specifications and protection circuits operated correctly under testing.
Date : 15/01/2023 Client : M/s.ZF Wind Power Coimbatore Private Limited, Coimbatore. Project: Maintenance Testing of CT, PT, Breaker & Relays.
1. Location : Ht Panel Room / 33 KV Switchboard
Feeder Name : Incomer From Switch Gear Room Outgoing Feeder -01 (CUEH 002)
Panel No : 01
2. Name Plate Details :
TESTED BY VEPL WITNESSED BY ZF
SHEET : 2 OF: 11 TEST REPORT FOR CURRENT TRANSFORMER PAGE : Date : 15/01/2023 Client : M/s.ZF Wind Power Coimbatore Private Limited, Coimbatore. Project: Maintenance Testing of CT, PT, Breaker & Relays.
Make Electrical Control & Systems
Type Wound Sl.No. R: 08/021648 Y: 08/021652 B: 08/021647 Core Core 1 Core 2 Ratio 450/1A 450/1A VA 15 15 Class 1.0 5P20 Insulation Class E Hsv/IL 36/70/170KVp
TESTED BY VEPL WITNESSED BY ZF
SHEET : 3 OF: 11 TEST REPORT FOR CURRENT TRANSFORMER PAGE : Date : 15/01/2023 Client : M/s.ZF Wind Power Coimbatore Private Limited, Coimbatore. Project: Maintenance Testing of CT, PT, Breaker & Relays.
3. General Inspection & Polarity Checks : OK
4. Insulation Resistance test:
Measured Resistance Value in GΩ
Reference Applied voltage(V) R Y B Pri – Earth 5000 8.56 7.45 8.65 Pri – Core1 5000 15.36 14.2 14.6 Pri – core2 5000 15.81 15.6 11.8 Core1- Earth 500 >1 >1 >1 Core2- Earth 500 >1 >1 >1 TESTED BY VEPL WITNESSED BY ZF SHEET : 4 OF: 11 TEST REPORT FOR CURRENT TRANSFORMER PAGE : Date : 15/01/2023 Client : M/s.ZF Wind Power Coimbatore Private Limited, Coimbatore. Project: Maintenance Testing of CT, PT, Breaker & Relays.
Core1-Core2 500 >1 >1 >1
5. Winding Resistance Measurement:
Measured Resistance Value in Ω
Reference R Y B Core 1 5.8 5.6 5.8 Core 2 6.5 6.1 6.8
TESTED BY VEPL WITNESSED BY ZF
SHEET : 5 OF: 11 TEST REPORT FOR CURRENT TRANSFORMER PAGE : Date : 15/01/2023 Client : M/s.ZF Wind Power Coimbatore Private Limited, Coimbatore. Project: Maintenance Testing of CT, PT, Breaker & Relays.
6. Ratio test:
TESTED BY VEPL WITNESSED BY ZF
SHEET : 6 OF: 11 TEST REPORT FOR CURRENT TRANSFORMER PAGE : Date : 15/01/2023 Client : M/s.ZF Wind Power Coimbatore Private Limited, Coimbatore. Project: Maintenance Testing of CT, PT, Breaker & Relays.
Injected Current in Measured Current in secondary (A)
SHEET : 7 OF: 11 TEST REPORT FOR CURRENT TRANSFORMER PAGE : Date : 15/01/2023 Client : M/s.ZF Wind Power Coimbatore Private Limited, Coimbatore. Project: Maintenance Testing of CT, PT, Breaker & Relays.
7. Protection Checks through Primary Injection:
Reference Set Current Time & Curve
EF High Set 0.20 * In Instantaneous EF Low Set 10% * In Normal Inverse (TMS:0.5)
Protection Circuit checks:
TESTED BY VEPL WITNESSED BY ZF SHEET : 8 OF: 11 TEST REPORT FOR CURRENT TRANSFORMER PAGE : Date : 15/01/2023 Client : M/s.ZF Wind Power Coimbatore Private Limited, Coimbatore. Project: Maintenance Testing of CT, PT, Breaker & Relays.
Reference Set Current(A) Operated Current(A) Relay & Breaker Status
Relay Operated on E/F High Set & R 0.20 0.201 Breaker Tripped Relay Operated on E/F High Set & Y 0.20 0.202 Breaker Tripped Relay Operated on E/F High Set & B 0.20 0.204 Breaker Tripped
TESTED BY VEPL WITNESSED BY ZF
SHEET : 9 OF: 11 TEST REPORT FOR CURRENT TRANSFORMER PAGE : Date : 15/01/2023 Client : M/s.ZF Wind Power Coimbatore Private Limited, Coimbatore. Project: Maintenance Testing of CT, PT, Breaker & Relays.
TESTED BY VEPL WITNESSED BY ZF
SHEET : 10 OF: 11 TEST REPORT FOR CURRENT TRANSFORMER PAGE : Date : 15/01/2023 Client : M/s.ZF Wind Power Coimbatore Private Limited, Coimbatore. Project: Maintenance Testing of CT, PT, Breaker & Relays.
8. Functional checks: (Whether Operational Checks OK / Not OK / Not Applicable)
1. CT secondary core should be shorted & Earthed OK
2. CT Secondary All terminals Tightness Should be checked OK 3. Protection and metering circuit checking OK
9. Comments : Nil.
10. Remarks : Current Transformer & Protection Circuit Found Healthy.
TESTED BY VEPL WITNESSED BY ZF
SHEET : 11 OF: 11 TEST REPORT FOR CURRENT TRANSFORMER PAGE : Date : 15/01/2023 Client : M/s.ZF Wind Power Coimbatore Private Limited, Coimbatore. Project: Maintenance Testing of CT, PT, Breaker & Relays.