You are on page 1of 81

BQS612

APPLIED STUDIES

PRIME 7
GROUP 3
SUPERVISOR: SIR NABIL FIKRI BIN SAAID
TABLE OF CONTENT

INTRODUCTION

COMPANY BACKGROUND (CONSULTANT)

PROPOSED PROJECT BACKGROUND

TASK 1 : TENDER DOCUMENT AND PRE-TENDER ESTIMATES

CONTENT OF TENDER DOCUMENT

TOTAL PROJECT COST BREAKDOWN (PTE)

ELEMENTAL COST PROJECT BREAKDOWN (PTE)


TABLE OF CONTENT
TASK 2 : PRICING AND COMPLETION OF TENDER DOCUTION, BUILT-UP RATES AND
WORK PROGRAMME

COMPANY BACKGROUND (CONTRACTOR)

TOTAL PROJECT COST BREAKDOWN FOR 7 TENDERS

BUILT-UP RATE
PRELIMINARIES
SITE MEETING
BUILDING WORKS
CONCRETE
REINFORCEMENT
FORMWORK
EXTERNAL WORKS
FENCING AND GATES
WORK PROGRAMME
TABLE OF CONTENT
TASK 3 : PRICING AND COMPLETION OF TENDER DOCUTION, BUILT-UP RATES AND
WORK PROGRAMME

TENDER EVALUATION PROCESS

METHODS OF INVITATION FOR TENDER

LIST OF TENDERERS INVOLVED

COMPARISON BETWEEN TENDERERS AND CONSULTANT PRICE ESTIMATIONS

TENDER EVALUATION

CONCLUSION
BQS612
APPLIED STUDIES I

GROUP MEMBERS

MUHAMMAD AL-AMIR RAFIQ BIN MAHDI FAQIHAH AMNI BINTI MOHAMAD MELVIN KLUIBERT ANAK YESTER MOHD ALDRIN BIN ALFANDI
(2021483018) (2021621818) (2021483468) (2021813652)

SITI NUR SYAHZANANI MOHAMAD SAIRUS NUR FAIZAH BINTI HARATONO ANESSA TAMI ANAK ANDREW JANWARI
(2021483104) (2021492492) (2021846526)
PRIME 7 CONSULTANT
SDN BHD
In the fields of project investigation, feasibility studies, conceptual designs,
details designs, contract administration, and construction supervision, as
well as the testing and commissioning of various projects such as offices, high
rise commercial buildings, cultural as well as religious buildings and
infrastructures. Strives to continuously pursue the quest for quality and
excellence, through synergistic teamwork and simultaneosly achieving
efficiency, functionality and innovation in design, construction and
maintenance.

A Quantity Surveying Firm Based in Kuching, Sarawak

Year of establishment are 2002

Certificates and Licenses from the Lembaga Ukur Bahan Malaysia,


Jabatan Kerja Raya Malaysia, Royal Institute of Surveyor Malaysia,
Construction Industry Development Berhad, and the Ministry of
Finance Malaysia
VISION

Our vision is to establish ourselves as the premier integrated


professional consultant firm in the area, whose efforts
favourably impact the growth of urban infrastructure and the
quality of life for everybody. Dedicated to offering exceptional
and high-quality project management in the construction
industry by incorporating innovative design solutions, a focus
on sustainability and cost-effectiveness, the careful selection of
skilled tradespeople, and a concern for the health and safety of
all involved parties, as well as the satisfaction
MISSION

Our mission is to provide our customers with timely, high-


quality service in the consultant field To achieve quality and
efficiency mastery in every value-added project delivery,
making us the first and only option for our clients. To improve
efficiency and reduce costs by using cutting-edge technology in
both production processes and raw materials. To account for,
and reduce where possible, any negative environmental effects
that might be attributed to our operations.
ORGANIZATIONAL CHART AS CONSULTANT
Sr MUHAMMAD AL-AMIR
RAFIQ BIN MAHDI

DIRECTOR

Sr SITI NUR SYAHZANANI


MOHAMAD SAIRUS

EXECUTIVE DIRECTOR
Service 001

Sr MELVIN KLUIBERT Sr MOHD ALDRIN


ANAK YESTER BIN ALFANDI
SENIOR QUANTITY
SENIOR QUANTITY
SURVEYOR
SURVEYOR

NUR FAIZAH BINTI ANESSA TAMI ANAK FAQIHAH AMNI


HARATONO ANDREW JANWARI BINTI MOHAMAD
CONTRACT CONTRACT CONTRACT
EXECUTIVE EXECUTIVE EXECUTIVE
PROJECT BACKGROUND
CADANGAN MEMBINA 4 BLOK KUARTERS DAN BLOK MAKMAL, SEKOLAH MENENGAH KEBANGSAAN TSHUNG TSIN,
LORONG OYA 22, JALAN OYA, 96000 SIBU, SARAWAK

