S.

No Date Jobs Due Date Responsibility


1 10.07.2023 ReachTruckTBA CBA 11.07.2023 Karthikeyan
2 10.07.2023 Fumehood PO 10.07.2023 Karthikeyan
3 10.07.2023 Loading Unloading pump Quote 12.07.2023 Karthikeyan
4 10.07.2023 Lab Cabinet Colour selection 10.07.2023 Karthikeyan
5 10.07.2023 Lab Equipment TBA CBA 12.07.2023 Karthikeyan
6 10.07.2023 Liq N2 PO amendment 11.07.2023 Karthikeyan
7 10.07.2023 Signage 14.07.2023 Pintu
8 10.07.2023 O&M Documentation 22.07.2023 Sandeep/Pintu
9 10.07.2023 Boundary wall Backfilling/ Painting 12.07.2023 Diptiranjan
10 10.07.2023 Snag List of activities 12.07.2023 Sandeep/Pintu
11 10.07.2023 Electrical Load Phase 2 11.07.2023 Diptiranjan
12 10.07.2023 Pipe rack Final 14.07.2023 Diptiranjan
13 10.07.2023 Aircompressor 14.07.2023 Diptiranjan
14 10.07.2023 Drum filling 20.07.2022 Diptiranjan
15 10.07.2023 Staker 20.07.2022 Diptiranjan
16 10.07.2023 Checkchart Precommissioning, Commissioning 14.07.2023 Sandeep/Pintu
17 10.07.2023 ITP, MEP, hydro testing documents 14.07.2023 Sandeep/Pintu
18 10.07.2023 Tia Tech VBFM and DES Deliery 20.07.2023 Diptiranjan
19 10.07.2023 GEW loading platform delivery 20.07.2023 Diptiranjan
20 10.07.2023 Liq N2 delivery 20.07.2023 Diptiranjan
21 10.07.2023 Lab Furniture delivery 20.07.2023 Diptiranjan
22 10.07.2023 Forklift Delivery 20.07.2023 Diptiranjan
23 10.07.2023 Fumehood Delivery 20.07.2023 Diptiranjan
24 10.07.2023 Panel for solid mixer 20.07.2023 Diptiranjan
25 10.07.2023 Lab Equipment delivery 12.07.2023 Karthikeyan
26 10.07.2023 SOPs Operations and logistics 20.07.2023 Pintu
27 10.07.2023 Outsourcing Labour and Technician 20.07.2023 Sandeep
28 10.07.2023 First aid Training 22.07.2023 Pintu
29 10.07.2023 Meeting with Mr. Sandip Mehta 25.07.2023 Pintu
30 10.07.2023 Effluent and Sewage disposal transporter 20.07.2023 Sandeep
31 10.07.2023 RO reject management plan 22.07.2023 Pintu
32 10.07.2023 Skips, scrap management plan 22.07.2023 Pintu
S.No Date Jobs Due Date
1 10.07.2023 Tender quote, SOW, PO 12.07.2023
2 10.07.2023 Boudary wall Light 12.07.2023
3 10.07.2023 Interlock approval followup 12.07.2023
4 10.07.2023 RA approval followup 12.07.2023
5 10.07.2023 AMC PO 12.07.2023
Responsibility
Karthikeyan/Diptiranjan
Karthikeyan/Diptiranjan
Karthikeyan
Karthikeyan
Karthikeyan
S.No Date Jobs Due Date Responsibility
1 10.07.2023 Process PFD and Description 12.07.2023 Karthikeyan/Subratoji
2 10.07.2023 Tender Phase1 20.07.2023 Karthikeyan
3 10.07.2023 Water line 31.07.2023 Yahya
4 10.07.2023 EIA process data 12.07.2023 Karthikeyan/Subratoji
5 10.07.2023 Phase 2 Drawing Comments 14.07.2023 JEC
6 10.07.2023 RC EIA Air/Noise Data discussion 11.07.2023 GEEC