CIREBON 2, 1X1000MW COAL FIRED POWER PROJECT,

INDONESIA

SITE ACCEPTANCE TEST REPORT


Pituin Sukses Energi
400V LV SWGR PROTECTIVE SETTING RELAY
Location Feeder No. Feeder Name Date
COAL HANDLING
P2BGA02GS002 BELT CONVEYOR (BC-07A)
SYSTEM
I. SETTING RELAY
Checked
1 PHASE TOC 1 Value
OK N/A
a Phase TOC 1 Function Trip

b Phase TOC 1 Pickup 0.8 CT

c Phase TOC 1 Curve IEC Curve B

d Phase TOC 1 TDM 4

e Phase TOC 1 Reset Instantaneuos

f Phase TOC 1 Direction Disable

g Phase TOC 1 Relays Operate

h Phase TOC 1 Block 1 Off

i Phase TOC 1 Block 2 Off

j Phase TOC 1 Block 3 Off


Checked
2 PHASE IOC 1 Value
OK N/A
a Phase IOC 1 Function Trip

b Phase IOC 1 Pickup 6.8 CT

c Phase IOC 1 Delay 0.1 sec

d Phase IOC 1 Direction Disable

e Phase IOC 1 Relays Operate

f Phase IOC 1 Block 1 Off

g Phase IOC 1 Block 2 Off

h Phase IOC 1 Block 3 Off


Checked
3 GROUND TOC 1 Value
OK N/A
a Ground TOC 1 Function Trip

b Ground TOC 1 Pickup 0.2 CT


b Ground TOC 1 Pickup 0.2 CT

c Ground TOC 1 Curve Definite Time

d Ground TOC 1 TDM 0.1

e Ground TOC 1 Reset Instantaneuos

f Ground TOC 1 Direction Disable

g Ground TOC 1 Relays Operate

h Ground TOC 1 Block 1 Off

i Ground TOC 1 Block 2 Off

j Ground TOC 1 Block 3 Off


Checked
4 GROUND IOC 1 Value
OK N/A
a Ground IOC 1 Function Disable

b Ground IOC 1 Pickup -

c Ground IOC 1 Delay -

d Ground IOC 1 Direction -

e Ground IOC 1 Relays -

f Ground IOC 1 Block 1 -

g Ground IOC 1 Block 2 -

h Ground IOC 1 Block 3 -


Checked
5 PHASE UV Value
OK N/A
a Phase UV Function Trip

b Phase UV Pickup 0.8 VT

c Phase UV Curve Definite Time

d Phase UV Delay 2 sec

e Phase UV Phases All Three

f Phase UV Min Voltage 0.1 VT

g Phase UV Relays Operate

h Phase UV Block 1 Off

i Phase UV Block 2 Off

j Phase UV Block 3 Off


Note :

Tested by: Witnessed by: Approved by:


PT Pituin Sukses Energy Dong Hwa Hyundai Cirebon Power