DECLARATION
I, Anwar ul Haq, hereby declare that the presented report of field training titled
“Construction of boundary wall” is uniquely prepared by me almost completion of four
months’ work at Banu Mukhtar Contracting (Pvt.) Ltd
I also confirm that, the report is only prepared for my academic requirement not for any
other purpose. It might not be used with the interest of opposite party of the corporation.
___________________
Anwar ul Haq
2k19-CIVET-01
BSc Civil Engineering Technology
NFC-Institute of Engineering &Technology
Multan
ii
CERTIFICATE
This is to certify that the following student of (BATCH 2019-23) have successfully
completed the four-month project in partial fulfillment of the requirements for a Bachelor’s
degree in Civil Engineering & Technology from NFC institute of Engineering &
Technology, Multan, Pakistan
Internal Supervisor
___________________ ______________________
___________________
Project Manager
iii
DEDICATION
I dedicate this work to Almighty Allah, the giver of life, who give us guidance, love,
protection and strength. I dedicate this work to my parents who always prayed for our good
future, they supported us in all financial matters. I dedicate this work to the humble faculty
of Civil Engineering Department.
I also dedicate this work to the respected Supervisor Engr. Shafiq ur Rehman of NFC
Institute of Engineering & technology Multan. I am taught by them with great zeal and
today I am able to reach the apogee.
I want to say God bless you all.
iv
ACKNOWLEDGEMETS
Firstly, I like to thank Almighty Allah. This internship would not have been successfully
completed without the assistance and contribution of all those who helped me in diverse
ways.
v
ABSTRACT
vi
INTERNSHIP LETTER
vii
ACCEPTANCE LETTER
viii
CONTENTS
CHAPTER 1 ................................................................................................................................... 1
BACKGROUND OF TRAINING ORGANIZATION ............................................................... 1
1.1 Introduction ........................................................................................................................ 1
1.2 History................................................................................................................................. 2
1.3 Organizational Structure .................................................................................................. 3
1.4 Vision, Mission & values ................................................................................................... 9
1.5 Objectives............................................................................................................................ 9
1.6 Location, Area and Locality.............................................................................................. 9
1.7 Facilities & Services ......................................................................................................... 10
CHAPTER 2 ................................................................................................................................. 11
SCHEDULE OF TRAINING AND DUTIES ............................................................................ 11
2.1 1st Week Report ................................................................................................................ 11
2.2 2nd Week Report ............................................................................................................... 11
2.3 3rd Week Report ............................................................................................................... 12
2.4 4th Week Report ............................................................................................................... 12
2.5 5th Week Report ............................................................................................................... 13
2.6 6th Week Report ............................................................................................................... 13
2.7 7th Week Report ............................................................................................................... 14
2.8 8th Week Report ............................................................................................................... 14
2.9 9th Week Report ............................................................................................................... 15
2.10 10th Week Report.............................................................................................................. 15
2.11 11th Week Report.............................................................................................................. 16
2.12 12th Week Report.............................................................................................................. 16
2.13 13th Week Report.............................................................................................................. 17
2.14 14th Week Report.............................................................................................................. 17
2.15 15th Week Report.............................................................................................................. 18
2.16 16th Week Report.............................................................................................................. 18
Fig 2.1: Boundary Wall Details ................................................................................................. 19
Fig 2.2: Survey Point ................................................................................................................. 19
Fig 2.3: Layout ........................................................................................................................... 19
Fig 2.4: Excavation .................................................................................................................... 20
Fig 2.5: P.C.C Work .................................................................................................................. 20
ix
Fig 2.6: Precast Concrete Column Fixing .................................................................................. 20
Fig 2.7: Column Shuttering........................................................................................................ 21
Fig 2.8: Concrete Pouring .......................................................................................................... 21
Fig 2.9: Roding .......................................................................................................................... 21
Fig 2.10: Removing Shuttering .................................................................................................. 22
Fig 2.11: Curing ......................................................................................................................... 22
Fig 2.12: Cleaning & Oiling ...................................................................................................... 22
Fig 2.13: Backfilling .................................................................................................................. 23
Fig 2.14: Planks Fixing .............................................................................................................. 23
Fig 2.15: Material Shifting......................................................................................................... 23
Fig 2.16: Unloading Planks & Column ...................................................................................... 24
Fig 2.17: Cylinder Pouring ........................................................................................................ 24
Fig 2.18: shifting shuttering ....................................................................................................... 24
Fig 2.19: Boundary Wall............................................................................................................ 25
Fig 2.20: T.P Point ................................................................................................................... 25
Fig 2.21: Planks Cutting .......................................................................................................... 25
Fig 2.21: Working Area ........................................................................................................... 26
CONCLUSION & RECOMMENDATION............................................................................... 27
3.1 Conclusion ........................................................................................................................ 27
3.2 Recommendation.............................................................................................................. 27
x
CHAPTER 1
1.1 Introduction
Banu Mukhtar Contracting (Pvt.) Limited is the lead Company of Banu Mukhtar –
incorporated in 1964 carrying a wide spectrum of expertise in Construction Management,
Planning, Designing, Supervision and Execution across the length and breadth of Pakistan.
