Professional Documents
Culture Documents
28.1 Introduction
An effective corrosion control program for a pipeline should contain the
following four components1:
• Understand the corrosion mechanisms prevailing during various phases
of operations including startup, steady-state operations, shut-in, etc.
• Formulate and implement mitigation measures according to the appro-
priate corrosion mechanisms.
• Validate the effectiveness of the corrosion mitigation measures by mon-
itoring corrosion at strategic locations.
• Verify the physical integrity of the pipeline by suitable inspection
activities.
This chapter describes several case studies where the use of the field sig-
nature method inspection tool has led to early warnings of the lack of
performance of the mitigation measures which, if left unchecked, could
result in more severe corrosion and eventually, failure.
658
© 2008, Woodhead Publishing Limited
Corrosion monitoring using the FSM-IT 659
monitors internal corrosion over a large area and can differentiate between
general corrosion and isolated pitting thanks to the matrix design where
general corrosion affects all pin pair responses and pitting corrosion only
affects nearby pin pairs.
K-3 12˝ FSM-IT accumulated wall loss trends and corrosion rates
7.0
Pitted area #1 -Accumulated NEW wall loss detected
6.5 in ADDITION to the original 2.0 mm pit depth
Pitted area #2 -Accumulated NEW wall loss detected
6.0
in ADDITION to the original 3.76 mm pit depth
5.5 Pitted area #1 Corrosion rate
4.5
Metal loss (mm)
4.0
3.5
3.0
2.5 35
FSM-IT readings (mm/yr)
Corrosion rate between
2.0 30
25
1.5 20
1.0 15
10
0.5
5
0.0 0
Sep 14
Sep 16
Sep 18
Sep 20
Sep 22
Sep 24
Sep 26
Sep 28
Sep 30
Oct 02
Oct 04
Oct 06
Oct 08
Oct 20
Oct 22
Oct 24
Oct 26
Oct 28
Oct 30
Nov 03
Nov 05
Nov 07
Nov 09
Oct 12
Oct 14
Oct 16
Oct 18
Oct 10
Nov 13
Nov 15
Nov 17
Nov 19
Nov 01
Nov 11
The line was shut down and FSM-IT device was installed ‘over’ existing pits.
The monitoring was started in September 2004.
Results
Figure 28.4 shows the monitoring results. Area 1 had an original pit depth
of 2.0 mm and was growing at a maximum rate of over 25 mm/y as detected
by FSM-IT. Area 2 had an original pit depth of 3.8 mm and was growing at
Benefits
Because of the timely detection of high corrosion rate by the FSM-IT
device, action was taken to cut out the section of the corroded pipe. In
adjacent areas not covered by the device, corrosion rate as high as 75 mm/y
was observed at the deepest pits. It was learned that it was difficult to miti-
gate deep pits with continuous-injection inhibitors. This FSM-IT monitoring
program effectively prevented sour gas leak under river.
Results
Figure 28.5 shows the monitoring results. Significant corrosion was detected
from June 2002 with indicated wall loss of 87% as of January 2003.
Benefits
Because of the timely detection of high corrosion rate by the FSM-IT
device, action was taken to cut out the section of the corroded pipe (Figure
28.6). It was learned that changing operations (plunger lift) resulted in more
severe corrosivity/fluid flows. Actual wall loss was 44% and actual corrosion
rate of 5 mm/y allowed re-calibration of software. The second sour gas leak
was prevented.
4˝ Sour gas pipeline – FSM-IT detection of isolated pit defect initiation and growth
3.5
3.0
2.5
Wall loss (mm)
2.0
1.5
1.0
0.5
0.0
Jan 01,01
Feb 01,01
Mar 01,01
Apr 01,01
May 01,01
Jun 01,01
Jul 01,01
Aug 01,01
Sep 01,01
Oct 01,01
Nov 01,01
Dec 01,01
Jan 01,02
Feb 01,02
Mar 01,02
Apr 01,02
May 01,02
Jun 01,02
Jul 01,02
Aug 01,02
Sep 01,02
Oct 01,02
Nov 01,02
Dec 01,02
Jan 01,03
28.5 Case study 2: corrosion monitoring responses.
installed on the two adjacent old/new pipes (Fig. 28.7) and another one on
one elbow. Corrosion monitoring was started in June 2002.
Results
Figures 28.8 and 28.9 show the monitoring results: 70% wall loss on old
pipe, 52% on new one as of November 2002. On-going corrosion rate was
in good trending agreement with LPR and ER (located in the plant further
upstream) probe readings.
