ERDMP AUDIT
• Earthing system to be properly maintained. Earth pit
resistance values (Individual & Grid) to be recorded and
displayed on the earth pit cover
• Work permit format to be strictly followed
• ERDMP awareness/ training programs to be regularly
conducted, It is a good tool to disseminate the
information
• Training on QRA & HAZOP analysis to be organized
• Regular testing of CO2 flooding system of the compressor
room to be carried out in CNG stations for the CGD
network
• Hazard distance, individual risk & societal risk to be
essentially covered in the ERDMP & all scenarios to be
covered
11
ERDMP AUDIT
12
AREAS OF CONCERN
• MORE AUDIT MAN DAYS MAY BE CONSIDERED FOR CGD
NETWORK, WHICH IS SPREAD ACROSS GEOGRAPHICALLY
IN DIFFERENT PARTS OF THE CITY
13