The Company has to its credit construction of scores of Industrial, Commercial &
Institutional Buildings, High Rise Structures and infrastructure projects involving all kinds
of Civil and MEP works. This diversity of scope and magnitude of scale of work sets the
firm apart in its capability to partner with clients and achieve strategic and operational
goals.
The Company is certified by Pakistan Engineering Council (PEC) in highest C-A Category.
The company can provide one widow solution as per customer requirements because we
have totally integrated R&D, Engineering Design, Business development, Procurement
and Execution departments.
We have a long list of success stories working with scores of National and Multi National
Organizations on projects of varied nature. The secret of our success is our long-term
Customer relationship due to our proactive approach towards project’s success parameters
like Quality and Timely completion along with our Special Focus on ‘Workplace Safety’
and ‘Environmental Protection’.
1
1.2 History
Banu Mukhtar owes its name to late Sheikh Mukhtar Ahmad who migrated from India in
1947 and got settled in Montgomery (now Sahiwal). He left behind five renowned sons
namely Izhar Ahmad, Dr. Israr Ahmad, Iqtedar Ahmad, Vaqar Ahmad and Dr. Absar
Ahmad. Ever since 1960, construction and production of Pre-Cast Concrete Products was
a family business. Izhar (Pvt) Ltd. (Now Banu Mukhtar Contracting (Pvt.) Limited after
change of name in 2012), the ACE Company of Banu-Mukhtar, was founded in 1964 by
Sheikh Mukhtar Ahmad’s eldest son Mr. Izhar Ahmed who was a Civil Engineer by
profession.
After a split in the family business in 1977, Mr. Iqtedar Ahmad, who was previously
managing another company doing similar business, took charge of Banu Mukhtar
Contracting (Pvt.) Limited independently and remained the chief executive of the company
till 1983 at which time he handed over the charge to his eldest son Engr. M. S. Asad
Mukhtar and adopted an advisory role for himself.
Since 1983 Mr. M. S. Asad Mukhtar is the Chief Executive of the Company and Chairman
of the Group working under the banner of Banu-Mukhtar.
Elder son of Mr. Asad Mukhtar, Umar Asad Mukhtar, joined Banu Mukhtar as director in
2008 and since then he is taking charge of the baton from his father and is now leading the
re-alignment of organizational structure and business models.
Starting from a very small family construction business, under the leadership and
management of M. S. Asad Mukhtar, Banu Mukhtar Contracting (Pvt. Ltd. has evolved
into a big name in construction and contracting industry of Pakistan with its sister
companies, notably Banu Mukhtar Products (Pvt.) Limited which is engaged in production
and supply of a large range of Precast Concrete Products with area offices and plants
spreading all over the country and Banu Mukhtar Steel (Pvt.) Ltd which is manufacturing
Pre Engineered Steel Buildings and involved in Mechanical Fabrication works.
2
1.3 Organizational Structure
Banu Mukhtar has a very competent team of professionals; engineers, project
managers, quantity surveyors, architects, designers, planners and most importantly a huge
base of skilled labor work force.
Zeeshan Azhar
Executive Director
Head Office
Asim Sultan
H. Office
Waliullah Zahid
Civil Engineer
Head Office
Director Administration
MBBS
Head Office
3
Zaheer Ud Din Alamgir
Civil Engineer
Head Office
S. Muhammad Arshad
P.E (Civil)
Head Office
Raja M. Iftikhar K.