CLIENT:
KEMENTERIAN PELAJARAN MALAYSIA

IMPLEMENTING AGENCY:
JABATAN KERJA RAYA SARAWAK
TASK 1
TENDER DOCUMENT & PRE-TENDER ESTIMATE
CONTENT OF TENDER DOCUMENT
GRAND SUMMARY OF TENDER
TOTAL PROJECT COST BREAKDOWN
(PTE)
BILL PERCENTAGE
DESCRIPTION AMOUNT (RM)
NO. (%)

1 PRELIMINARIES AND GENERAL 1,119,950.00 5

2 PILING WORKS (ALL PROVISIONAL) 4,564,050.90 21

3A BUILDING WORKS ( QUARTERS ) 13,306,171.87 63

BUILDING WORKS ( HOMESCIENCE


3B 649,484.62 3
LAB )

4 EXTERNAL WORKS 1,038,306.96 5

5 PROVISIONAL SUM 73,000.00 0

6 PRIME COST SUM 566,157.28 3

TOTAL 21,317,121.63 100


ELEMENTAL BREAKDOWN (QUARTERS)
BILL PERCENTAGE
DESCRIPTION AMOUNT (RM)
NO. (%)

A WORK BELOW LOWEST FLOOR FINISH 1,079,217.20 8

B FRAME 1,948,414.50 15

C UPPERFLOOR 1,665,804.91 12

D ROOF AND RAINWATER GOODS 1,565,854.63 12

E STAIRCASES 536,055.50 4

F EXTERNAL WALL 1,395,325.00 10

G INTERNAL WALL 1,101,694.84 8

H DOOR 511,132.00 4

J WINDOW 378,395.20 3

K FLOOR FINISHES 792,659.00 6

L WALL FINISHES 1,240,324.00 9

M CEILING FINISHES 605,574.00 5

N SANITARY FITTINGS AND APPLIANCES 338,586.00 3

P PLUMBING 147,135.09 1

TOTAL 13,306,171.87 100


ELEMENTAL BREAKDOWN (HOMESCIENCE LAB)
BILL PERCENTAGE
DESCRIPTION AMOUNT (RM)
NO. (%)

A WORK BELOW LOWEST FLOOR FINISH 138,152.00 21

B FRAME 120,118.00 19

D ROOF AND RAINWATER GOODS 127,369.38 20

F EXTERNAL WALL 51,360.00 8

G INTERNAL WALL 48,972.00 8

H DOOR 8,926.00 1

J WINDOW 33,304.40 5

K FLOOR FINISHES 15,100.00 2

L WALL FINISHES 13,214.84 2

M CEILING FINISHES 92,968.00 14

TOTAL 649,484.62 100


ELEMENTAL BREAKDOWN (EXTERNAL WORKS)
BILL PERCENTAGE
DESCRIPTION AMOUNT (RM)
NO. (%)

A SITE PREPARATIONS AND EARTHWORKS 12,400.00 1

B TURFING 54,768.00 5

C COVERED WALKWAY 15,763.00 2

D FENCING AND GATES 440,400.00 42

E SURFACE WATER DRAINAGE 30,589.00 3

F SEWERAGE 30,293.46 3

G WATER RETICULATION 102,538.00 10

H ROADWORKS 351,555.50 34

TOTAL 1,038,306.96 100


TENDER ADVERTISEMENT
TASK 2
PRICING AND COMPLETION OF TENDER DOCUMENT ,
PREPARATION OF WORK PROGRAMME AND BUILD-UP RATES
INTRODUCTION
PRIME 7 CONTRACTOR SDN BHD

COMPANY BACKGROUND

A general contractor and founded by Mohd Al Amir Rafiq.

Located at 1st Floor, Lot 10872, Section 13, Jalan Mendu, 93200 Kuching, Sarawak.

