INDUSTRIAL TRAINING REPORT

Name: Anwar Ul Haq

Roll No: 2K19-CIVET-01

Semester: 8th

Training Course: Field Training

Training Period: Sixteen Weeks

Training Organization: Banu Mukhtar Contracting (Pvt.) Ltd

BATCH 2019-2023

DEPARTMENT OF CIVIL ENGINEERING

NFC INSTITUTE OF ENGINEERING & TECHNOLOGY MULTAN

PAKISTAN

i
DECLARATION

I, Anwar ul Haq, hereby declare that the presented report of field training titled
“Construction of boundary wall” is uniquely prepared by me almost completion of four
months’ work at Banu Mukhtar Contracting (Pvt.) Ltd
I also confirm that, the report is only prepared for my academic requirement not for any
other purpose. It might not be used with the interest of opposite party of the corporation.

___________________
Anwar ul Haq
2k19-CIVET-01
BSc Civil Engineering Technology
NFC-Institute of Engineering &Technology
Multan

ii
CERTIFICATE

This is to certify that the following student of (BATCH 2019-23) have successfully
completed the four-month project in partial fulfillment of the requirements for a Bachelor’s
degree in Civil Engineering & Technology from NFC institute of Engineering &
Technology, Multan, Pakistan

Name Roll NO.

Anwar ul Haq 2k19-CIVET-01

Internal Supervisor

___________________ ______________________

Engr. Shafiq ur Rehman HOD:

Engr. Dr Basit Ehsan


Department of Civil Engineering &Technology
NFC Institute of Engineering & Technology,
Multan
External Supervisor

___________________

Project Manager

Engr. Zafar Shahzad Khan

iii
DEDICATION

I dedicate this work to Almighty Allah, the giver of life, who give us guidance, love,
protection and strength. I dedicate this work to my parents who always prayed for our good
future, they supported us in all financial matters. I dedicate this work to the humble faculty
of Civil Engineering Department.
I also dedicate this work to the respected Supervisor Engr. Shafiq ur Rehman of NFC
Institute of Engineering & technology Multan. I am taught by them with great zeal and
today I am able to reach the apogee.
I want to say God bless you all.

iv
ACKNOWLEDGEMETS

Firstly, I like to thank Almighty Allah. This internship would not have been successfully
completed without the assistance and contribution of all those who helped me in diverse
ways.

I would like to thank my internship supervisor Engr. Shafiq ur Rehman. He helped me


in every stage. This internship gave me knowledge about practical work in construction
field.

v
ABSTRACT

I have completed my internship as a trainee engineer at a project of construction of


boundary wall at Bahria town Karachi. I start this project from layout and excavation of
boundary wall. My job description was to check material and calculate the quantities of
concrete as per drawing. During my internship, I also learnt how to calculate materials
(Bricks, Cement, Sand, Crush and Steel). In this report I describe each day activities with
details.

vi
INTERNSHIP LETTER

This letter is provided by NFC Institute of Engineering & Technology Multan.

