INDIAN CANE POWER.

LTD
UNIT:ALAGAWADI BIRESHWAR SUGAR
Boiler & ESP Work Details
Gland & Termination Work Cable Tray Work & Cable
Sl No. Description LCS Box Earthing
(Power & Control Cable) Dressing
Motor/Transformer/
Feeder Side
Heater Side
Completed upto Main
1 Rectifier Transf- 1 Pending Completed NA
Cable Trench
Completed upto Main Cable Tray & Dressing completed
2 Rectifier Transf- 2 Pending Completed NA
Cable Trench upto ESP top, pending only top side
Completed upto Main
3 Rectifier Transf- 3 Pending Completed NA
Cable Trench
Gland Work done,
4 Emitting Electrode Drive-1 Pending Pending Pending
termination pending

Gland Work done, Cable Tray & Dressing completed


5 Emitting Electrode Drive-2 Pending Pending Pending
termination pending upto ESP top, pending only top side
No GearBox, So Motor Gland Work done,
6 Emitting Electrode Drive-3 Pending Pending
Not palced termination pending
Pending Cable Tray & Dressing completed
7 Air Blower Pending Pending Pending
Fan & Motor Not Placed upto ESP top, pending only top side
Pending completed upto ESP Top, pending
8 Insulator Heaters Pending Pending Pending
JB Box inside penthouse
Gland Work done,
9 Collecting Electrode Drive-1 Pending Pending Pending
termination pending
only Cable Laying Completed,
Gland Work done,
10 Collecting Electrode Drive-2 Pending Pending Pending dressing work & cable tray pending
termination pending
on motor side
Gland Work done,
11 Collecting Electrode Drive-3 Pending Pending Pending
termination pending

12 ESP RAV-1 Completeted Completed Completed Pending

Completed
13 ESP RAV-2 Completeted Completed Completed Pending
Motor 1& 2 trail taken
No GearBox, So Motor
14 ESP RAV-3 Completed Completed Pending
Not palced
Pending Gland Work done,
15 Hopper Heater-1 NA NA
Heater Coil Not Working termination pending
Pending Gland Work done, Tray work, Cable laying & dressing
16 Hopper Heater-2 NA NA
Heater Coil Not Working termination pending work completed
Pending Gland Work done,
17 Hopper Heater-3 NA NA
Heater Coil Not Working termination pending

1 ID Fan-1 Completed Completed Completed Completed Power & Control Cable Tray work,
dressing work pending on only Motor
2 ID Fan-2 Completed Completed Completed Completed side
3 SA Fan-1 Completed Completed Completed Completed Power & Control Cable Tray work,
dressing work pending on only Motor
4 SA Fan-2 Completed Completed Completed Completed side
5 FD Fan-1 Completed Completed Completed Completed Power & Control Cable Tray work,
dressing work pending on only Motor
6 FD Fan-2 Completed Completed Completed Completed side
Pending only terminal
7 Boiler Feed Pump-1 Completed Completed Completed
box Earthing
Pending only terminal
8 Boiler Feed Pump-2 Completed Completed Completed Completed
box Earthing
Pending only terminal
9 Boiler Feed Pump-3 Completed Completed Completed
box Earthing

10 Feed Transfer Pump-1 Completed Completed Completed Completeted


Completed
11 Feed Transfer Pump-2 Completed Completed Completed Completeted
Pending
12 Economiser RAV-1 Completed Completed Completed
(temporary Earthed)
Pending
13 Economiser RAV-2 Completed Completed Completed
(temporary Earthed) Cable tray & Dressing work pending only
Pending Motor end
14 Economiser RAV-3 Completed Completed Completed
(temporary Earthed)
Pending
15 Economiser RAV-4 Completed Completed Completed
(temporary Earthed)
16 APH RAV-1 Pending Pending Pending Pending
Pending Cable Laying, Tray & dressing
17 APH RAV-2 Pending Pending Pending Pending
18 SBC Pending Pending Pending Pending Pending
HP Dosing Pump 1,2 & Cable Tray & Dressing work pending on
19 Completed Completed Completed Completed
stirrer Motor Side
Gland & Termination Work Cable Tray Work & Cable
Sl No. Description LCS Box Earthing
(Power & Control Cable) Dressing
Motor/Transformer/
Feeder Side
Heater Side
LP Dosing Pump 1,2 & Cable Tray & Dressing work pending on
20 Completed Completed Completed Completed
stirrer Motor Side
Gland Work done,
21 FD Bypass damper Completed Completed Pending
termination pending
Completed
Gland Work done,
22 SA Bypass damper Completed Completed Pending
termination pending
23 Screw Feeder-1 Completed Completed Completed Pending

24 Screw Feeder-2 Completed Completed Completed Pending

25 Screw Feeder-3 Completed Completed Completed Pending Completed

26 Screw Feeder-4 Completed Completed Completed Pending

27 Screw Feeder-5 Completed Completed Completed Pending


Gland Work done,
28 Fuel Feeder- 1 Completed Completed Pending
termination pending
Gland Work done,
29 Fuel Feeder- 2 Completed Completed Pending
termination pending
Gland Work done, Completed
30 Fuel Feeder- 3 Completed Completed Pending
termination pending
Gland Work done,
31 Fuel Feeder- 4 Completed Completed Pending
termination pending
Gland Work done,
32 Fuel Feeder- 5 Completed Completed Pending
termination pending

33 Drag Chain Feeder- 1 Completed Completed Completed Pending

34 Drag Chain Feeder- 2 Completed Completed Completed Pending


Cable tray & Dressing work pending only
Motor end
35 Drag Chain Feeder- 3 Completed Completed Completed Pending

36 Drag Chain Feeder- 4 Completed Completed Completed Pending

Gland Work done,


37 Air Modeling Damper- 1 Pending Pending Pending
termination pending
Pending
Gland Work done,
38 Air Modeling Damper- 2 Pending Pending Pending
termination pending

39 Coal Spreader- 1 Completed Completed Completed Pending

40 Coal Spreader- 2 Completed Completed Completed Pending


Completed
41 Coal Spreader- 3 Completed Completed Completed Pending

42 Coal Spreader- 4 Completed Completed Completed Pending

43 Stroker Drive- 1 Completed Completed Completed Pending


Completed
44 Stroker Drive- 2 Completed Completed Completed Pending

45 Deaerator Tank side MOV's Temporarily Terminated Completed (MCB) NA Pending


Cable Tray Work Completed, Cable
Dressing work Pending
46 Boiler Top side MOV's Temporarily Terminated Completed (MCB) NA Pending