Professional Documents
Culture Documents
Description Total
Sl.No Unit Rate Amount
Quantity
-
Dismantling of STP including removal of PCC, RCC, Masonry, Flooring, Structural
members and if any addition will be added and stacking the useful materials as
directed by the engineer-in-charge. The cost should also include the cost of
necessary lead, lift, loading, and unloading of material. Necessary permission to
be obtained from local authorities/ Owners of the dumping yard, no extra shall be
2 payable on this account. . The cost should be including of necessary excavations. L.S 1 385000 385,000
The vendor should visit the site and understand the work before submitting their
offer. Area to be verify by the vendor at site before submitting their offer. Nothing
will be pay additional. The rate should includes removal of equipment and
machine fitted on their.
-
Removal of existing tree including necessary cutting, transport, of various height
and diameter including removing the trunks, branches and rubbish , etc. and
disposal away from site including all lead. and all complete as directed by
3 Engineer in Charge. The rate is including uprooting of rank. Necessary permission EACH 52 12500 650,000
from relavant govt. authorties to be obtained for tree removal including disposal.
-
Removal and replanting of existing tree including including necessary Excavtion,
filling soil mixture of farmyard manure, red earth and river sand, etc and all
4 complete as directed by Engineer in Charge. If any trees damaged while removing EACH 144 19000 2,736,000
it should be disposed away from the site. It shall be measured under relevant item
of work.
5 Existing Road modification works. Sqm 100 19500 1,950,000