Year of establishment 2002 with over 20 years of experience (civil & building works)

Core services are Building Works, Infrastructure Works, Water Works

Bumiputera ownership

Company registration number is 1208462-T

CIDB registration is Grade 7 with specialization code of B01, B02, B04, CE21, CE24
ORGANIZATIONAL CHART AS CONTRACTOR
MUHAMMAD AL-AMIR RAFIQ
BIN MAHDI

DIRECTOR

SITI NUR SYAHZANANI


MOHAMAD SAIRUS

ASSOCIATE DIRECTOR

MOHD ALDRIN BIN


MELVIN KLUIBERT ANESSA TAMI ANAK
ALFANDI
ANAK YESTER ANDREW JANWARI

HEAD PROJECT HEAD HEAD COST


CONTROL CONTRACTS CONTROL

NUR FAIZAH BINTI FAQIHAH AMNI


HARATONO BINTI MOHAMAD
HEAD SPECIAL HEAD PROJECT
PROJECTS IMPLEMENTATION
TOTAL PROJECT COST
BREAKDOWN FOR ALL 7
TENDERER
W&M MS AP8 A&F BNT RL
MORPHEOUS
TENDERER CONSTRUCTION SDN CONSTRUCTION CONSTRUCTION CONSTRUCTION CONSTRUCTION CONSTRUCTION
BHD SDN BHD
SDN BHD SDN BHD SDN BHD SDN BHD SDN BHD

PRELIMINARIES AND
RM1,1168,700.00 RM 947,254.20 RM1,320,993.19 RM1,225,249.74 RM730,000.00 RM1,071,540.00 RM 577,099.17
GENERALLY

PILING
WORKS RM5,293,128.90 RM 4,279,241.60 RM3,639,813.60 RM3,492,062.90 RM8,716,269.70 RM4,698,847.54 RM 5,171,368.79
(PROVISIONAL)

BUILDING WORKS
RM13,520,963.20 RM 11,699,474.33 RM12,703,204.07 RM13,851,087.39 RM12,369,597.86 RM12,189,392.80 RM 14,169,791.83
(QUARTERS)

BUILDING WORKS
RM634,393.60 RM 638,249.00 RM597,268.87 RM619,969.88 RM555,791.04 RM567,012.04 RM 670,499.62
(HOMESCIENCE LAB)

EXTERNAL
RM2,179,204.50 RM 1,429,331.40 RM1,270,112.12 RM960,260.01 RM1,020,685.42 RM1,107,417.70 RM1,377,377.54
WORKS

PRIME COST SUM RM734,915.90 RM 573,899.80 RM587,932.56 RM566,157.28 RM562,346.61 RM321,927.30 RM 587,932.56

PROVISIONAL SUM RM73,000.00 RM 76,650.00 RM73,000.00 RM73,000.00 RM73,000.00 RM73,000.00 RM 73,000.00

TOTAL RM 23,604,306.10 RM19,644,100.33 RM18,261,279.73 RM20,787,787.20 RM 18,317,658.59 RM20,029,137.28 RM 22,627,019.51


CADANGAN PROJEK BINA BARU SK AGAMA KUCHING NO 2, DI ATAS LOT 7449, BLOK 9, SALAK LAND
DISTRICT, KUCHING, SARAWAK

ELEMENT PRICE

PRELIMINARIES AND
RM 902,500.00
GENERALLY

PILING
RM 2,057,869.80
WORKS (PROVISIONAL)

BLOK PENTADBIRAN RM 1,831,545.45

BLOK AKADEMIK RM 4,404,109.48

BLOK KEMUDAHAN AKADEMIK RM 1,039,363.73

EXTERNAL
RM 2,444,778.25
WORKS

PRIME COST SUM RM 1,533,705.65

PROVISIONAL SUM RM 901,587.42 M & W QS CONSULTANT


TOTAL RM 15,115,459.78
CADANGAN MEMBINA DAN MENYIAPKAN 3 BLOK 6 TINGKAT PANGSAPURI (8 UNIT/TINGKAT@144 UNIT
KESELURUHAN), PONDOK PENGAWAL DAN RUMAH SAMPAH DI JALAN UNIVERSITI, LUTONG MIRI,
SARAWAK UNTUK KEMENTERIAN PERUMAHAN KERAJAAN TEMPATAN

ELEMENT PRICE

PRELIMINARIES AND GENERAL RM2,107,000.00

PILING WORKS RM2,055,194.00

3 BLOCKS OF PANGSAPURI RM23,525,989.96

PONDOK PENGAWAL RM137,101.52

RUMAH SAMPAH RM27,274.46

EXTERNAL WORKS RM4,156,505.74

PRIME COST SUM RM1,701,966.54

PROVISIONAL SUM RM922,811.11

TOTAL RM34,633,843.33 MORPHEUS CONSTRUCTION SDN BHD


CADANGAN PROJEK PEMBINAAN BANGUNAN AKADEMIK DAN BANGUNAN PENTADBIRAN DI
SEKOLAH MENENGAH KEBANGSAAN MUARA TUANG, SAMARAHAN, SARAWAK.

