WORK SCHEDULE DC BODY PUBLIKA KL

Date / Tarikh Site Supervisor Work Description / Perincian Kerja

(i) Installation of DB Box partition board near waiting area


Ilham
1/1/2024 (ii) Skim ceiling board and L-Box corner
(Monday)
Ahmad (i) Installation of electrical fitting T5 LED light and eyeballs ( L-box corner and Toilets )

(i) Skim DB Box and DB Aircond partition wall

Ilham (ii) Installation of 8 ceiling manhole

(iii) Tiles work TR5 (40%)


1/2/2024
(Tuesday)
Ahmad (i) Installation of electrical fitting : Switches and sockets

Azfar (i) Levelling using Novoplan 21 self leveling underlayment ( Except TR4, TR5 and TR6 )

(i) Tiles works TR5 (60%)


Ilham
1/3/2024 (ii) Tiles works TR6 ( 20%)
(Wednesday)
Ahmad (i) Installation of SPC Flooring : TR1, TR2 and TR3
(i) Sambung buat kerja wiring lampu dan socket
(i) Tiles works TR5 (90%)
Ilham
(ii) Tiles works TR6 ( 50%)
1/4/2024
(Thursday) Ahmad (i) Installation of SPC Flooring : Salad bar, Reception area, CR1 and CR2

Azfar (i) Levelling using Novoplan 21 self leveling underlayment : TR4, TR5 and TR6

(i) Tiles works TR5 (100%)


Ilham
(ii) Tiles works TR6 ( 70%)
1/5/2024
(Friday) Ahmad (i) Installation of SPC Flooring : TR4, TR5 and TR6

Haris (i) Glass installation : CR1 and CR2

(i) Tiles works TR6 (90%)


Ilham
(ii) Paint works (Textured wall ) : Salad bar, reception area and waiting area

Ahmad (i) Installation of tinted glass : CR1, CR2


1/6/2024
(Saturday)
Haris (i) Glass installation : Main entrance

(i) Outerframe door : TR1, TR2, TR3 and TR4


Adnan
(ii) Cabinet : TR1 and TR2
Ilham (i) Tiles works TR6 (100%)

Ahmad (i) Installation of tinted glass : TR1, TR2


1/8/2024
(Monday) (i) Outerframe door : TR5, TR6, Hidden door pantry
Adnan
(ii) Cabinet : TR3 and TR4
(iii) Fluted panel : TR1, TR2 and TR3
Ilham (i) Venetian Blind : CR1, CR2 and Hallway beside CR

Ahmad (i) Installation of tinted glass : TR5, TR6


1/9/2024
(Tuesday) (i) Installation of door : TR1, TR2, TR3 and TR4

Adnan (ii) Cabinet : TR5 and TR6

(iii) Fluted panel : TR4, TR5 and TR6

Ilham (i) Venetian Blind : TR5, TR6 and Shower Room 6

Ahmad (i) Installation of artwork outside wall : 50%

(i) Installation of signage outside premises : 2 nos


1/10/2024
Azfar (ii) Reception counter font logo
(Wednesday)
(ii) Main entrance with font logo

(i) Installation of door : TR5, TR6 and Hidden door pantry


Adnan (ii) Cabinet : Salad bar and Pantry
(iii) Reception counter cabinet

Ilham (i) Venetian Blind : TR5, TR6 and Shower Room 6

1/11/2024 Ahmad (i) Installation of artwork outside wall : 100%


(Thursday)
(i) Cabinet : Shower Room 5 and Shower Room 6
Adnan
(iii) Cabinet : Reception area and hiddren area

(i) Rectification period


1/12/2024
Azfar
(Friday) (ii) Handover final date