You are on page 1of 19

Doc.

No: HSE-FM-060
BM CONSULTING ENGINEERS
Revision: 00
Function: Health, Safety and Environmental Date: 11/03/2024
Author: Dumisani Nyambi Page: 1 of 19

Baseline Risk Assessment


Site: Engineering procumentant construction (EPC)/Turkey-Key Services for the Construction of New UNISA Nelspruit Learner on the site Portion 8Erf
3411, Nelspruit Extension 29, 24 Jerepico Street
Name and Surname: Date: Signature:
Created by: Dumisani Nyambi 10/03/2024
Approved by: Lerato Mashigo 10/03/2024
Next Review Date: 09/03/2025

Risk Assessment Guide:

Procedure for conducting the Risk Assessment:


1) Identify and list all hazards in the area being assessed.
2) Quantify each hazard i.e. 30kg Packages handled, 200 liters diesel or 7 people exposed etc.
3) Identify the Risks associates with each hazard i.e. Back injuries, fire and electricity shock.
4) Consider the existing control measures and then rank the risk from each hazard, using the scoring chart below
5) Complete and distribute an action list to minimize/ remove all risks identified according to risk priority list.
6) If the risk is Medium or High then further control is required if technically possible. For Low risk further control is only required if economically
viable
7) Any Very High risk activity or situation must be rectified immediately.

Each Safe Operating Procedure lists all the steps in the Activity, the Potential Risk, and Control/Preventative
Steps and Immediate Corrective Action In Case of Emergency.
Doc. No: HSE-FM-060
BM CONSULTING ENGINEERS
Revision: 00
Function: Health, Safety and Environmental Date: 11/03/2024
Author: Dumisani Nyambi Page: 2 of 19

Probability Index

SEVERITY/ CONCEQUENCE INDEX= INJURY FREQUENCY RISK INDEX


PROBABILITY INDEX
INDEX INJURY LOSS SCORE CATEGORY ACTION PRIORITY
1 Inevitable 10 Fatal 10 No production 10 Permanently 41-50 A Very High Risk Immediate
0 present
9 Almost certain 9 Permanent total 9 One month production loss 9 Arises every 31-40 B High Risk Within a month
disability 30 seconds
8 Very likely 8 Permanent slight 8 3 weeks production loss 8 Arises every 21-30 C Medium Risk Within 3 months
disability 30 minutes
7 Probable 7 <14 days with 7 2 weeks production loss 7 Arises every 11-20 D Low Risk Within 6 months
remaining incapacity 30 minutes
6 More than 6 14 days with complete 6 1 week production loss 6 Arises every 1-10 E Very Low Risk Within a year
even chance recovery hour
5 Even chance 5 3-14 days with 5 1 day production loss 5 Arises every
complete recovery shift
4 Less than even 4 3 days with complete 4 50 man-shifts lost 4 Arises every
chance recovery week
3 Improbable 3 Loss of one or more 3 15 man-shifts lost 3 Arises every
shifts month
2 Highly 2 Medical case 2 3 man-shifts lost 2 Arises every
improbable year
1 Impossible 1 First aid case 1 1 man shift lost 1 Arises every 5
years
Doc. No: HSE-FM-060
BM CONSULTING ENGINEERS
Revision: 00
Function: Health, Safety and Environmental Date: 11/03/2024
Author: Dumisani Nyambi Page: 3 of 19

Risk Rating Table

RISK RANKING TABLE SEVERITY


1 2 3
DEPARTMENT: EXPOSURE FREQUENCY MINOR INCIDENCE MAJOR DEATHS OR
INCIDENCE DISABLING
PROBABILITY 1 0-50% OF SECTION RARE OCCURRENCE OR 2 3 4
UNLIKELY
2 50-75% OF SECTION INFREQUENT 3 4 5
OCCURRENCE OR LIKELY
3 75-100% FREQUENT 4 5 6
OCCURRENCE OR VERY
LIKELY

KEY: VERY HIGH RISK - 6


HIGH RISK - 5
MEDIUM RISK - 4
LOW RISK- 3
VERY LOW RISK- 2
Doc. No: HSE-FM-060
BM CONSULTING ENGINEERS
Revision: 00
Function: Health, Safety and Environmental Date: 11/03/2024
Author: Dumisani Nyambi Page: 4 of 19

