Professional Documents
Culture Documents
Strategic Construction
Procurement
Week 9
Critical Clauses of Standard Forms
of Contract
Dr Nilupa Udawatta
Level 4 - John Hay Building
Deakin University, Geelong
Tel: +613 524 79388
E-mail: nilupa.udawatta@deakin.edu.au
Teaching Team
Week Commencing Class Topic Delivered by Bb Collaborate Sessions Assignments Due Dates
1 9 March Introduction to the unit and overview of Nilupa
construction procurement
2 16 March Procurement Methods – Part A Xin Session 1 - Thursday, 19
March 2020 at 6.30pm
3 23 March Procurement Methods – Part B Xin
4 30 March Procurement Methods – Part C Xin A1 (Individual) – Strategic
Procurement Report (20%)
5 6 April Contract Payment Options and Tendering Xin Session 2 - Thursday, 9
Process April 2020 at 6.30pm
6 20 April Subcontracting Practices and Construction Nilupa
Contract Risk
– A statement of objectives
– A summary and analysis of project objectives, requirements, characteristics, risks,
client capabilities etc.
– Analysis and recommendation of procurement/delivery routes: Procurement
Traditional route
Design and construct route
method
Management routes determines
Collaborative routes such as partnering who carries
Integrated routes such as PPP what risks…..
– Analysis and recommendation of contract pricing options:
Lump-sum contracts
Measurement contracts
Reimbursement contracts
– Analysis and recommendation of tendering methods:
Open tendering
Selective tendering
Etc…
– Procurement approaches
– Analysis and recommendation of form of contract and contract administration
4 Forms of contracts
Deakin University CRICOS Provider Code: 00113B Contract administration arrangement
Assessments
Extension of Time
Progress Claim
6
Extension of
Time (EOT)
7
Extension of Time (EOT) - Outline
Construction delay
Causes, Effects, types
8
Causes of Construction Delay
Environmental
Project
Resources
Management
Causes of
Delay
Contractual
Regulation
relationship
9
Financial
Effects of Construction Delay
Time
overrun
Productivity
Cost
and Efficiency
Overrun
loss
Late Effects of
Disputes
Payment Delay
Company Total
Reputation abandonment
Rescheduling
10
Types of Construction Delay
Non-compensable
(Time)
Excusable delays
Compensable
(Time +cost)
Non-excusable
Types
delays
Concurrent delays
11
Provisions for Construction Delay
Identify
cause for
delay
Notify it to
Superintendent
(34.2)
Within 28
days submit
the claim
(34.3)
Within 28
days grant
EOT
13
(34.5)
Case: Gaymark Inv. -Vs-
Walter Const. (1999)
Construction of a Hotel in Australia, Walter claimed $4,900,341 on a
number of bases, principally for variations, prolongation and
disruption/acceleration.
Gaymark counter-claimed for $1,554,059, principally arising through the
application of liquidated damages in accordance with the contract.
Employer delayed work for 77 days
Contract requires Contractor to give notice. But Contractor failed to do so
No contractual authority for EoT without notice
Since no EoT notice, would contractor recover damage?
Contractor to damages.
Qualifying Cause of Delay –
Excusable
Events whether occurring before or on - Date for Practical Completion;
18
Latent Conditions – Cl.25
20
Non - Excusable Delays
21
Concurrent Delays – 34.4
22
Concurrent Delays
Delay 2 days A
(employer’s fault)
C
Delay 4 days B
(Contractor’s
fault)
23
Concurrent Delays
Delay 4 days A
(employer’s fault)
C
Delay 2 days B
(Contractor’s
fault)
24
Concurrent Delays
Delay 3 days A
(employer’s fault)
C
Delay 3 days B
(Contractor’s
fault)
25
Concurrent Delays
Delay 3 days A
(employer’s fault)
C
Delay 3 days B
(Contractor’s
fault)
26
Concurrent Delays – 34.4
27
Henry Boot Construction (UK) Limited Vs
Malmaison Hotel (Manchester) Limited
[1999]
Henry Boot contracted with Malmaison for the construction of a hotel in
Piccadilly, Manchester. The contractor claimed an extension of time as a
result of delay caused by variations and late information. The employer
argued that the alleged variations did not cause any delay because they
were not on the critical path and that the true cause of the delay was other
matters which were contractor-risk events.
30
Contract Sum
Adjustment
31
Provisions for CSA
32
Circumstance of CSA
36
Components Of Variation Claim
Scope of Work
Pricing of variation
Direct costs: actual performance (labour, plant,
materials)
Indirect costs: overheads, administration, and profit
Consequential costs: result of disruption, delay or
inefficiency
Evidence
Quotations, Quantities and rates, Sketches, drawings and
specifications, Photographs, Correspondence
Variation order instruction
Extension of Time (EOT) 37
a) necessitates a change:
I. to the Works
40
41
Progress
Claim
42
Progress Claim
Periodic payments
Milestone payments
Single or one-off
payments
The deposit: 5%
The slab or base stage: 15%
Frame stage: 20%
Lockup stage: 20%
Fit-out or fixing stage: 30%
Practical completion stage: 10%
Single Payments
Progress Claims
Principal
Contractor
Stakeholders
Progress claim
Subcontractor
Superintendent
Provisions for Progress Claims
& Payments
AS 4000– Cl. 37: Payment
Cl. 5 – Security
Ensure contractor performs its obligations
Protection against consequence of inability to perform
Cl. 4 – Retention
A percentage deducted from the amount due and retained by the
client
To be held as a set off in the event the contractor does not honour the
contract in regards to defects
The court upheld the decision and found that whether or not there had
been substantial performance of the work or such substantial defects that
the work was not carried out, was essentially a question of fact to be
determined on the evidence and circumstances of each case.
Final payment claim - AS4000 1997
63
Security of Payment (SOP)
To ensure that contractors and sub-contractors get paid for the work
that they have performed.
The Building and Construction Industry Security of Payment Act 2002
Provides a fast and inexpensive process to recover payments due under
a construction contract
Saves time and cost to engage lawyers
The VBA monitors the operation of the SOP Act. It does not nominate
adjudicators or take part in payment disputes. This is the role of
Authorised Nominating Authorities (ANAs), who are authorised by the
VBA to perform this service.
https://www.vba.vic.gov.au/building/security-of-payment
Despite the laws, SOP is an on-going issue in the Construction Industry
in AU.
55
Security of Payment (SOP)
Builders who are in financial difficulty and do not have the cash flow to
pay subcontractors.
https://www.youtube.com/watch?v=TQnD1AV5F3M