CADANGAN MEROBOH DAN MEMBINA SEMULA MASJID NURUL EHSAN, DI ATAS LOT 18645 &

11239 DI JALAN SERI CHERAS 6, TAMAN SERI CHERAS, MUKIM CHERAS, DAERAH HULU LANGAT,
SELANGOR DARUL EHSAN.

Item:- 225mm x 20mm Thick hardwood fascia board including painting

Qty Rate Amount


RM
225mm x 20mm thk tbr (m3) 0.0045 4,550.00 20.47
add 15.00% 3.07
23.55

Painting (m2) 0.265 5.00 1.33


add 15.00% 0.20
25.07

Say, RM 25.00/m

AncBldg2/roof/1
ACS ministrip ceiling panel in high tensile steel with Zinclume and colourbond
coated strips of module of size 75mm centre

Quote: ACS strip ceiling RM 67.29 per M2 delivered to site

Materials:

ACS strip ceiling 67.29

Waste 5% 3.36

Labour at RM 25.00 per M2 25.00

95.65

Profit 15% 14.35

Total Cost Per M2 110.00


CADANGAN MEROBOH DAN MEMBINA SEMULA MASJID NURUL EHSAN, DI ATAS LOT 18645 &
11239 DI JALAN SERI CHERAS 6, TAMAN SERI CHERAS, MUKIM CHERAS, DAERAH HULU LANGAT,
SELANGOR DARUL EHSAN.

150 mm x 20 mm Thick timber skirting

Amount
RM
1. Material (150 mm x 20mm timber) 4.40
2. Labour for fixing including forming coved & capping
0.43 hr X RM 80.00/8 hr 4.30
8.70

add 15.00% overhead + profit 1.31


Cost per metre RM 10.00
SAY RM 10.00
arm
35
Door

Supply and fix 900mm x 2100mm timber flush door complete with hinges and including painting

Description Unit Qty Rate (RM)

Supply door NO 1 86.00

Add
Labour cost
0.75/m2 x RM 94.60

Add
15% Profit & attendance

COST PER NO.

SAY
ing painting

Amount (RM)

86.00

86.00

64.50
150.50

22.58

173.08

173.00
CADANGAN MEROBOH DAN MEMBINA SEMULA MASJID NURUL EHSAN, DI ATAS LOT 18645
DAN 11239 DI JALAN SERI CHERAS 6, TAMAN SERI CHERAS, MUKIM CHERAS, DAERAH
HULU LANGAT, SELANGOR DARUL EHSAN.

Approved 1 hour fire rated door 1800 x 2100mm high

JKH RM
Supply & install fire door ref : CARPENTER/2005/1/9 1,201.00

Add
Profit + overhead 15% 180.15
1,381.15 /No.

Say, RM 1,381.15/No.
CADANGAN PEMBANGUNAN SEBUAH BANGUNAN BALAI POLIS 3 TINGKAT (KATEGORI A)
BERSERTA KEMUDAHAN BERKAITAN DAN 1 BLOK KUARTERS 18 TINGKAT MENGANDUNGI 6 UNIT
KUARTERS KELAS E DAN 150 UNIT KUARTERS KELAS F DI ATAS LOT 42567, MUKIM DAMANSARA,
DAERAH PETALING, SELANGOR DARUL EHSAN

BREAK-UP RATE

A. To Supply and install combination of high density ,medium density and low RM
density acoustic infill onto HW Frame finish with fabric ,plywood at lower area
including skirting

Supply and install 450.00

1Nos of door :1400mm x 2100mm


Total Area m2 1.89 m2

1Nos of door : 1.89 X RM450 850.50

Total 850.50
b.u.r/1
71 -

- as final by ARMPSB
259,647.00 FINAL FIGURE ON DISCUSSION
(259,647.00) + additional
CADANGAN PEMBANGUNAN SEBUAH BANGUNAN BALAI POLIS 3 TINGKAT (KATEGORI A)
BERSERTA KEMUDAHAN BERKAITAN DAN 1 BLOK KUARTERS 18 TINGKAT MENGANDUNGI 6
UNIT KUARTERS KELAS E DAN 150 UNIT KUARTERS KELAS F DI ATAS LOT 42567, MUKIM
DAMANSARA, DAERAH PETALING, SELANGOR DARUL EHSAN

BREAK-UP RATE

A. Supply and install polycarbonate fixed lourvers with aluminium frame RM


including all sealing the gap etc. all to manufacturer's detail specification

i. Supply and install polycarbonate fixed lourvers


(Refer quotation - Petaling Metalworks Fabrication Sdn Bhd) 350.00 /m2

ii. ADD - Profit & Overhead 15% 52.50


402.50 /m2

b.u.r/1
330.00
15%
379.50 20,113.50
APK N O. 3 - Pindaan pada ruang 1.46 (Kefeteria)

BUILT-UP RATE

Take down the installed timber door frame overall size


1800mm x 2100mm carting away debris from site and
making good work disturbed to received new works L.S.

Description Ref Unit Qty Rate

Total Qty involved = 2 nos completed brickwall


Resources = 2 general worker & 1 carpenter @ 1 days

Labour
Labourer SW/4/A Day 2 45.00
Carpenter and joiner SW/4/G Day 1 70.00

Sub-Total

Add 15 % (for ordinary plant, tools, scaffolding, supervision and profit)

Total
Amount

90.00
70.00

160.00

24.00

184.00
CADANGAN MEROBOH DAN MEMBINA SEMULA MASJID NURUL EHSAN, DI ATAS LOT 18645 &
11239 DI JALAN SERI CHERAS 6, TAMAN SERI CHERAS, MUKIM CHERAS, DAERAH HULU LANGAT,
SELANGOR DARUL EHSAN.

GRC plaster ceiling

Amount
RM
Material plasterceiling 30.00

Labour RM 80.00 /day/8 hr 2.650 hr 26.50


56.50

add 15.00% overhead + profit 8.48


64.98

Say, RM 65.00 / m2
arm
65 /m2