Hazard Prompts

Fire: Mechanical: Hazardous Substances: Workplace: Physical agents:


 Arson  Trapping  Oils  Confined space  Noise
 Cutting/ Welding/  Auto start  Chemicals  Work at heights  Vibration
Grinding  Entanglement  Contaminated  Lightning  Stored energy
 Sources of ignition  Impact water  Dust (weights)
 Flammable  Ejection  Resins  Gases Vapor  Compressed air/
materials/ Liquids  Machine failure  Acids(e.g. Batteries)  Irritants (fibers) fluids
 Chemical reaction  Contact  Release of  Unstable equipment  Steam / Heat
 Spontaneous  Inadequate / no substances  Sharp/ protruding Biological agents:
Combustion guards  Inadequate storage parts  General infections
 Gases  Badly positioned  Lubricants  Uneven floor  Contaminated
 Lightning controls  Fuel  Difficult access water/ spray
 Electrical Faults  Machine  Additives  Ergonomic design
 Overheard movements  Solvents
Machines  Vehicular traffic  Bleach/ Cleaning
 Friction  Fluids)
 Combustible
Materials
Moving Machinery: Ergonomics: PPE Induced: Hazardous Objects: Human factors:
 Pedestrians  Manual handling  Sharp objects  Stress
 Nip points  Poor posture  Exhaustion  Hot/ Cold  Peer pressure
 Driver/ Passenger  Bad working  Dehydration  Heavy  Monotony
protection position  Restricted Hearing /  Unbalanced  Complacency
 Driver Competence Vision  Moving  Lack of training
 Traffic control  Increased stress  Abrasive  Claustrophobia
 Road/ Track
condition
 Suitability of
machine
 Maintenance
 Safety Devices
Doc. No: HSE-FM-060
BM CONSULTING ENGINEERS
Revision: 00
Function: Health, Safety and Environmental Date: 11/03/2024
Author: Dumisani Nyambi Page: 5 of 19

Occupational Hygiene: Environment & Health Electrical : Communication Bad Ventilation:


 Sanitation Hazards:  Arcing  Hand signals  Suffocation
 Diseases  Isolation/Permit  2way radios  Poisoning
 Radiation  Water pollution  Earthling  Telephones  Confined space
 Thermal Stress  Air pollution  Bridging out  Whistles  Welding fumes
 Mental Workload  Insects  Failed trips  Chemical vapors
 Noise  Snacks  Tampering  Fire/ Explosion
 Smoke  Wind  Power Failure
 Heat  Oil spills  Cable Damage
 Vibrations  Chemicals  Wrong wiring
 Poor lightning/  Dust  Shock/ Burns
Glare  Noise  Secondary accidents
 Waste
 Fires
 Weather
Pressure Systems: Moving parts of Slipping, Tripping & Hazardous Objects: Pressure Systems:
 Hydraulic systems Machinery: Falling:  Sharp objects  Hydraulic systems
 Air/ Water pipes  Floor conditions  Hot/ Cold  Air/ Water pipes
 Gas cylinders  Operator protection  Falls from heights  Heavy  Gas cylinders
 Pressure vessels  Machine guards  Wet conditions  Unbalanced  Pressure vessels
 Lock-out  Oil and grease  Moving
 Smooth surfaces  Abrasive
 Loose cables,
Equipment, tools and
material in walkways or
working areas
Doc. No: HSE-FM-060
BM CONSULTING ENGINEERS
Revision: 00
Function: Health, Safety and Environmental Date: 11/03/2024
Author: Dumisani Nyambi Page: 6 of 19

