Title: Implementation of BRIGADA ESKWELA 2023

Goal: To improve and innovate activities to help secure the safety and health of all.
Outcome: Improve the knowledge ans skills, emnhance awareness of teachers, parents, learners and stakeholders in creating a safe healthy and conducive
environment.

IMPLEMENTATION PLAN 2022-2023

Responsible/Accountable Unit
Critical Action Timeframe Estimated Budget Budget Source
(FD)

What actions/activities must be Who is responsible for the When must the How much will it Where will the
completed to implement the policy? action/activity? action/activity be cost to implement funding come from?
completed? the action? (internal and
external funding
source)
OUTPUT 1 Brigada Eskwela Project & Activities
Activity 1  Putting up different informational
Project SAFE 2.0 signage’s at the premises of the
school.
 Conduct hazard mapping.
 Inspect the electrical Wiring of the August 14, 2023 –
School Head, DRRM 35,000.00
school Premises. July 2024 Donations
Coordinator
 Conduct the unannounced and
nationwide earthquake drills
 Update the Evacuation Area at the
school premises.
 Construction of DRRM Park
Activity 2  Rehabilitation of Different Park
Project GILAS  Repainting / Beautification of
August 14, 2023 –
Plant Box School Head, DRRM 50,000.00 Donations
July 2024
 Rehabilitation of Fish Pond Coordinator
 Pruning of Trees
 Construction of Drainage (Lgu)
Activity 3  Rehabilitation of Literacy Park
School head, DRRM,
Project Rise- Up  Enhancing the Reading Corner August 14, 2023 –
YES-o, Stakeholders 25,000.00 Donations
2.0 of Every Classroom July 2024
and learners
 Conduct of Numeracy and
Literacy
Activity 4  Repair of Rain Water Catcher
Project WATSAN  Repair of Faucet Every
` Washing Area
 Rehabilitation of Common Cr
 Repair of Water Outlet (Tubo) School head, DRRM,
 Yearly Water Test YES-o, Stakeholders and August 14, 2023 – 35,000.00 Donations
 Repair of Cr Every Classroom learners July 2024
 Repair of Lavatory
 Search for Most conducive
comfort room
 Enhancing and Beautification of
DESCAFE 2.0
Activity 5 School head, DRRM,
August 14, 2023 – Donations
PROJECT  Rehabilitation of Gulayan YES-o, Stakeholders 25,000.00
July 2024
EXPO-GP and learners
OUTPUT 2 Well-nformed internal and external stakeloders on the Brigada Eskwela Project & Activities indicated in the workplan.
Activity 1  Conducted Project SAFE launching
Project SAFE 2.0 activity. August 14, 2023 –
School Head, DRRM 35,000.00
 Disseminated planned activities to July 2024 Donations
Coordinator
targeted stakeholders thru: letters,
social media, flyers, tarpaulin
Activity 2  Conducted Project GILAS
Project GILAS launching activity. August 14, 2023 –
50,000.00 Donations
 Disseminated planned activities to School Head, BE Coordinator July 2024
targeted stakeholders thru: letters,
social media, flyers, tarpaulin
Activity 3  Conducted Project Rise- Up 2.0
School head, faculty
Project Rise- Up launching activity. August 14, 2023 –
Stakeholders and 25,000.00 Donations
2.0  Disseminated planned activities to July 2024
learners
targeted stakeholders thru: letters,
social media, flyers, tarpaulin
Activity 4  Conducted Project WATSAN School head, DRRM, August 14, 2023 – 35,000.00 Donations
Project WATSAN launching activity.
`  Disseminated planned activities to YES-O Coordinator
July 2024
targeted stakeholders thru: letters,
social media, flyers, tarpaulin
Activity 5  Conducted PROJECT EXPO-GP
PROJECT launching activity. School head, GP August 14, 2023 –
25,000.00 Donations
EXPO-GP  Disseminated planned activities to Coordinator July 2024
targeted stakeholders thru: letters,
social media, flyers, tarpaulin
OUTPUT 3 Implemented the target activities under Brigada Eskwela Project & Activities
Activity 1  Conducted assessment and
August 14, 2023 –
Project SAFE 2.0 inspection of the school environment. School Head, DRRM 35,000.00
July 2024 Donations
 Implemented the Project SAFE Coordinator
activities.
Activity 2  Conducted assessment and
August 14, 2023 –
Project GILAS inspection of the school environment. 50,000.00 Donations
School Head, BE Coordinator July 2024
 Implemented the Project GILAS
activities.
Activity 3  Conducted assessment in the School head, faculty
August 14, 2023 –
Project Rise- Up Dubinan Elementary School pupils Stakeholders and 25,000.00 Donations
July 2024
2.0  Implemented the Project Rise- Up learners
2.0 activities.
Activity 4  Conducted water testing from the
School head, DRRM,
Project WATSAN deepwell water August 14, 2023 – 35,000.00 Donations
YES-O Coordinator
`  Implemented the Project WATSAN July 2024
activities.
Activity 5  Conducted Assessment and
August 14, 2023 –
PROJECT inspection of gulayan area School Head, DRRM 35,000.00
July 2024 Donations
EXPO-GP  Implemented the Project EXPO-GP Coordinator
activities.
OUTPUT 4 Conducted post implementation review and monitoring evaluation on the conducted activities.
Activity 1  Prepared Accomplishment Report of School Head, DRRM August 14, 2023 – 35,000.00 Donations
Project SAFE 2.0 Project SAFE Coordinator July 2024
 Conducted Monitoring and
Evaluation on Project SAFE
 Reported accomplishment report to
stakeholders through Program
Implementation Review (PIR)
Activity 2  Prepared Accomplishment Report of
Project GILAS Project GILAS
 Conducted Monitoring and August 14, 2023 –
50,000.00 Donations
Evaluation on Project GILAS School Head, BE Coordinator July 2024
Reported accomplishment report to
stakeholders through Program
Implementation Review (PIR)
Activity 3  Prepared Accomplishment Report of
Project Rise- Up Project Rise-Up 2.0
School head, faculty
2.0  Conducted Monitoring and August 14, 2023 –
Stakeholders and 25,000.00 Donations
Evaluation on Project Rise-Up 2.0 July 2024
learners
 Reported accomplishment report to
stakeholders through Program
Implementation Review (PIR)
Activity 4  Prepared Accomplishment Report of
Project WATSAN Project WATSAN
`  Conducted Monitoring and School head, DRRM,
Evaluation on Project WATSAN August 14, 2023 – 35,000.00 Donations
YES-O Coordinator
Reported accomplishment report to July 2024
stakeholders through Program
Implementation Review (PIR)
Activity 5  Prepared Accomplishment Report of
PROJECT Project EXPO-GP
EXPO-GP  Conducted Monitoring and August 14, 2023 –
School Head, DRRM 35,000.00
Evaluation on Project EXPO-GP July 2024 Donations
Coordinator
 Reported accomplishment report to
stakeholders through Program
Implementation Review (PIR)
For School Level

Prepared by:

ANGELIKA D. RESPONZO
Name of Program Owner

Reviewed and Approved by:

MARJORIE D PILON
School Head

Recommending Approval:

JONATHAN A FRONDA PhD,CESE

Asst. Schools Division Superintendent

Approved:
FLORDELIZA C GECOBE Phd,CESO V

Schools Division Superintendent

You might also like