JADUAL PEMASANGAN

TAJUK: PEMASANGAN 20 UNIT


TEMPAT: INSTITUSI PENILAIAN NEGARA, JABATAN PENILAIAN
NEGARA DAN
PERKHIDHIDMATAN HARTA KEMENTERIAN KEWANGAN
MALAYSIA

BI SKOP KERJA HARI CATATAN


L
1. TEMPAH UNIT PENYAMAN 4 HARI KILANG MEMERLUKAN 4 HARI
UDARA[20 UNIT] BERKERJA UNTUK MENYEDIAKAN
UNIT SETELAH TEMPAHAN
DITERIMA SEKIRANYA KILANG
KEHABISAN STOK
2. PENGHAN TARAN PERALATAN 1 HARI SEHARI SAHAJA UNTUK
PENGANGKUTAN DAN
PENGHANTARAN PERALATAN
3. PENGHANTARAN UNIT PENYAMAN 1 HARI MENGAMBIL MASA SEHARI
UDARA[20 UNIT] UNTUK PENGHANTARAN UNIT
PENYAMAN UDARA KE TEMPAT
KERJA
4. PEMASANGAN PENDAWAIAN 3 HARI PROSES PEMASANGAN
PENDAWAIAN MENGAMBIL MASA
SEKURANGNYA 3 HARI
5. PEMASANGAN UNIT PENYAMAN 7 HARI 7 HARI MASA DIAMBIL UNTUK
UDARA[20 UNIT] PEMASANGAN 20 UNIT
PENYAMAN UDARA
6. PENGUJIAN UNIT PENYAMAN 2 HARI KERJA PENGUJIAN MENGAMBIL
UDARA MASA 2 HARI SEKIRANYA SISTEM
BEROPERASI MENGIKUT
SPESIFIKASI YANG TELAH
DITETAPKAN