HSE Hazard Identification and Control Measure

No Potential Hazardous Event Current/ Existing Controls Potential Risk Rating Additional measures
Shortcomings
1  Pre- and post-medical  Failure of  Obtain feedback from medical
examination of all personnel as medical examination. practitioners regarding status of staff
per legislation. Low examined.
Working at heights and/ or  Disciplinary codes/ actions
confined spaces.  Replacement of personnel
 Control by TBN Suppliers
and/or THEIR AGENT.
2  Correct coupling of Non-adherence to  Continuous monitoring,
Compressed air usage. hoses, use of PPE, non- use for standards. Low audits
cleaning clothes or body, no
leaks in hoses, and no kinks in
hoses.
3  TBN Suppliers Site Deviation from  Tool box Talks
establishment procedure procedure.  Risk assessment on area
Site lay-out Site risk assessment not Medium before site is established to determine
adequate where areas have to be changed and
where what will go
4  Provide sufficient and  Loss of Medium  Dual System with cell phones
reliable communication systems. communication. and 2-way radios and clients land lines.
 Communication signs  No adherence  Audits by TBN Suppliers and/
and call signs to standard procedures. or their agent
Loss of communication  Test communication
system in advance
 Report back on regular
basis as per requirements during
conversion.
 Training on
communication system
5 Documentation control system.  Lost  Verify documentation.
Lost documentation documentation Medium  Controlled filing system.
Doc. No: HSE-FM-060
BM CONSULTING ENGINEERS
Revision: 00
Function: Health, Safety and Environmental Date: 11/03/2024
Author: Dumisani Nyambi Page: 7 of 19

Document control procedure to  Unsigned  Duplicate filing system-


be in place. documents scanning of documents on
Documents to be incorporated in  CD.
job card  Audits by TBN Suppliers and/
Ensure documents are received or their agent.
by the relevant supervisors
Sweepers and fitter controllers
take responsibility of all
documentation, signing thereof
and returning to Project office.
6  Comply with asset/  Loss of  Stock taking-verifying of
material/ security control productivity required materials for each phase to
system.  Delay in be done 1 week before phase.
 Security control system obtaining spares/ tools  Purchasing of additional,
Theft and loss of tools, materials  Asset/ material/security Medium material can be done at local agent.
and vehicles control system.  Disciplinary action-dismissal.
 Double checking of all,
materials to be issued.
 Responsibility of
material before issuing-Client/ or
the agent.
 After issuing –TBN
Suppliers
 Trend analysis of
materials lost after each phase.

7  Good human relations  Personnel  Incentive/ completion bonus.


 Signed agreements with absent/ sick  Incentive schemes
each personnel stating duration  Disciplinary action.
of employment, hours of work Medium
Personnel absent/ turnover. etc.
 Lucrative bonus system.
 No pro-rata bonuses to
be paid.
Doc. No: HSE-FM-060
BM CONSULTING ENGINEERS
Revision: 00
Function: Health, Safety and Environmental Date: 11/03/2024
Author: Dumisani Nyambi Page: 8 of 19

 Placement within the


network conversion.

8  Plant induction/  Injuries/  Risk assessments to be done


informed as per legal Incidents due to at all clients/ customers where no
requirement. unknown risks or information is available.
 Hazards and risks hazards. Medium  Client/ or their agent to
Injury/ incidents due to unknown identified by Client/ or their inform TBN Suppliers of these hazards
high risks. agent and conveyed to. TBN and risks per client.
Suppliers  All incidents no matter how
 Do plant specific small to be reported.
inductions with risks been
specified.
 Inform client of work
hazards or risks
 Client/ customer
supervision required.
 Liaison with customer
before conversion takes place.
 Liaison with Safety
Department, clarification of risks
not covered by customers/
clients.

9  Adherence to client  Non- Medium  Continuous monitoring,


Environmental pollution specific requirements as well as adherence to specific audits.
Client requirements. site requirements.
10  Comply with legal  Ensure correct placement of
requirements.  Injuries. individuals
 Provide additional/  Damage  Audits by TBN Suppliers and
specialized training as required.  Project delay. Medium Client/ or their agent.
Employee incompetence.  Client induction
training- risks
 TBN Suppliers induction
training
Doc. No: HSE-FM-060
BM CONSULTING ENGINEERS
Revision: 00
Function: Health, Safety and Environmental Date: 11/03/2024
Author: Dumisani Nyambi Page: 9 of 19