vii
ACCEPTANCE LETTER

This letter is provided by Banu Mukhtar contracting (Pvt.) Lt

viii
CONTENTS

CHAPTER 1 ................................................................................................................................... 1
BACKGROUND OF TRAINING ORGANIZATION ............................................................... 1
1.1 Introduction ........................................................................................................................ 1
1.2 History................................................................................................................................. 2
1.3 Organizational Structure .................................................................................................. 3
1.4 Vision, Mission & values ................................................................................................... 9
1.5 Objectives............................................................................................................................ 9
1.6 Location, Area and Locality.............................................................................................. 9
1.7 Facilities & Services ......................................................................................................... 10
CHAPTER 2 ................................................................................................................................. 11
SCHEDULE OF TRAINING AND DUTIES ............................................................................ 11
2.1 1st Week Report ................................................................................................................ 11
2.2 2nd Week Report ............................................................................................................... 11
2.3 3rd Week Report ............................................................................................................... 12
2.4 4th Week Report ............................................................................................................... 12
2.5 5th Week Report ............................................................................................................... 13
2.6 6th Week Report ............................................................................................................... 13
2.7 7th Week Report ............................................................................................................... 14
2.8 8th Week Report ............................................................................................................... 14
2.9 9th Week Report ............................................................................................................... 15
2.10 10th Week Report.............................................................................................................. 15
2.11 11th Week Report.............................................................................................................. 16
2.12 12th Week Report.............................................................................................................. 16
2.13 13th Week Report.............................................................................................................. 17
2.14 14th Week Report.............................................................................................................. 17
2.15 15th Week Report.............................................................................................................. 18
2.16 16th Week Report.............................................................................................................. 18
Fig 2.1: Boundary Wall Details ................................................................................................. 19
Fig 2.2: Survey Point ................................................................................................................. 19
Fig 2.3: Layout ........................................................................................................................... 19
Fig 2.4: Excavation .................................................................................................................... 20
Fig 2.5: P.C.C Work .................................................................................................................. 20

ix
Fig 2.6: Precast Concrete Column Fixing .................................................................................. 20
Fig 2.7: Column Shuttering........................................................................................................ 21
Fig 2.8: Concrete Pouring .......................................................................................................... 21
Fig 2.9: Roding .......................................................................................................................... 21
Fig 2.10: Removing Shuttering .................................................................................................. 22
Fig 2.11: Curing ......................................................................................................................... 22
Fig 2.12: Cleaning & Oiling ...................................................................................................... 22
Fig 2.13: Backfilling .................................................................................................................. 23
Fig 2.14: Planks Fixing .............................................................................................................. 23
Fig 2.15: Material Shifting......................................................................................................... 23
Fig 2.16: Unloading Planks & Column ...................................................................................... 24
Fig 2.17: Cylinder Pouring ........................................................................................................ 24
Fig 2.18: shifting shuttering ....................................................................................................... 24
Fig 2.19: Boundary Wall............................................................................................................ 25
Fig 2.20: T.P Point ................................................................................................................... 25
Fig 2.21: Planks Cutting .......................................................................................................... 25
Fig 2.21: Working Area ........................................................................................................... 26
CONCLUSION & RECOMMENDATION............................................................................... 27
3.1 Conclusion ........................................................................................................................ 27
3.2 Recommendation.............................................................................................................. 27

x
CHAPTER 1

BACKGROUND OF TRAINING ORGANIZATION

1.1 Introduction

Banu Mukhtar Contracting (Pvt.) Limited is the lead Company of Banu Mukhtar –
incorporated in 1964 carrying a wide spectrum of expertise in Construction Management,
Planning, Designing, Supervision and Execution across the length and breadth of Pakistan.
The Company has to its credit construction of scores of Industrial, Commercial &
Institutional Buildings, High Rise Structures and infrastructure projects involving all kinds
of Civil and MEP works. This diversity of scope and magnitude of scale of work sets the
firm apart in its capability to partner with clients and achieve strategic and operational
goals.

The Company is certified by Pakistan Engineering Council (PEC) in highest C-A Category.

Our National Footprint and a historic know-how of stakeholder management, we stand


high to serve you right from requirements’ definition up to the stage of turning your dream
into a reality.

The company can provide one widow solution as per customer requirements because we
have totally integrated R&D, Engineering Design, Business development, Procurement
and Execution departments.

We have a long list of success stories working with scores of National and Multi National
Organizations on projects of varied nature. The secret of our success is our long-term
Customer relationship due to our proactive approach towards project’s success parameters
like Quality and Timely completion along with our Special Focus on ‘Workplace Safety’
and ‘Environmental Protection’.

1
1.2 History
Banu Mukhtar owes its name to late Sheikh Mukhtar Ahmad who migrated from India in
1947 and got settled in Montgomery (now Sahiwal). He left behind five renowned sons
namely Izhar Ahmad, Dr. Israr Ahmad, Iqtedar Ahmad, Vaqar Ahmad and Dr. Absar
Ahmad. Ever since 1960, construction and production of Pre-Cast Concrete Products was
a family business. Izhar (Pvt) Ltd. (Now Banu Mukhtar Contracting (Pvt.) Limited after
change of name in 2012), the ACE Company of Banu-Mukhtar, was founded in 1964 by
Sheikh Mukhtar Ahmad’s eldest son Mr. Izhar Ahmed who was a Civil Engineer by
profession.