Benefits
Because of the timely detection of high corrosion rate by the FSM-IT
devices, action was taken to cut out both new/old sections of the corroded
pipe (Figure 28.10). It was learned that there was a slight difference in
new/old pipe corrosion. The data was useful in evaluating further mitigation
strategy.
FSM-IT accumulated GENERAL CORROSION wall loss trends and corrator ER probes
8.5
8.0 Downstream "New Pipe" FSM-IT (long term corrosion rate: 22 mpy)
7.5 Aurora ER probe metal loss at FSM reading dates (long term corrosion rate: 14.7 mpy)
7.0 Upstream (Old Pipe) FSM-IT (long term corrosion rate: 15.5 mpy)
6.5
3D Bend FSM-IT (long term corrosion rate: 11.3 mpy)
6.0
Base Plant ER probe metal loss at FSM reading dates (long term corrosion rate: 6.2 mpy)
5.5
Metal loss (mils)
5.0
4.5
4.0
3.5
3.0
2.5
2.0
1.5 Brush
launched
1.0 then
Seven
Three day double
0.5 One day Brush
day outage dose of
outage pig chemical
0.0 outage
Sep 02, 02
Sep 05, 02
Sep 08, 02
Sep 11, 02
Sep 14, 02
Sep 17, 02
Sep 20, 02
Sep 23, 02
Sep 26, 02
Sep 29, 02
Aug 03, 02
Aug 06, 02
Aug 09, 02
Aug 12, 02
Aug 15, 02
Aug 18, 02
Aug 21, 02
Aug 24, 02
Aug 27, 02
Aug 30, 02
Nov 01, 02
Jun 25, 02
Jun 28, 02
Jul 01, 02
Jul 04, 02
Jul 07, 02
Jul 10, 02
Jul 13, 02
Jul 16, 02
Jul 19, 02
Jul 22, 02
Jul 25, 02
Jul 28, 02
Jul 31, 02
Oct 02, 02
Oct 05, 02
Oct 08, 02
Oct 11, 02
Oct 14, 02
Oct 17, 02
Oct 20, 02
Oct 23, 02
Oct 26, 02
Oct 29, 02
28.8 Case study 3: corrosion monitoring responses from FSM-IT and
ER probes.
Accumulated wall loss trends for PITTING corrosion; FSM-IT and LPR
32
31
30
29 LPR @ Base Plant, Accumulated wall loss at FSM reading dates (long term corr rate: 80 mpy)
28
27 Downstream "New Pipe" FSM-IT (long term corrosion rate: 65 mpy)
26
25
3D Bend FSM-IT (long term corrosion rate: 58 mpy)
24
23
22 Upstream "Old Pipe" FSM-IT (long term corrosion rate: 45 mpy)
21
20
19
Metal loss (mils)
18
17
16
15
14
13
12
11
10
9
8
7
6 Brush
5 Seven
launched
4 day
then
3 Three outage
Brush double
2 One day day
pig dose of
1 outage outage
chemical
0
Jun 25, 02
Jun 28, 02
Jul 01, 02
Jul 04, 02
Jul 07, 02
Jul 10, 02
Jul 13, 02
Jul 16, 02
Jul 19, 02
Jul 22, 02
Jul 25, 02
Jul 28, 02
Jul 31, 02
Aug 03, 02
Aug 06, 02
Aug 09, 02
Aug 12, 02
Aug 15, 02
Aug 18, 02
Aug 21, 02
Aug 24, 02
Aug 27, 02
Aug 30, 02
Sep 02, 02
Sep 05, 02
Sep 08, 02
Sep 11, 02
Sep 14, 02
Sep 17, 02
Sep 20, 02
Sep 23, 02
Sep 26, 02
Sep 29, 02
Oct 02, 02
Oct 05, 02
Oct 08, 02
Oct 11, 02
Oct 14, 02
Oct 17, 02
Oct 20, 02
Oct 23, 02
Oct 26, 02
Oct 29, 02
Nov 01, 02
The previously corroded line was cut out and FSM-IT device was installed.
The monitoring was started in October 2002.
Results
Figure 28.11 shows the monitoring results: an alarm of 66% wall loss and
19 mm/y corrosion rate.
Benefits
Because of the timely detection of high corrosion rate by the FSM-IT
device, action was taken to shut down the pipeline, cut out the corroded
pipe (Fig. 28.12) and in-line inspection of the remaining line. Actual wall
loss was measured at 41%. The current inhibition program was not effective.
A sour gas leak was prevented.