 All training done before


conversion starts.
 Verification of skills
 Records of all training to
be obtained and copies to Client/
or their agent.
11  Adhere to Road traffic  Loss of  Disciplinary codes
act and OHS Act 85 of 1993. productivity.  Accident reporting and
Hijacking, accidents, vehicle road  Proof of valid driver’s  Project delays Medium investigations.
worthiness. Drivers licenses, license.  Damage to  Audits by TBN Suppliers and
break downs  Obtain public drivers vehicles Client/ or their agent.
permit for driver if transporting  Civil and
more than 10 passengers. criminal liability
 Policy in place regarding  3rd party
speeding and traffic rules and claims.
regulations
 Awareness of hijacking
to be discussed.
 Vehicle tracking systems
to be installed
 Daily vehicle checklist
procedure
 Allocated drivers to be
placed on
12 Noise  PPE-Matrix, noise  No use of PPE Medium  Continuous monitoring
control.  No training
Survey done
13 Dusts  PPE- permits  Non Medium  Continuous monitoring
 PPE Matrix adherence
14  Checks by users and  Using of Medium  Ongoing checks and training
Use of hand tools store man. Correct tools for job. dangerously worn tools. and toolbox talks. Enforcing SMP
Lanyards on tools when working Tools lying loose on requirements
on elevated positions. platforms. No lanyards
used.
Doc. No: HSE-FM-060
BM CONSULTING ENGINEERS
Revision: 00
Function: Health, Safety and Environmental Date: 11/03/2024
Author: Dumisani Nyambi Page: 10 of 19

15  Training on the hazards  Non- Medium  Continuous monitoring


Handling Hazardous chemical identified as per Material data adherence to MSDS
substances sheets of HCS’s, and the correct requirements.
and safe manner of discarding  No training
waste products without pollution done.
hazards
16 Noncompliance to legal  Adhere to OHS Act 85 of
requirements 1993 and regulations, safe work
procedures and individual client  Non
requirements. adherence to standard High
 Need analysis on all and existing controls.
legal requirements-TBN  Investigation of incidents and
Suppliers accidents.
 Risk assessments on all  Emergency procedure
activities and equipment-TBN required
Suppliers  Audits by TBN Suppliers and/
 Compile SHE plan and or their agent.
implementation schedule  Strong disciplinary action.
 Procedures and safe (Dismissal)
work TBN Suppliers Adherence
to SOP, implementation and
maintaining of procedures.
 Training of personnel
before commencement of
conversion.
 Statistical reporting on
monthly basis.
 Reporting to DoL
(Department of Labour) when
working higher than
3 meters
 Supply letter of good
standing to Client/ or their
agent- TBN Suppliers
Doc. No: HSE-FM-060
BM CONSULTING ENGINEERS
Revision: 00
Function: Health, Safety and Environmental Date: 11/03/2024
Author: Dumisani Nyambi Page: 11 of 19

 Copies of legal
appointments to Client/ or their
agent.
17  Lock out procedures  Use of Ensure all personnel are trained in the
used. defective equipment. use and handling of electrical and
 Inspections on  Inspections rotating equipment/ tools.
Rotating equipment electrical equipment and installations. not done Ensure that all tools and equipment
tools handling and maintenance  WSOP (Written Safe  Not following High has been cleared by qualified person
of electrical installations Operating Procedures) WSOP. (Electrician).
 WSWP (Written Safe  Not following Ensure that registers are u8pdated
Work Procedures) WSWP regularly.
 Registers are updated  Not updating
and kept up to date frequently. registers
 Trade related training as
well as on the job training.
18 Electrical power tools  Checks by Store man  Non reporting High Ongoing checks and training and
and users, training in usage, defects, use of tools toolbox talks
inventory and checklists without authority
19 Snakebite.  Careful removals of  Non High Continuous inspections and talks
material to ensure no snakes are adherence of safe
under or inside. Use of PPE. procedure.
Reminders during team talks.
Remove bitten patient plus
snake if possible take to hospital
20 Lifting equipment and gear  Checks by Store man  Incorrect use High  Ongoing checks and training
and users, training in usage, of gear and equipment. and toolbox talks.
inventory and checklists.
21 Steel erection activities.  PPE.  Checking holes  All personnel to stand away
 Toolbox talks. of steel for alignment when lifts are done.
 Safety lanyards for tools with fingers.  All tools to be slung on arm
to prevent falling objects.  Losing balance when not used.
 Personnel receive on and falling.
High  No homemade tools to be
the job training for working with  Falling tools. used.
steel and on elevated heights.
Doc. No: HSE-FM-060
BM CONSULTING ENGINEERS
Revision: 00
Function: Health, Safety and Environmental Date: 11/03/2024
Author: Dumisani Nyambi Page: 12 of 19

