You are on page 1of 3

VESSEL NAME

FML PSC CHECKLIST - 2020 -2021

PERSON INCHARGE FOR BELOW CHECKS: THIRD ENGINEER

NAME

SIGN

DATE

S.NO AREA/EQUIPMENT ASSESSED

A ENGINE ROOM
1 PORTABLE AND FIXED FIREFIGHTING SYSTEMS YES NO REMARKS

Machinery space fire hoses are of correct length


a
(15m maximum) (Check Fire Plan)

1. Confirm Boiler burner location is provided with sand box Or a fire


extinguisher. (Which Type of Extinguisher)
b
2. Check & confirm Hoses & Nozzles are in good condition (No crack
or damage) for 40ltrs Fire Extinguisher near to Boiler.

1. Is Monthly inspection of extinguisher done and marked on the


c inspection tags.
2. Extinguisher Discharge Nozzles are satisfactory.

1. Are all EEBD / ELSA pressure checked and are showing full (Green
d Zone).
2. IMO symbols displayed next to each LSA / FFA Equipment.

Confirm Fire hoses in Engine room are in satisfactory condition and


e
Fire Nozzles are of 3 way type and greased.
1. Confirm all Fire doors in Engine room are closing fully by itself
otherwise adjusted self closure.
f 2. Check Fire Door safety lining (Steering Gear room, Purifier room ,
Engine room entrance, etc) is in satisfactory condition without any
damage.

2 AUXILIARY ENGINES AND EQUIPMENT YES NO REMARKS

1. Confirm all Auxiliary Engines are running satisfactory upto load of


80%.
2. Is there any leak in Aux Engine if yes, from where its leaking.
3. Are all alarms (Fuel Leak off / Low lub oil pressure / Reverse
a
power / Etc) tested and found in satisfactory condition. (DATE OF
ALARM TEST)
4. Are Gauges in good condition.
5. Is Quick closing valves tested.

1. Confirm Fire line isolating valve between the engine room (ER)
and deck has been tested for free operation. (Where is the Location
b
of Valve).
2. Isoation valve is colored Red and Direction Marked.

3 BOILER YES NO REMARKS


Confirm Boiler Trips and alarms are tried out and working DATE: _______
satisfactory.
1. Low Leval alarm
a
2. Burner failuer.
3. Low Low Level Alarm
(DATE OF ALARM TESTING)

Fire Extinguisher is at boiler platform checked and Hose are


b
satisfactory. (Which Type Of Extinguisher)

4 LIFE BOAT AND RESCUE BOAT YES NO REMARKS

a 1. Life Boat & Rescue Boat engine tried out and in good operational
condition.
2. Is Life boat and Rescue boat fuel tank more than 90% full.

b 1. Is Functioning of Rescue Boat Davit on all modes (Manual,


Accumulator & Pump) tested.
2. How much time it takes to slew davit (180 deg) on accumulator.

1. Confirm there are no Hydraulic leaks observed on Davit, lever &


c Gauges.
2. Is accummulator Pressure gauge is in good condition.
Check and confirm Rescue boat outboard engine cooling water
d
outlet jet is evident.

LifeBoats exhaust pipe lagging to be opened and inspected for any


e
wastage or leak (3 monthly). (Inspection Date)

5 LSA EQUIPMENT YES NO REMARKS

1. Life Jacket in Control Room is checked and in satisfactory


condition without any damage.
2. Is Life Jacket Light working. (Light expiry date)
a
3. Vessel Name is stenciled on Life jacket.
4. Is IMO symbol for Life Jacket is displayed in ECR.
5. How many Life Jackets are in Control Room.

1. Is Immersion Suits in ECR opened / checked and in satisfactory


condition without any damage to suit.
2. Confirm Immersion Suit Light in working condition.
b
(Light Expiry Date)
3. Vessel Name is stenciled on Life jacket.
4. Is IMO symbol for Immersion Suit is displayed in ECR.

Confirm Medical First Aid Kit in ECR have no expired medicines. All
c
expired items replaced handedover to 2nd officer.

6 DOCUMENTS YES NO REMARKS

a Boiler Test is carried out weekly and record maintained onboard.

Confirm in Engine room logbook Steering gear check & Fire safety
b round have to be recorded. (Same need to be carried out /
Recorded every watch)

7 MISC YES NO REMARKS

Is there any other concerns observed apart from above checks.


a
(PLS MENTION BELOW)