6˝ Sour Gas Pipeline – FSM-IT PinPairs detecting isolated pit defect initiation and growth
2.500
Date: 31-Mar-03
0:00
2.250
Wall loss Fsm matrix area surface plot
(mm) 64 65 66 67 68 69 70 71 72 73 74 4:30
2.000
1.80–2.00
53 54 55 56 57 58 59 60 61 62 63 5:00
1.60–1.80
1.750 1.40–1.60
38 39 40 41 42 43 44 45 46 47 48 5:30
Wall loss (mm)
1.20–1.40
PinPair 20
1.00–1.20 27 28 29 30 31 32 33 34 35 36 37 6:30
1.500
0.80–1.00
0.60–0.80 12 13 14 15 16 17 18 19 20 21 22 7:00
1.250 0.40–0.60
0.20–0.40 1 2 3 4 5 6 7 8 9 10 11 7:30
0.00–0.20
1.000 0.00
0
17.5
52.5
87.5
122.5
157.5
192.5
227.5
262.5
297.5
332.5
367.5
mm
0.750 PinPair 21
0.500
PinPairs 9, 19, 35
0.250
0.000
Oct 18, 02
Oct 22, 02
Oct 26, 02
Oct 30, 02
Nov 03, 02
Nov 07, 02
Nov 11, 02
Nov 15, 02
Nov 19, 02
Nov 23, 02
Nov 27, 02
Dec 01, 02
Dec 05, 02
Dec 09, 02
Dec 13, 02
Dec 17, 02
Dec 21, 02
Dec 25, 02
Dec 29, 02
Jan 02, 03
Jan 06, 03
Jan 10, 03
Jan 14, 03
Jan 18, 03
Jan 22, 03
Jan 26, 03
Jan 30, 03
Feb 03, 03
Feb 07, 03
Feb 11, 03
Feb 15, 03
Feb 19, 03
Feb 23, 03
Feb 27, 03
Mar 03, 03
Mar 07, 03
Mar 11, 03
Mar 15, 03
Mar 19, 03
Mar 23, 03
Mar 27, 03
Mar 31, 03
28.11 Case study 4: corrosion monitoring responses.
Results
Figure 28.13 shows the monitoring results. A maximum corrosion rate of
3.5 mm/y was indicated. The monitoring results will be validated in future
in-line or UT inspection.
48˝ Oil Transmission Pipeline – corrosion activity detected by FSM-IT vs. batch inhibitor treatments
6.0
5.5 Peak corrosion rates
detected by the most
5.0 Batch inhibition active PinPairs
Corrosion rate (mm/yr)
3.5
3.0
2.5
2.0
1.5
1.0
0.5
0.0
Jan 18, 03
Feb 07, 03
Feb 27, 03
Mar 19, 03
Apr 08, 03
Apr 28, 03
May 18, 03
Jun 07, 03
Jun 27, 03
Jul 17, 03
Aug 06, 03
Aug 26, 03
Sep 15, 03
Oct 05, 03
Oct 25, 03
Nov 14, 03
Dec 04, 03
Dec 24, 03
Jan 13, 04
Feb 02, 04
28.13 Case study 5: corrosion monitoring responses.
Benefits
Batching activities were found to be correlated to corrosion readings and
hence could be optimized using FSM-IT results. The line will continue to
operate until an alarm level is reached.
Results
Figure 28.14 shows monitoring results. From October 2001 to June 2002,
average corrosion of 2 mm/y (80 mpy) was detected. After October 2002,
average corrosion of 5 mm/y (200 mpy) was detected.
Benefits
Because of the timely detection of high corrosion rate by FSM-IT, the line
was shut down and a weld overlay was installed as the inhibition was not
70
60 80 mpy average corrosion rate
50
40
Corrosion rate
30 Increase to over
20 200 mpy
10
0
–10
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
28/09/2001 to 12/09/2002
28.2.7 Summary
In the six case studies, FSM-IT as a corrosion monitoring tool has been
successfully used in monitoring the mitigation effectiveness and has been
found beneficial in preventing sour gas leaks in four cases, and in providing
useful data for further evaluation in the other two.
28.3 Acknowledgments
The sharing of corrosion experience and monitoring information by Ray
Goodfellow and Jason Thomas of Chevron Texaco Canada, Harley Fear
of Shell Canada, Ben Kitt and Dave Webster on behalf of Syncrude, Mike
Johnson of Talisman and Tanis Elm and Joe Boivin of/on behalf of Enbridge
is acknowledged and greatly appreciated.
28.4 References
1 Nguyen N. Bich, ‘An Approach to Corrosion Mitigation for Wet Gas Pipelines’,
4th International Pipeline Conference, 29 September–3 October 2002, Calgary,
Canada, Paper IPC02-27417.