 Use of  Condition of tools to be


homemade tools. checked by supervisor before work
 Condition of starts.
tools.  Supervisor to enforce the
wearing of safety harness with double
lanyards.
22 Boom extension and operation of  Crane to boom down  Crane driver High  Driver to be informed of all
the crane in the construction completely when driving under ignores warnings and the danger/ hazards identified before
area. structures. damages structures and driving to site commences.
 Flagmen to be present or equipment.  Supervisor to observe at all
during whole operation.  Supervision times for overhead hazards.
 Continuous supervision not present when work  Flagmen to be used in places
for whole mobilization. is performed. where limited space is present.
 Boom extension to be  Un-competent
done by competent personnel. driver or rigger is used.
 Driver does
not observe.
 Other vehicle
movements on site
 Crane
damages floor surface
during travelling.
23 Boom extension and operation of  After any alteration to a  Crane High  Refer to the rigging studies
the cranes in the construction crane load tests will be damages structures and for all major/ awkward lifts.
area. performed and the crane cleared or equipment during  Each major/ awkward lift to
for the heaviest lift on the job. operations. be separately assessed.
 Only competent  Rigging studies  Crane to be slewed to
personnel does maintenance and not conducted and position where production activities
extension work on cranes. crane cannot handle will not be hampered.
loads.
24 Tying loads, lifting loads, shifting  PPE  Un-competent High  Check certification of all
loads, letting loads down,  Rigging practices. rigger. equipment to be used before work
stacking materials, positioning  Crane operations  Un-competent starts.
loads. procedure. driver.  Toolbox talks.
Doc. No: HSE-FM-060
BM CONSULTING ENGINEERS
Revision: 00
Function: Health, Safety and Environmental Date: 11/03/2024
Author: Dumisani Nyambi Page: 13 of 19

 Guide operation  Faulty  Ensure that all personnel


procedure. equipment. wear the correct PPE and are trained
 Guide ropes used.  No guide ropes before work starts.
 Storage and stacking used.  Supervisor to enforce the
standards followed.  Bad storage wearing of the correct PPE by all
and stacking. Practices personnel at all times.
 PPE not worn.

25 Stacking and storage-rigging.  Use of correct PPE (  Use of High  Risk assessment to be
Gloves ,Safety Shoes, Overalls, unapproved PPE. conducted on specific high risk lifts as
Hard hats) and certified  No guide ropes well as toolbox talks conducted to
equipment used. ensure all personnel understand the
 Crane to be tested and  Manual dangers and the precautions to be
certified. Labour. taken.
 Toolbox talks.  Slipping of  Only competent personnel to
 Supervision. loads. be used.
 Only competent  Poor stacking
personnel to off load equipment. and storage practices.
 Rigger not
competent.
26 Rigging Practices (Stacking and  PPE.  Bad rigging High  Ensure compliance of all
Storage).  Only certified practices. equipment to the legal requirements
equipment will be used.  Condition of by keeping registers up to date and
 Toolbox talks. equipment. adhering to test dates.
 Supervision  Competency of  Ensure only competent
 Regular inspections on personnel. personnel use equipment.
rigging equipment will register as  Bad layout of  Ensure that adequate
guide. storage areas and bad supervision is present when work is
 Only qualified riggers to storage practices. conducted.
do lifts.  Ensure that the layout of lay-
 Regular inspections on down areas as well as the storage
storage and stacking of practices is according to the standard.
equipment and materials.
Doc. No: HSE-FM-060
BM CONSULTING ENGINEERS
Revision: 00
Function: Health, Safety and Environmental Date: 11/03/2024
Author: Dumisani Nyambi Page: 14 of 19

27 Handling and transport of  PPE  Bottles falling High  Supervisor to enforce that all
cylinders to site and coupling of  All bottles to be over. trolley are held firmly and tied down
torches and gauges as well using transported and stored in an  Explosions or to prevent toppling of trolleys.
the cutting torch. upright position and chained to fire.  Inspections of bottles to be
storage facility or trolley.  Not using enforced by safety officer.
 Inspections on bottles, jubilee clamps on  Ensure that all personnel who
gauges and torch before use. hoses. work with the equipment are properly
 Use of the correct tools.  No arrestors trained.
 Use of new flashback- on bottles or torch.  Tests to be enforced by
arrestors.  No tests done supervisor.
 No oils will be used on  Continuous monitoring,
bottles. audits
 Use of flint lighters only.
28 Fire  Trained fire marshals  Non- High  Continuous monitoring,
and available fire-fighting adherence to standards audits.
equipment, Good housekeeping,
storage of flammable and
combustibles separate. Contact
emergency services on site.
 Supply fire
extinguishers at site offices at
site offices and at areas where
hot work is to be done.
29 Using ladders to get to elevated  Ladders will be  No anti-slip High  Tests to be enforced by
positions. inspected and on register. rubbers on ladders. supervisor.
 All ladders will be tied  Ladders not on  Supervisors to enforce.
down to ensure that they do not register.
slip.  Ladders used
 No climbing of ladders when it rains.
with tool that can be carried in  No assistance
tool belt. when persons use
 Ladder to fit with anti- ladders.
slip rubbers.  Ladders do not
 Ladders not used when protrude over work
it rains. level.
Doc. No: HSE-FM-060
BM CONSULTING ENGINEERS
Revision: 00
Function: Health, Safety and Environmental Date: 11/03/2024
Author: Dumisani Nyambi Page: 15 of 19

