PRE-EXCAVATION CHECKLIST
Area Location:

DONE
ACTIONS REMARKS (√) INITIALS

KOLIN Technical Manager/Requesting Civil Engineer to attach and review


excavation drawing showing existing utilities and location on site.

KOLIN Technical Manager/Requesting Civil Engineer to arrange


demarcation of excavtion site.

KOLIN Technical Manager/Requesting Civil Engineer to arrange a site visit


of proposed excavation area with SAPMT Construction representative.

KOLIN Technical Manager/Requesting Civil Engineer to arrange sign-off of


TECHNICAL AND this checklist by all parties.
ENGINEERING
KOLIN Technical Manager/Requesting Civil Engineer to provide noification
other parties as required.

KOLIN Technical Manager/Requesting Civil Engineer to determine location


of underground (U/G) utilities, including requirements of Government
Departments if Excavation is off site.

KOLIN Technical Manager/Requesting Civil Engineerto verify operational


status and operating condition of U/G utilities.

KOLIN Technical Manager/Requesting Civil Engineer to arrange cable/pipe


detection equipment to locate utilities not shown on drawing and
unmarked in the field.

DONE
ACTIONS REMARKS INITIALS
(√)
Issuer, Reciever and Competent person to survey (visits) the excavation
site.

Issuer, Reciever and Competent person to review excavation drawing.


OPERATIONS

Issuer, Reciever and Competent person to de-energize known cables and


isolate piping, if possible, after coordination with other parties.

Competent person to advise Work Permit Issuer about precautions that


are required.
DONE
ACTIONS REMARKS INITIALS
(√)
Reviewed KOLIN Excavation safety requirement and implement applicable
measures
PERMIT RECIEVER
Double-check the area for unknown U/G utulities by using a cable/metal
detector in the presence of the WP issuer

Provide WP Issuer with this fully signed Pre-excavation checklist and


Excavation Drawing

TECHNICAL DEPARTMENT MANAGER REQUESTING CIVIL ENGINEER CONSTRUCTION MANAGER

____________________________ ____________________________ ____________________________


NAME, SIGNAURE & DATE NAME, SIGNAURE & DATE NAME, SIGNAURE & DATE

PERMIT ISSUER PERMIT RECIEVER COMPETENT PERSON

____________________________ ____________________________ ____________________________


NAME, SIGNAURE & DATE NAME, SIGNAURE & DATE NAME, SIGNAURE & DATE