ELEMENT PRICE

PRELIMINARIES AND RM95,900.00


GENERAL

PILING WORKS RM5,593,802.30

BLOK AKADEMIK DAN


RM12,986,634.26
PENTADBIRAN

EXTERNAL WORKS RM1,382,067.08

PRIME COST SUM RM635,764.48

RM567,302.40
PROVISIONAL SUMS

TOTAL RM21,261,470.51
BNT CONSTRUCTION SDN BHD
CADANGAN MEMBINA DAN MENYIAPKAN WISMA SAHABAT DI JALAN NENAS, 96100 SARIKEI
SARAWAK

ELEMENT PRICE

PRELIMINARIES AND
RM1,057,620.00
GENERALLY

PILING WORKS RM2,537,446.26

BUILDING WORKS RM6,683,159.26

EXTERNAL WORKS RM6,585,119.30

PRIME COST SUM RM3,536,000.00

PROVISIONAL SUM RM2,530,000.00

TOTAL RM22,929,344.82

RL CONSTRUCTION SDN BHD


CADANGAN MEMBINA DAN MENYIAPKAN 26 UNIT TINGKAT 2 KEDAI DAN PEJABAT, 6 UNIT 3 TINGKAT KEDAI DAN PEJABAT SERTA 1 UNIT
PENCAWANG SEB DI BATU 15 JALAN KUCHING SERIAN, SIBURAN, 94200, SERIAN, SARAWAK.

ELEMENT PRICE

PRELIMINARIES AND
RM1,752,500.00
GENERALLY

PILING WORKS RM2,067,120.08

2 STOREY BUILDING RM9,570,986.61

3 STOREY BUILDING RM7,633,427.50

OTHERS RM90,327.50

SEB SUBSTATION RM143,700.66

EXTERNAL WORKS RM5,866,520.97

AP8 CONSTRUCTION BERHAD


PRIME COST SUM RM4,680,000.00

PROVISIONAL SUM RM470,000.00

TOTAL RM32,274,493.32
CADANGAN MEMBINA PUSAT PELAJAR UNIVERSITI TEKNOLOGI PETRONAS DI LOT 10176 JALAN DATO
MOHAMMAD MUSA, 93400 KOTA SAMARAHAN, SARAWAK

ELEMENT PRICE

PRELIMINARIES AND GENERAL


RM2,464,492.92

PILING WORKS
RM1,736,489.00

PUSAT PELAJAR RM11,568,613.92

EXTERNAL WORK RM1,145,947.90

PRIME COST SUM RM1,318,902.00

PROVISIONAL SUM RM660,000.00

TOTAL RM18,894,445.74 A & F CONSTRUCTION SDN BHD


CADANGAN MEMBINA DAN MENYIAPKAN 3 TINGKAT BLOK AKADEMIK DAN PENTADBIRAN SERTA
MASJID DAN LAIN-LAIN KEMUDAHAN DI SEKOLAH KEBANGSAAN (A) MAJLIS ISLAM SARAWAK
MUKAH, SARAWAK
ELEMENT PRICE

PRELIMINARIES AND
GENERAL RM941,120.00

PILING WORKS RM3,127,905.48

ACADEMIC BUILDING RM8,172,972.83

MOSQUE RM3,343,285.04

GUARD HOUSE RM35,489.80

PUMP AND MSB ROOM RM114,889.90

STORE RM31,305.30

EXTERNAL WORK RM2,414,754.94

PRIME COST SUM RM3,767,627.03

PROVISIONAL SUM RM499,200.00 MS CONSULTANT


TOTAL RM22,448,550.32
BUILT UP RATES
Based on MORPHEUS CONSTRUCTION SDN BHD
PRELIMINARY (SITE MEETING)
CONCRETE (GRADE 30)
REINFORCEMENT
FORMWORK
FORMWORK
EXTERNAL (FENCING & GATES)
WORK PROGRAMME
Based on MORPHEUS CONSTRUCTION SDN BHD
TASK 3
TENDER EVALUATION PROCESS
TENDER BACKGROUND
TENDER TITLE : CADANGAN MEMBINA 4 BLOK KUARTERS DAN 1 BLOK MAKMAL, SEKOLAH MENENGAH
KEBANGSAAN TSHUNG TSIN, LORONG OYA 22, JALAN OYA, 96000 SIBU, SARAWAK.

