Road & Infrastructure in AL Ebb & Leabaib - Package 01

9. Lessons Learned

Responsible Personnel Evidence of Date


# Lesson Learned Applicable Process
(Full name, position) communication (DD, Month, YYYY)

The Contractor should


not take the risk of
proceeding with the
works without
1 conducting the required Drainage/Roads Yasser Ayman Quality Meeting 8-Nov-23
initial testing. Approved
ITP should be followed
and to be strictly
implemented.
No sub-base works at
the carriageway shall
2 proceed without an Drainage/Roads Yasser Ayman Quality Meeting 8-Nov-23
approved Utility
Clearance.
Importance of Initial
3 Deflection & Air Testing Drainage/Roads Sudhakar Jayaraman Email 20-Nov-23
@ Pipes'-
Trench Excavations Left
4 Open for Long periods Drainage/Roads Sudhakar Jayaraman Email 24-Dec-23
of Time
5 - - - - -