CONTENTS
1. Intent of AMC
2. Equipment Information
3. Hydraulics Checklist
4. Transmission Checklist
5. Electrical and C&I Checklist
6. Overall Machine Checklist
AMC for Energo make PF-1 | GDK OC3 CHP | RG-2 Page 1
Annual Maintenance Contract Schedule for Paddle Feeder
Plant: GDK OC3 CHP | Area : RG-2
Item / Work Description : AMC For Energo make PF-1
AMC for Energo make PF-1 | GDK OC3 CHP | RG-2 Page 2
Annual Maintenance Contract Schedule for Paddle Feeder
Plant: GDK OC3 CHP | Area : RG-2
Item / Work Description : AMC For Energo make PF-1
Paddle Wheel
Diameter : 3600MM
No. of Blades : 6
Drive Arrangement : Hydraulic Drive
Arrangement
Travel Arrangement
No. of travel wheels : 4
Drive arrangement : Through Geared Motor
Power supply
arrangement : Through festoon cable
arrangement
AMC for Energo make PF-1 | GDK OC3 CHP | RG-2 Page 3
Annual Maintenance Contract Schedule for Paddle Feeder
Plant: GDK OC3 CHP | Area : RG-2
Item / Work Description : AMC For Energo make PF-1
B) Physcical/Operational
1) Hydraulic Pump
a.Pump & Motor coupling condition (Any worn out sign)
b.Pump Noise in Idle & load condition (Judgemental)
For Close loop pump (c & d)
c.Boost pressure (Between 25 to 35 bar) Mention actual value
d.Pressure in A & B line in idle condition (Boost pressure) Mention actual
e.Pump internal leakage Open loop pumps (Measure at working pressure)
Criteria : below 5 %of rated flow
2) Valves
Criteria: Valve function as desired & as per ckt logic
3) Filters:
a. Pr.line filter(check & replace if choked)
Criteria: Existing element good/replace
b. Rtn.line filter(check & replace if choked)
Criteria: Existing element good/replace
c. Re-circulation filter(check & replace if choked)
Criteria: Existing element good/replace
4)Cylinder
a) External oil leakage
Criteria : No leakage
b) Preper function
Criteria: Operation
5)Hyd.Motor
a) External oil leakage
Criteria : No leakage
b) Internal leakage
Criteria : below 5 %of rated flow at working pressure
C) Functional test YES NO NA Remark
a. Pumps
Criteria : As desired/Circuit
b. Valves (Pressure/flow/DC/Prop/ etc)
AMC for Energo make PF-1 | GDK OC3 CHP | RG-2 Page 4
Annual Maintenance Contract Schedule for Paddle Feeder
Plant: GDK OC3 CHP | Area : RG-2
Item / Work Description : AMC For Energo make PF-1
Criteria: As desired/circuit/logic
c.Actuators (Cylinders/Motors)
Criteria: As desired/circuit/logic
Readings:
Pump Boost pressure(close loop) Unit As per ckt Actual Remarks
Load pressure (A line close loop) Bar
Load pressure (B line close loop) Bar
Line pressure (open loop) Bar
Cylinder speed Bar
Motor speed (Variable) mm/sec
Stocks
Whether required spares maintained at Customer YES NO
AMC for Energo make PF-1 | GDK OC3 CHP | RG-2 Page 5
Annual Maintenance Contract Schedule for Paddle Feeder
Plant: GDK OC3 CHP | Area : RG-2
Item / Work Description : AMC For Energo make PF-1
AMC for Energo make PF-1 | GDK OC3 CHP | RG-2 Page 6
Annual Maintenance Contract Schedule for Paddle Feeder
Plant: GDK OC3 CHP | Area : RG-2
Item / Work Description : AMC For Energo make PF-1
AMC for Energo make PF-1 | GDK OC3 CHP | RG-2 Page 7
Annual Maintenance Contract Schedule for Paddle Feeder
Plant: GDK OC3 CHP | Area : RG-2
Item / Work Description : AMC For Energo make PF-1
Operation
AMC for Energo make PF-1 | GDK OC3 CHP | RG-2 Page 8
Annual Maintenance Contract Schedule for Paddle Feeder
Plant: GDK OC3 CHP | Area : RG-2
Item / Work Description : AMC For Energo make PF-1
Maintenance
1.
2.
AMC for Energo make PF-1 | GDK OC3 CHP | RG-2 Page 9
Annual Maintenance Contract Schedule for Paddle Feeder
Plant: GDK OC3 CHP | Area : RG-2
Item / Work Description : AMC For Energo make PF-1
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
AMC for Energo make PF-1 | GDK OC3 CHP | RG-2 Page 10
Annual Maintenance Contract Schedule for Paddle Feeder
Plant: GDK OC3 CHP | Area : RG-2
Item / Work Description : AMC For Energo make PF-1
AMC for Energo make PF-1 | GDK OC3 CHP | RG-2 Page 11
Annual Maintenance Contract Schedule for Paddle Feeder
Plant: GDK OC3 CHP | Area : RG-2
Item / Work Description : AMC For Energo make PF-1
coupling teeth
TRAVEL DRIVE ASSEMBLY (NON DRIVE SIDE-DUST COLLECTOR)
18. Wheel bearing to be
checked visually for any
dust
19. Bolts tightness of
bearing housing &
bearing cover
20. Alignment of wheels
COMMON CHECK
21. Visual check for rust
formation in fabricated
structure
AMC for Energo make PF-1 | GDK OC3 CHP | RG-2 Page 12
Annual Maintenance Contract Schedule for Paddle Feeder
Plant: GDK OC3 CHP | Area : RG-2
Item / Work Description : AMC For Energo make PF-1
AMC for Energo make PF-1 | GDK OC3 CHP | RG-2 Page 13