PRE-TENDER ESTIMATE: RM21,317,121.63 TENDER : 90 DAYS


VALIDITY
PERIOD
METHOD OF
TENDER N0: T/030/12/2022 : SELECTIVE METHOD
TENDERING

TYPE OF TENDER: SELECTIVE TENDER


More Information ...
METHOD OF INVITATION FOR
TENDERER

TENDER OPENING : 15th NOVEMBER 2022 TENDER : 90 DAYS PERIOD OF : 24 MONTHS


VALIDITY CONSTRUCTION
PERIOD
TENDER CLOSING : 16th DECEMBER 2022 METHOD OF : SELECTIVE METHOD
TENDERING
LIST OF TENDERER INVOLVED

W & M CONSTRUCTION SDN BHD


MS CONSTRUCTION SDN BHD
AP8 CONSTRUCTION BERHAD
MORPHEOUS CONSTRUCTION SDN BHD
A & F CONSTRUCTION SDN BHD
BNT CONSTRUCTION SDN BHD
RL CONSTRUCTION SDN BHD
LKS CONSTRUCTION SDN BHD
BINAJAYA SDN BHD
KACC CONSTRUCTION SDN BHD
PRICING BY TENDERER IN ASCENDING ORDER
PRICE COMPARISON
PRICE COMPARISON
STAGE 1
ANALYSIS ON COMPLETENESS OF TENDER
FULFILLMENT
ANALYSIS OF SUBMISSION OF COMPULSORY
DOCUMENTS
ANALYSIS OF THE ADEQUACY OF MINIMUM CAPITAL

PASS PASS PASS PASS PASS


ANALYSIS OF THE ADEQUACY OF MINIMUM CAPITAL

PASS PASS PASS PASS PASS


CURRENT WORK ANALYSIS
TEND. CURRENT WORK CONTRACT PRICE REAL PROGRESS SCHEDULED PROGRESS RESULT
CADANGAN PEMBANGUNAN KOMPLEKS ISLAM DI
1/10 PUSAT KOMERSIL DI ATAS LOT 1784 DAN 1785, BLOK 2, RM 50,000,000.00 92 % Lorem ipsum dolor
94%sit amet, PASS
$ 1.234,56
SIMANGGANG TOWN DISTRICT, SRI AMAN, SARAWAK
consectetur adipiscing elit, sed do
eiusmod tempor incididunt ut labore et
2/10 N/A
N/A N/A N/A Ut enim ad minim
dolore magna aliqua. PASS

PROJEK PEMBINAAN DAN PENYIAPAN HOSPITAL

3/10 PENGAJAR DAN PUSAT KESIHATAN PRIMA (PKP)


UNIVERSITI MALAYSIA SARAWAK (UNIMAS), KOTA RM 485,988,888.00 40% 30% PASS
SAMARAHAN, SARAWAK (REKA DAN BINA)

1. MEMBINA DAN MENYIAPKAN KEM APMM SARAWAK


CAWANGAN KUCHING SECARA KESELURUHAN, Di
Atas Lot 1878-1887, Kampung Parit Buntal, Kuching, RM 127,745,878.00 92% 95%
Sarawak.
4/10 2. MEMBINA DAN MENYIAPKAN LOJI RAWATAN AIR PASS
BATANG SALAK, 2 BLOK KUARTERS STAFF, 1 BLOK
PEJABAT PENGURUSAN, DAN FASILITI PENDUDUK DI
LOT 45688 EXIT JALAN AKSES FAC, UNTUK LEMBAGA
RM 104,383,898.00 85.50% 95.50%
AIR KUCHING