GM Admin.
Head Office
GM Sales (South)
Hons. Graduate
Imran Qamar
Manager Marketing
Architect
Head Office
Ali Ahmed
Manager Accounts
Head Office
4
Muhammad Tahir Ismail
Head Office
Rehan Rauf
Head Office
Fahad Aziz
Head Office
Hafiz M. Ajmal K.
Sales Manager
BMP
Head Office
Graduate
MBA
5
Irshad Rabbani
Manager Sales
DAE (Civil),
Nabil Shehzad
Civil Engineer
Head Office
Waseem Ilyas
Manager Projects
Electrical Engineer
Head Office
Hassaan Zahid
Manager Projects
Head Office
Hussain Akif
L. L. B (Hons)
Head Office
Mohsin Mahmood
Head Office
6
Muhammad Arshad
Electrical Engineer
Head Office
Civil Engineer
North Office
Ziaullah
Manager Sales
Zulfiqar Ahmed
Manager Sales
Graduate
H. Office
Abdul Rehman
Mechanical Engineer
Head Office
Rafique Saqib
Project Manager
Project Manager
Head Office
7
Yasir Nawaz Khan
Manager Projects
Mohsin Naqvi
Project Manager
Abdul Moeed
Project Manager
Iftikhar Ali
Adnan Jamil
Company Secretary
Ejaz Akbar
Manager Finance
Naveed Akhtar
Manager Import
M. Nadeem Shah
Plant Manager
8
1.4 Vision, Mission & values
Vision:
Mission:
Keeping the customers our first priority our mission is to deliver the best quality of
construction services and products through innovative engineering and efficient processes.
We empower every individual of our complete supply chain team to improve the quality
of our services & products every day.
Core Values:
Banu Mukhtar remains loyal to its founding values of Quality, Honesty, Professional
Commitment and Hard Work. We put strong emphasis in building a long-term Customer
relationship by focusing on a proactive approach on deliverable that matters like Quality,
Timely completion, Safety & Professional attention. We recognize that the company’s
primary asset is its dedicated team of professionals which is a key to project success. We
constantly endeavor to provide an encouraging work environment that would promote
Professional ethics, Communication, Dedication, Honesty, Integrity & Mutual respect.
1.5 Objectives
To become the Market Leader in services and products of construction industry. Banu
Mukhtar remains loyal to its founding values of Quality, Honesty, Professional
Commitment and Hard Work
Ali Block Park, 5-A, Main Boulevard Garden Town, Ali Block Garden Town, Lahore,
Punjab 54000
9
1.7 Facilities & Services
Banu Mukhtar is one of the leading manufacturers in Precast Concrete Products with
production facilities spread all over Pakistan. Our products are of premium quality as
they are manufactured by the latest automated plants of top notch American, German,
Korean, Turkish and Chinese brands. Our precast plants are functioning across the
country at following locations:
Hattar (4 Plants)
Baigpur (2 Plants)
Pindibhattian
Taxila
Nooriabad
Sadhoke
Port Qasim
Hub
10
CHAPTER 2
24-01-2023 Tue
01-02-2023 Wed Remove form work, form work cleaning and oiling,
02-02-2023 Thu Column layout, shifting form work, concrete, rodding,
04-02-2023 Sat
11
2.3 3rd Week Report
10-02-2023 Fri Remove form work, form work cleaning and oiling
,Column layout , shifting form work , concrete ,
11-02-2023 Sat
rodding , and lean curing.
13-02-2023 Mon
Back filling , repairing and planks fixing
14-02-2023 Tue
12
2.5 5th Week Report
21-02-2023 Tue
22-02-2023 Wed
Remove form work, form work cleaning and oiling
23-02-2023 Thu ,Column layout , shifting form work , concrete ,
rodding , and lean curing.
24-02-2023 Fri
25-02-2023 Sat
02-03-2023 Thu
Remove form work, form work cleaning and oiling
03-03-2023 Fri ,Column layout , shifting form work , concrete ,
rodding , and lean curing.