After a split in the family business in 1977, Mr. Iqtedar Ahmad, who was previously
managing another company doing similar business, took charge of Banu Mukhtar
Contracting (Pvt.) Limited independently and remained the chief executive of the company
till 1983 at which time he handed over the charge to his eldest son Engr. M. S. Asad
Mukhtar and adopted an advisory role for himself.

Since 1983 Mr. M. S. Asad Mukhtar is the Chief Executive of the Company and Chairman
of the Group working under the banner of Banu-Mukhtar.

Elder son of Mr. Asad Mukhtar, Umar Asad Mukhtar, joined Banu Mukhtar as director in
2008 and since then he is taking charge of the baton from his father and is now leading the
re-alignment of organizational structure and business models.

Starting from a very small family construction business, under the leadership and
management of M. S. Asad Mukhtar, Banu Mukhtar Contracting (Pvt. Ltd. has evolved
into a big name in construction and contracting industry of Pakistan with its sister
companies, notably Banu Mukhtar Products (Pvt.) Limited which is engaged in production
and supply of a large range of Precast Concrete Products with area offices and plants
spreading all over the country and Banu Mukhtar Steel (Pvt.) Ltd which is manufacturing
Pre Engineered Steel Buildings and involved in Mechanical Fabrication works.

2
1.3 Organizational Structure
Banu Mukhtar has a very competent team of professionals; engineers, project
managers, quantity surveyors, architects, designers, planners and most importantly a huge
base of skilled labor work force.

 Zeeshan Azhar

Executive Director

Civil Engineer, PMP

Head Office

 Syed Azhar Ahmad

Executive Director (South)

Civil Engineer, MBA

Area Office Karachi

 Asim Sultan

General Manager MEP

B.Sc (Mech), E-MBA

H. Office

 Waliullah Zahid

Director Procurement & Coordination

Civil Engineer

Head Office

 Dr. Arif Rasheed

Director Administration

MBBS

Head Office

3
 Zaheer Ud Din Alamgir

Chief Engineer Design

Civil Engineer

Head Office

 S. Muhammad Arshad

Executive Director Projects

P.E (Civil)

Head Office

 Raja M. Iftikhar K.

GM Admin.

Group Level Admin

Head Office

 Arif Jamal Faiyazee

GM Sales (South)

Hons. Graduate

Area Office Karachi

 Imran Qamar

Manager Marketing

Architect

Head Office

 Ali Ahmed

Manager Accounts

Chartered Accountant (ACA)

Head Office

4
 Muhammad Tahir Ismail

General Manager Operations

Civil Engineer, PMP

Head Office

 Rehan Rauf

Deputy General Manager Business Development

MS Civil (US), P.E (Civil), PMP

Head Office

 Fahad Aziz

Senior Manager Business Development

B.Sc (Civil), E-MBA

Head Office

 Hafiz M. Ajmal K.

Sales Manager

BMP

Head Office

 Musab Umair Khan

Area Manager Sales (FSD)

Graduate

Sales Office Faisalabad

 Kamran Aman Tola

Sr. Manager Sales

MBA

Area Office Karachi

5
 Irshad Rabbani

Manager Sales

DAE (Civil),

Area Office Islamabad

 Nabil Shehzad

Senior Structural Engineer

Civil Engineer

Head Office

 Waseem Ilyas

Manager Projects

Electrical Engineer

Head Office

 Hassaan Zahid

Manager Projects

Mechanical Engineer, MBA

Head Office

 Hussain Akif

Senior Manager Operations

L. L. B (Hons)

Head Office

 Mohsin Mahmood

Manager IT & SAP

MSc. Computer Science

Head Office

6
 Muhammad Arshad

Sr. Manager QA/QC

Electrical Engineer

Head Office

 Omer Farooq Asim

General Manager Construction (North)

Civil Engineer

North Office

 Ziaullah

Manager Sales

Civil Engineer, Msc.

