INSPECTION AND TEST PLAN FOR PIPING
Rev. 0
(Spot Inspection) S Inspection and checks during routing visits by Worley and/or Project. This inspection point does not require hold in work.
(Witness Point) W Worley and Project need to be informed in advance, but work will not be held. (See Note below for the exception on application of Witness Point).
(Review) R Review and approve documents such as Procedures, personnel qualification and NDE report by Worley and Project.
Inspection point where the work will not proceed until witnessing and signing work releasing Hold Points. The Project, Worley and/or Third-Party Inspectors are to be advised
(Hold Point) H by Construction and/or Construction Subcontractor, as applicable, of witness points. Hold points may not be waived by identified participants. Work may not proceed beyond
these mandatory Hold Points without witness by the identified participants.
Note: For rotating equipment installation ITPs, all identified inspection witness points (W) shall be handled as Hold (H) points as per API definition.In line with the 'specific' project Quality Control Assessments
Verification and Monitoring Procedures minimum notification requirements for typical Witness and Hold Points.
Doc. No.: PP-ITP-001
INSPECTION AND TEST PLAN FOR PIPING
Rev. 0
RESP / INSPECTION
VERIFICATION ACTIVITY SURVIEILLANCE CODE
OPERATIONAL ACTIVITY DESCRIPTION ACCEPTANCE CRITERIA RECORDS REMARK
DESCRIPTION
ABB WTL SCOT
2.1 Welder Qualification Test Qualify welder cover all work ASME Section IX. WQT Control Log H H/W S/R
Welder
To verify the internal weld defect and
2.3 RT examination ASME B31.3. Performance H R R
any imperfection defect
Record (FM-PP-012)
(FM-PP-008)
2.4 Welder certificate & welder card test Follow third party provide ASME Section IX.
(FM-PP-011) H R R
Doc. No.: PP-ITP-001
INSPECTION AND TEST PLAN FOR PIPING
Rev. 0
RESP / INSPECTION
VERIFICATION ACTIVITY SURVIEILLANCE CODE
OPERATIONAL ACTIVITY DESCRIPTION ACCEPTANCE CRITERIA RECORDS REMARK
DESCRIPTION
ABB WTL SCOT
3. MATERIALS
4. PIPE SUPPORTS
4.1 Fabrication Follow pipe support standard Follow pipe support standard - H S R
7. PRESSURE TEST
7.1 Air leakage test reinforcement pad No test until PT are complete ASME B31.3. (FM-PP-015) H H/W W/R If required
7.3 Punch list To be clear all A punch A punch close. (FM-PP-006) H H/W W/R
Doc. No.: PP-ITP-001
INSPECTION AND TEST PLAN FOR PIPING
Rev. 0
RESP / INSPECTION
VERIFICATION ACTIVITY SURVIEILLANCE CODE
OPERATIONAL ACTIVITY DESCRIPTION ACCEPTANCE CRITERIA RECORDS REMARK
DESCRIPTION
ABB WTL SCOT
Inspection Report
7.5 Valve test & pressure relief valves Project specification Project specification. H H W/R If required
by Third party
8. TIE-IN
WTL/SCOT to be confirm and
8.1 Survey Tie-in point Follow P&ID Required H H H
approve the Tie-in point.
(FM-PP-003)
8.2 Fabrication new pipe spool Follow isomeric drawing ASME B31.3./ASME Section IX. (FM-PP-004) H S/W S/R
(FM-PP-005)
NDE (PT, MT, RT, PAUT, FRTetc.) for ASME Section V./ ASTM B31.3 Inspection Report
8.3 Follow Project Specification H W R
new pipe spool (ASTM E562) by Third party