 No inspections
done on ladders.
 Ladders not
tied down
30 Work in enclosed areas/ confined  Permit issue, PPE,  Non- High  Continuous monitoring
spaces. Adhere to OHS Act 85 o0f 1993 adherence to permit
requirements. conditions.
31 Falling objects  Lanyards on tools/  Non- High  Continuous monitoring
equipment. adherence.
 Store man to control.
 Supervision to inspect/
monitor.
32 Electrical extension cords.  Identified, checked by  Non- High  Continuous monitoring,
Store man/Supervisors or adherence to audits
competent person and users, standards.
leads not to hang in walk/
driveways, and leads not to lie in
water.
33 Electrical Installations.  Qualified electrician’s  Electrician not High  Ensure wiring is done by
installs and tests all installations. competent qualified electricians.
 Cables are put  Cable  All equipment must be tested
underground. damaged by excavation with proof on register.
 Plot plans indicate tools whilst excavating.  Ensure that all electrical
where cables lie. cables are placed at a safe depth and
 Electricians to prove all all excavations are checked for cables.
electrical work.  A certificate of compliance to
be issued for all electrical installations
done on site establishment.

34 Injuries  Trained first-aiders, first  Unsafe acts/ High  Safety talks, audits,
aid boxes under control and conditions. awareness campaigns
stocked, report, investigate,
follow-up actions to avoid re-
occurrence.
Doc. No: HSE-FM-060
BM CONSULTING ENGINEERS
Revision: 00
Function: Health, Safety and Environmental Date: 11/03/2024
Author: Dumisani Nyambi Page: 16 of 19

Using a 9 or 4 angle grinder.  Only persons trained to  Taking short High  Continuous monitoring during
use equipment. cuts, using incorrect audits and walk about by supervision
 New types of wheel for job, using and safety officers.
equipment training before use. equipment unsafely.  Discipline unsafe users.
 Dangers in use to be  Permit  Personnel using the
explained to all before use conditions not adhered equipment to be trained in the basic
during team talks. to. maintenance and use of the
 Permits to be issued by  Personnel not equipment.
client before use. wearing PPE.
 Use of correct  Person not
PPE(Gloves, Safety Shoes, Hard using correct disc for
hats, Overall, Goggles, Face the job.
shield, Earplugs and dust masks).  Grinder not
 Safety signs. checked
 Regular checks on  No record of
equipment and on register. grinder in register.
 No adherence
to safety signs/ rules
35 Driving on roads.  Licensed drivers only to  No adherence High  Continuous awareness
drive vehicles coded for. to national road traffic campaigns
 Warning of tall grass act.
and cattle and other stray
animals which come out from
nowhere.
 Adhere to speed limits
at all times.
 The driver to be medical
and physically fit at all times and
in position of a medical
certificate
Driving on the site with trucks as  Flagmen present at all  Collisions with High  Flagmen to guide and watch
well as tractors and trailers when times when driving with tractor other vehicles or out for any obstructions on the way.
steel and equipment have to be and trailer. structures.  Driver informed of all the
off-loaded  Competent drivers used danger before going onto site.
to drive vehicles.
Doc. No: HSE-FM-060
BM CONSULTING ENGINEERS
Revision: 00
Function: Health, Safety and Environmental Date: 11/03/2024
Author: Dumisani Nyambi Page: 17 of 19