Area Office South

 Zulfiqar Ahmed

Manager Sales

Graduate

H. Office

 Abdul Rehman

Operations Mgt. Engineer

Mechanical Engineer

Head Office

 Rafique Saqib

Project Manager

Project Manager

Head Office

7
 Yasir Nawaz Khan

Manager Projects

 Mohsin Naqvi

Project Manager

 Abdul Moeed

Project Manager

 Iftikhar Ali

Deputy Manager MEP

 Adnan Jamil

Asst. Manager Projects

 Altaf Ahmad Qazi

Company Secretary

 Ejaz Akbar

Manager Finance

 Naveed Akhtar

Manager Import

 M. Nadeem Shah

Manager Planning & Coordination

 Adnan Naeem Butt

Asst. Brand Manager

 Hafiz Ilyas Naeem

Plant Manager

 Khawaja Ali Iqbal

Assistant Manager Proposal

8
1.4 Vision, Mission & values

Vision:

To become the Market Leader in Services and Products of Construction Industry.

Mission:

Keeping the customers our first priority our mission is to deliver the best quality of
construction services and products through innovative engineering and efficient processes.
We empower every individual of our complete supply chain team to improve the quality
of our services & products every day.

Core Values:

Banu Mukhtar remains loyal to its founding values of Quality, Honesty, Professional
Commitment and Hard Work. We put strong emphasis in building a long-term Customer
relationship by focusing on a proactive approach on deliverable that matters like Quality,
Timely completion, Safety & Professional attention. We recognize that the company’s
primary asset is its dedicated team of professionals which is a key to project success. We
constantly endeavor to provide an encouraging work environment that would promote
Professional ethics, Communication, Dedication, Honesty, Integrity & Mutual respect.

1.5 Objectives
To become the Market Leader in services and products of construction industry. Banu
Mukhtar remains loyal to its founding values of Quality, Honesty, Professional
Commitment and Hard Work

1.6 Location, Area and Locality

Ali Block Park, 5-A, Main Boulevard Garden Town, Ali Block Garden Town, Lahore,
Punjab 54000

9
1.7 Facilities & Services
Banu Mukhtar is one of the leading manufacturers in Precast Concrete Products with
production facilities spread all over Pakistan. Our products are of premium quality as
they are manufactured by the latest automated plants of top notch American, German,
Korean, Turkish and Chinese brands. Our precast plants are functioning across the
country at following locations:

 Hattar (4 Plants)
 Baigpur (2 Plants)
 Pindibhattian
 Taxila
 Nooriabad
 Sadhoke
 Port Qasim
 Hub

10
CHAPTER 2

SCHEDULE OF TRAINING AND DUTIES


Construction of Library at NFC Institute of Engineering & Technology Multan.

2.1 1st Week Report


Date Day Activity Name
23-01-2023 Mon

24-01-2023 Tue

25-01-2023 Wed Site visit.

26-01-2023 Thu Survey team gave points.

27-01-2023 Fri Layout , excavation.

28-01-2023 Sat Material ,machinery and form work shifting.

29-01-2023 Sun Weekly Off

2.2 2nd Week Report

Date Day Activity Name

30-01-2023 Mon compaction, leveling and lean.

Column layout , form work , concrete , rodding and


31-01-2023 Tue
lean curing.

01-02-2023 Wed Remove form work, form work cleaning and oiling,
02-02-2023 Thu Column layout, shifting form work, concrete, rodding,

03-02-2023 Fri and lean curing.

04-02-2023 Sat

05-02-2023 Sun Weekly Off

11
2.3 3rd Week Report

Date Day Activity Name

Remove form work, form work cleaning and oiling


06-02-2023 Mon ,Column layout , shifting form work , concrete ,
rodding , and lean curing.