5/10 RM 2,728,828.00 38% 38% PASS


PROPOSED HOMODIALYSIS CENTRE OF KLINIK
KESIHATAN SELANGAU SARAWAK

KERJA PEMBAIKAN CERUN DAN KERJA-KERJA DI


6/10 SEKOLAH MENENGAH KEBANGSAAN AGAMA LIMBANG, RM 1,000,000.00 90% 94% PASS
SARAWAK

PEMBINAAN GANTIAN PENUH 36 BILIK DARJAH, 500

7/10 PELAJAR ASRAMA DAN LAINLAIN KEMUDAHAN DI


SEKOLAH MENENGAH KEBANGSAAN MERDANG, RM 15,000,000.00 60% 70% PASS
SAMARAHAN, SARAWAK

8/10 N/A N/A N/A N/A PASS

9/10 RM1,115,050.00 80% 85% PASS


BINA BARU JALAN PERTANIAN DI KAMPUNG ANNAH
ABANG KE KAMPUNG JABIR, JALAN SERIAN, SARAWAK

10/10 RM 1,540,890.00 90% 96% PASS


BINA BARU 2 UNIT PONTOON PANGKALAN UTAMA DAN
PANGKALAN ULU NELAYAN KAMPUNG SIBU LAUT
SUMMARY OF PRELIMINARY EVALUATION
RESULTS SCHEDULE
PRE-TENDER ESTIMATE (PTE): RM 21,317,121.63
LIST OF TENDERERS PASSEDD THE PRELIMINARY
EVALUATION IN ASCENDING TENDER PRICE ORDER
STAGE 2
FINANCIAL BID CAPACITY
WORK EXPERIENCE
Projects completed by the tenderer calculated based on the total value of the projects that have been completed
(including the current part of the work that has been completed) and the largest value of the projects completed

TENDER
NAME OF TENDERER PAST PROJECT PASS
ER

1/10 W & M CONSTRUCTION SDN BHD 39

2/10 MS CONSTRUCTION SDN BHD 7

3/10 AP8 CONSTRUCTION SDN BHD 8

MORPHEOUS CONSTRUCTION
4/10 12
SDN BHD

5/10 A & F CONSTRUCTION SDN BHD 11

6/10 BNT CONSTRUCTION SDN BHD 7

7/10 RL CONSTRUCTION SDN BHD 12

8/10 LKS SDN BHD 10

9/10 BINAJAYA SDN BHD 20

10/10 KACC CONSTRUCTION SDN BHD 15


TECHNICAL STAFF

Notes:-

Category A - Engineers (Civil, Mechanical and Electrical) in the field of construction, Architects, Quantity Surveyors, members of the Institute Of Building
graduates in the field of Construction Management, graduates of universities recognized by the Government.

Category B - Diploma holders whom graduates from Institutions of Higher Learning recognized by the Government, in the field of construction and also
graduates in other fields

Category C - Other staff who assist or carry out technical tasks such as supervision of work on construction sites, survey work, design and so on.
OWNERSHIP OF PLANT AND BASIC EQUIPMENT

TENDERER NAME OF TENDERER PLANT AND MACHINERY

1/10 W & M CONSTRUCTION SDN BHD

2/10 MS CONSTRUCTION SDN BHD

3/10 AP8 CONSTRUCTION SDN BHD

4/10 MORPHEOUS CONSTRUCTION SDN BHD

5/10 A & F CONSTRUCTION SDN BHD

6/10 BNT CONSTRUCTION SDN BHD

7/10 RL CONSTRUCTION SDN BHD

8/10 LKS SDN BHD

9/10 BINAJAYA SDN BHD

10/10 KACC CONSTRUCTION SDN BHD


SUMMARY OF SECOND STAGES EVALUATION RESULTS
SCHEDULE
STAGE 3
PRICE ADJUSTMENT AND RESTRUCTURING OF TENDER ORDER DUE
TO TAKING INTO ACCOUNT THE PERIOD OF COMPLETION OF WORK
CUT - OFF
SUMMARY OF THIRD STAGE EVALUATION RESULTS
SCHEDULE (IN ASCENDING PRICE ORDER)
LIST OF TENDERERS PASSED THE THIRD STAGE
EVALUATION (IN ASCENDING PRICE ORDER)
SUCCESSFUL TENDERER
PRICE OFFERED FINANCIAL CREDIBILITY
100% 100% MS CONSTRUCTION SDN BHD

TENDERER CONSTRUCTION
OFFERED PRICE % PTE
NO PERIOD
TENDER COMPLETENESS PLANT AND MACHINERY
100% 100%
2/10 RM 19,644,100.33 24 MONTHS -7.85%

WORKING EXPERINCE TECHNICAL STAFF


100% 100%
CONCLUSION
PRIME 7 CONTRACTOR SDN BHD

SUMMARY

In conclusion, the process for the quantity surveyor to start a tender takes a lot
of time and preparation.

As a consultant, the process start from a preliminary estimate until tender


report.

Meanwhile as a contractor, we need to bid on the project with relevant prices


and good quotations and require specific times to submit the tender.

And hence, we have gained an in-depth understanding of the quantity surveyor


profession that will be immensely useful to us in the future.
THANK YOU

You might also like