 When alternative routes  Damage to  Ensure that permission has


have to be taken the gate floor surface or been granted to go onto site.
indicated by the client as well as structures.
permission to do so will be  Speed of the
obtained beforehand. vehicles on site exceeds
 The driver to be medical 40 kph or client
and physically fit at all times and specifications.
in position of a medical  Not adhering
certificate. to TBN Suppliers
standards.
36 Working on any structure  All employees required  Expired High  A database and copies of
including, scaffolding platforms to work at heights>3 meters will medicals. medicals done by employees will be
and suspended scaffolding higher be required to be certified  Use of kept in a central point of control.
than 1.5meters (3 meters as per physically and psychologically fit damaged harnesses.  Damaged harness will be cut
Construction regulations). by a medical practitioner/ clinic.  Scaffold used into pieces to avoid use.
 A man-job specification before it is cleared for  Continual audits by
will be supplied. use. supervision to ensure adherence to
 Proof of these  PPE not used. safe work procedure.
certificates will be filed in the  Tools and  Scaffold inspector approves
site HS file(Health and Safety equipment thrown up all scaffolds.
file). to personnel.  All scaffolds that are used
 All employees will be  Personnel not have safe to use boards on them.
issued with double lanyard informed of the  Toolbox talks conducted to
safety belts and a pig tail to tie dangers inform personnel of dangers.
onto structures. They will sign  A recognized scaffold builder
for these as part of the standard does all scaffolding.
PPE issue register.
 All employees will be
trained in the correct use of and
maintenance of safety
harnesses.
 Proof of training will be
kept in the site HS (Health and
safety file.)
Doc. No: HSE-FM-060
BM CONSULTING ENGINEERS
Revision: 00
Function: Health, Safety and Environmental Date: 11/03/2024
Author: Dumisani Nyambi Page: 18 of 19

 Each harness will be


registered as per its unique
harness and lanyard serial
numbers on the standard
harness checklist and checked
monthly for defects as listed.
 Defective harnesses will
be removed and destroyed and
noted as destroyed in the
register.
 PPE
 Use of hoist ropes and
snatch blocks.
 WSWP
 WSOP
 Scaffolding inspections.
 Scaffold safe for use
boards.
 Scaffolds not used when
it rains.
Scaffold inspected after rain or
bad weather before it is used
again.
37 Hazards encountered while  All openings, floors,  Not all High  Fall protection for employees
working on elevated positions. edges, slabs, stairways and openings practical to working in high risk areas must get
hatches will be adequately close. special attention through additional
guarded, fenced or barricaded.  Access to safety controls and training.
 All work done on elevated positions not  Defective access routes or
elevated positions must be done to standard. platforms must be repaired by the
on a ladder or scaffold platform.  Debris not appointed competent person/s before
 Standard safety warning removed immediately. work can continue.
notices and/ or signs must be  Defective/  All debris must be removed
placed in conspicuous positions hazardous platforms from platforms and working areas as
at openings where persons may during construction soon as it is removed from its original
fall through. period
Doc. No: HSE-FM-060
BM CONSULTING ENGINEERS
Revision: 00
Function: Health, Safety and Environmental Date: 11/03/2024
Author: Dumisani Nyambi Page: 19 of 19

 Employees will be  Taking short position. Work will be stopped until


informed of the identification of cuts to platform work area is cleared of all debris and waste.
sturdy positions where to tie areas.  Any person identified in
their pig tails or harness to.  Crane driver taking a short cut to a work platform
 No debris will be informed of all the or elevated position will be disciplined
allowed to accumulate on a dangers before work immediately.
platform or working area. commences.  Deviations from this plan
 Where attachment  Supervisor must be identified by supervision and
positions are not available or are present when lifts are safety officers and corrective action
unpractical, a strong enough life done. taken.
line will be installed for lanyards Any information not included in this
to be connected to. plan which may be area/ site specific
 Supervision will ensure needs to be reported to the Sizanani
that fixing positions for lanyards Industrial Services Africa Safety
are safe and strong to carry the Department immediately to ensure
weight of all employees tied to this plan is updated and a copy
that position. distributed to sites.
 Supervision will future
more ensure that no employee
will be injured by the fixing
position or equipment if he
should fall.
 Elevated platforms such
as scaffolding and suspended
scaffolding will be erected by
competent persons only. Only
safe to use platforms may be
used.
 Unsafe platforms and
suspended platforms must be
reported to supervision
immediately and all employees
must be evacuated safe to use.
 Employees may only access
Crane operations.

You might also like