07-02-2023 Tue Survey team gave points , layout , excavation

Excavation , Material , machinery and form work


08-02-2023 Wed
shifting.

09-02-2023 Thu Curing , compaction , leveling and lean.

10-02-2023 Fri Remove form work, form work cleaning and oiling
,Column layout , shifting form work , concrete ,
11-02-2023 Sat
rodding , and lean curing.

12-02-2023 Sun Weekly Off

2.4 4th Week Report

Date Day Activity Name

13-02-2023 Mon
Back filling , repairing and planks fixing
14-02-2023 Tue

15-02-2023 Wed Planks fixing.

16-02-2023 Thu Client visit.

17-02-2023 Fri Survey team gave points, excavation and curing.

18-02-2023 Sat Material , machinery and form work shifting.

19-02-2023 Sun Weekly Off

12
2.5 5th Week Report

Date Day Activity Name

20-02-2023 Mon Curing , compaction , leveling and lean.

21-02-2023 Tue

22-02-2023 Wed
Remove form work, form work cleaning and oiling
23-02-2023 Thu ,Column layout , shifting form work , concrete ,
rodding , and lean curing.
24-02-2023 Fri

25-02-2023 Sat

26-02-2023 Sun Weekly Off

2.6 6th Week Report

Date Day Activity Name

27-02-2023 Mon Survey team gave points and excavation , curing

28-02-2023 Tue Material , machinery and form work shifting.

01-03-2023 Wed Curing , compaction , leveling and lean.

02-03-2023 Thu
Remove form work, form work cleaning and oiling
03-03-2023 Fri ,Column layout , shifting form work , concrete ,
rodding , and lean curing.
04-03-2023 Sat

05-03-2023 Sun Weekly Off

13
2.7 7th Week Report

Date Day Activity Name

06-03-2023 Mon

07-03-2023 Tue

08-03-2023 Wed Remove form work, form work cleaning and oiling
,Column layout , shifting form work , concrete ,
09-03-2023 Thu rodding , and lean curing.
10-03-2023 Fri

11-03-2023 Sat

12-03-2023 Sun Weekly Off

2.8 8th Week Report

Date Day Activity Name

13-03-2023 Mon Remove form work, form work cleaning and oiling
,Column layout , shifting form work , concrete ,
14-03-2023 Tue rodding , and lean curing.
15-03-2023 Wed
Back filling , repairing and planks fixing
16-03-2023 Thu

17-03-2023 Fri Planks fixing.

18-03-2023 Sat Client visit.

19-03-2023 Sun Weekly Off

14
2.9 9th Week Report

Date Day Activity Name

20-03-2023 Mon Survey team gave points , excavation , and curing

21-03-2023 Tue Material , machinery and form work shifting.

22-03-2023 Wed Curing , compaction , leveling and lean.

23-03-2023 Thu
Remove form work, form work cleaning and oiling
24-03-2023 Fri ,Column layout , shifting form work , concrete ,
rodding , and lean curing.
25-03-2023 Sat

26-03-2023 Sun Weekly Off

2.10 10th Week Report

Date Day Activity Name

27-03-2023 Mon

28-03-2023 Tue

29-03-2023 Wed Remove form work, form work cleaning and oiling
,Column layout , shifting form work , concrete ,
30-03-2023 Thu rodding , and lean curing.
31-03-2023 Fri

01-04-2023 Sat

02-04-2023 Sun Weekly Off

15
2.11 11th Week Report

Date Day Activity Name

03-04-2023 Mon Survey team gave points and excavation .

Excavation ,Material , machinery and form work


04-04-2023 Tue
shifting.

05-04-2023 Wed Curing , compaction , leveling and lean.

06-04-2023 Thu
Remove form work, form work cleaning and oiling
07-04-2023 Fri ,Column layout , shifting form work , concrete ,
rodding , and lean curing.
08-04-2023 Sat

09-04-2023 Sun Weekly Off

2.12 12th Week Report

Date Day Activity Name

10-04-2023 Mon

11-04-2023 Tue

12-04-2023 Wed Remove form work, form work cleaning and oiling
,Column layout , shifting form work , concrete ,
13-04-2023 Thu rodding , and lean curing.
14-04-2023 Fri

15-04-2023 Sat

16-04-2023 Sun Weekly Off

16
2.13 13th Week Report

Date Day Activity Name

17-04-2023 Mon Back filling , repairing and planks fixing.