04-03-2023 Sat
13
2.7 7th Week Report
06-03-2023 Mon
07-03-2023 Tue
08-03-2023 Wed Remove form work, form work cleaning and oiling
,Column layout , shifting form work , concrete ,
09-03-2023 Thu rodding , and lean curing.
10-03-2023 Fri
11-03-2023 Sat
13-03-2023 Mon Remove form work, form work cleaning and oiling
,Column layout , shifting form work , concrete ,
14-03-2023 Tue rodding , and lean curing.
15-03-2023 Wed
Back filling , repairing and planks fixing
16-03-2023 Thu
14
2.9 9th Week Report
23-03-2023 Thu
Remove form work, form work cleaning and oiling
24-03-2023 Fri ,Column layout , shifting form work , concrete ,
rodding , and lean curing.
25-03-2023 Sat
27-03-2023 Mon
28-03-2023 Tue
29-03-2023 Wed Remove form work, form work cleaning and oiling
,Column layout , shifting form work , concrete ,
30-03-2023 Thu rodding , and lean curing.
31-03-2023 Fri
01-04-2023 Sat
15
2.11 11th Week Report
06-04-2023 Thu
Remove form work, form work cleaning and oiling
07-04-2023 Fri ,Column layout , shifting form work , concrete ,
rodding , and lean curing.
08-04-2023 Sat
10-04-2023 Mon
11-04-2023 Tue
12-04-2023 Wed Remove form work, form work cleaning and oiling
,Column layout , shifting form work , concrete ,
13-04-2023 Thu rodding , and lean curing.
14-04-2023 Fri
15-04-2023 Sat
16
2.13 13th Week Report
24-04-2023 Mon
25-04-2023 Tue
26-04-2023 Wed Remove form work, form work cleaning and oiling
,Column layout , shifting form work , concrete ,
27-04-2023 Thu rodding , and lean curing.
28-04-2023 Fri
29-04-2023 Sat
17
2.15 15th Week Report
02-05-2023 Mon
03-05-2023 Tue
Remove form work, form work cleaning and oiling
04-05-2023 Wed ,Column layout , shifting form work , concrete ,
rodding , and lean curing.
05-05-2023 Thu
06-05-2023 Fri
07-05-2023 Sat
Weekly Off
08-05-2023 Sun
09-05-2023 Mon
10-05-2023 Tue
Remove form work, form work cleaning and oiling
11-05-2023 Wed ,Column layout , shifting form work , concrete ,
rodding , and lean curing.
12-05-2023 Thu
13-05-2023 Fri
14-05-2023 Sat
Weekly Off
15-05-2023 Sun
18
Fig 2.1: Boundary Wall Details
19
Fig 2.4: Excavation
20
Fig 2.7: Column Shuttering
21
Fig 2.10: Removing Shuttering
22
Fig 2.13: Backfilling
23
Fig 2.16: Unloading Planks & Column
24
Fig 2.19: Boundary Wall
25
Fig 2.21: Working Area
26
CHAPTER 3
3.1 Conclusion
This Internship program is proved to be a bridge between the student life and professional
life. The various types of tasks and trainings that I have been undertaking during this
internship on the site and the office enhanced our knowledge in building construction. I am
very glad to see that what I have learnt in the university can be a repeated in the real world.
I was able to apply my theoretical knowledge of designing and construction works in the
real life situation. This internship program played an important role on facing real
challenges. I am attaining a high level of confidence to deal with problems that arise in a
building construction. During this internship I had been able to see the different theoretical
aspects, methodologies and how to construct a certain building. In the supervision session,
I have been able to see the important theoretical and practical aspects of building
construction.
3.2 Recommendation
I would like to recommend every person on the site to perform the necessary tasks. In many
sites I went, the workers did not use safety wearing like helmets and gloves to protect them
from accidental hand and head injuries. Therefore, we are recommending the workers of
any company to wear safe wearing in order not to overcome an accident. The department
of Civil Engineering and Technology should prepare such type of practical section
repeatedly with favorable time schedule and resource concern. If possible it would be better
to go on job training at the time of theoretical lessons. Finally, internship program must
continue since, it provides the students with knowledge of the real site work and it also
helps them to practice the theoretical knowledge with experimental engineering skills.