18-04-2023 Tue Back filling , repairing and planks fixing

19-04-2023 Wed Client visit.

20-04-2023 Thu Survey team gave points and excavation .

Excavation ,Material , machinery and form work


21-04-2023 Fri
shifting.

22-04-2023 Sat Curing , compaction , leveling and lean.

23-04-2023 Sun Weekly Off

2.14 14th Week Report

Date Day Activity Name

24-04-2023 Mon

25-04-2023 Tue

26-04-2023 Wed Remove form work, form work cleaning and oiling
,Column layout , shifting form work , concrete ,
27-04-2023 Thu rodding , and lean curing.
28-04-2023 Fri

29-04-2023 Sat

30-04-2023 Sun Weekly Off

17
2.15 15th Week Report

Date Day Activity Name

02-05-2023 Mon

03-05-2023 Tue
Remove form work, form work cleaning and oiling
04-05-2023 Wed ,Column layout , shifting form work , concrete ,
rodding , and lean curing.
05-05-2023 Thu

06-05-2023 Fri

07-05-2023 Sat
Weekly Off
08-05-2023 Sun

2.16 16th Week Report

Date Day Activity Name

09-05-2023 Mon

10-05-2023 Tue
Remove form work, form work cleaning and oiling
11-05-2023 Wed ,Column layout , shifting form work , concrete ,
rodding , and lean curing.
12-05-2023 Thu

13-05-2023 Fri

14-05-2023 Sat
Weekly Off
15-05-2023 Sun

18
Fig 2.1: Boundary Wall Details

Fig 2.2: Survey Point

Fig 2.3: Layout

19
Fig 2.4: Excavation

Fig 2.5: P.C.C Work

Fig 2.6: Precast Concrete Column Fixing

20
Fig 2.7: Column Shuttering

Fig 2.8: Concrete Pouring

Fig 2.9: Roding

21
Fig 2.10: Removing Shuttering

Fig 2.11: Curing

Fig 2.12: Cleaning & Oiling

22
Fig 2.13: Backfilling

Fig 2.14: Planks Fixing

Fig 2.15: Material Shifting

23
Fig 2.16: Unloading Planks & Column

Fig 2.17: Cylinder Pouring

Fig 2.18: shifting shuttering

24
Fig 2.19: Boundary Wall

Fig 2.20: T.P Point

Fig 2.21: Planks Cutting

25
Fig 2.21: Working Area

26
CHAPTER 3

CONCLUSION & RECOMMENDATION

3.1 Conclusion

This Internship program is proved to be a bridge between the student life and professional
life. The various types of tasks and trainings that I have been undertaking during this
internship on the site and the office enhanced our knowledge in building construction. I am
very glad to see that what I have learnt in the university can be a repeated in the real world.
I was able to apply my theoretical knowledge of designing and construction works in the
real life situation. This internship program played an important role on facing real
challenges. I am attaining a high level of confidence to deal with problems that arise in a
building construction. During this internship I had been able to see the different theoretical
aspects, methodologies and how to construct a certain building. In the supervision session,
I have been able to see the important theoretical and practical aspects of building
construction.

3.2 Recommendation

I would like to recommend every person on the site to perform the necessary tasks. In many
sites I went, the workers did not use safety wearing like helmets and gloves to protect them
from accidental hand and head injuries. Therefore, we are recommending the workers of
any company to wear safe wearing in order not to overcome an accident. The department
of Civil Engineering and Technology should prepare such type of practical section
repeatedly with favorable time schedule and resource concern. If possible it would be better
to go on job training at the time of theoretical lessons. Finally, internship program must
continue since, it provides the students with knowledge of the real site work and it also
helps them to practice the theoretical knowledge with experimental engineering skills.