HYDROTEST PROCEDURE
Revision : 00 Status : IFI
Document type : PLN Discipline : PJM Rev. Date : 13/02/24
Contractor document number : Page 1 of 14
This document has been generated by an Electronic Document Management System. When printed it is considered as a for information only copy.
The “controlled copy” is the screen version and it is the holder's responsibility that he/she holds the latest valid version.
This document is the property of COMPANY. It must not be stored, reproduced or disclosed to others without written authorisation from the Company
SICCL-PRC-12-0025
SICCL-PRC-12-0025
HYDROTEST PROCEDURE
Revision : 00 Status : IFI
Document type : PLN Discipline : PJM Rev. Date : 13/02/24
Contractor document number : Page 2 of 14
TABLE OF CONTENTS
1.0 PURPOSE.................................................................................................................................4
2.0 SCOPE...................................................................................................................................... 4
3.0 REFERENCES.........................................................................................................................4
4.0 ABBREVIATIONS.................................................................................................................. 4
5.0 RESPONSIBILITIES.............................................................................................................. 4
6.0 PERSONNEL SAFETY.......................................................................................................... 5
7.0 HYDROSTATIC TEST...........................................................................................................5
7.1. EQUIPMENT AND INSTRUMENT FOR TEST.................................................................5
7.2. HYDRO TEST PRE-ACTIVITIES...................................................................................... 6
7.3. TYPICAL CONTENT OF HYDRO TESTING PACKAGE...............................................7
7.4. WATER TEST AND FILLING............................................................................................7
7.4.1. Water Test........................................................................................................................ 7
7.4.2. Filling............................................................................................................................... 7
7.5. PRESSURIZATION.............................................................................................................. 8
7.6. INSPECTION AND LEAKAGE REPAIR............................................................................8
7.6.1. Inspection......................................................................................................................... 8
7.6.2. Leakage repair:.................................................................................................................9
7.7. DEPRESSURIZING & DE-WATERING..................................................................................... 10
8.0 EMERGENCY RESPONSE PLAN..................................................................................... 10
8.1. WORK PERMITS / SAFETY SYSTEMS.................................................................................... 10
This document is the property of COMPANY. It must not be stored, reproduced or disclosed to others without written authorisation from the Company
SICCL-PRC-12-0025
SICCL-PRC-12-0025
HYDROTEST PROCEDURE
Revision : 00 Status : IFI
Document type : PLN Discipline : PJM Rev. Date : 13/02/24
Contractor document number : Page 3 of 14
1.0 PURPOSE
This method of statement provides the general requirement for the “Pipeline Hydro Static Test and
dewatering” for facilities modification in OML-17
2.0 SCOPE
This method of statement details the method and requirements of hydro test and Dewatering for
The internal piping in OML-17
3.0 REFERENCES
4.0 ABBREVIATIONS
HT: Hydro-Test
QAQC: quality assurance Quality control
HSE: Health, Safety & Environment
This document is the property of COMPANY. It must not be stored, reproduced or disclosed to others without written authorisation from the Company
SICCL-PRC-12-0025
SICCL-PRC-12-0025
HYDROTEST PROCEDURE
Revision : 00 Status : IFI
Document type : PLN Discipline : PJM Rev. Date : 13/02/24
Contractor document number : Page 4 of 14
5.0 RESPONSIBILITIES
The construction Engineers are responsible for management of engineering documents and
drawings, drafting process regulations for construction and management of
specifications/standards and construction inspection records;
The QA/QC Engineer is in charge of management of quality manuals, procedures, quality plans,
quality audit, quality verification, site notification/ non-conformance reports etc., and other
documents and data with regard to quality;
The Pipeline Engineer will lead the test.
This document is the property of COMPANY. It must not be stored, reproduced or disclosed to others without written authorisation from the Company
SICCL-PRC-12-0025
SICCL-PRC-12-0025
HYDROTEST PROCEDURE
Revision : 00 Status : IFI
Document type : PLN Discipline : PJM Rev. Date : 13/02/24
Contractor document number : Page 5 of 14
All personnel engaged in testing operations are to comply with the safety requirements.
All work other than hydro testing in the immediate vicinity of the pipe to be tested will be
suspended whilst testing is in progress.
Prior to pressure test, warning signs shall be placed along the right-of-way at all public
crossings and all points where there is exposed pipe or pipe appurtenances.
Warning signs and/or bunting will be installed so as to impede access to the pipe to be tested.
The test equipment and instruments will be located at manifold, where it is convenient to
monitor and operate.
The radio signal shall be reachable along the pipeline.
Responsible and experienced personnel shall be in charge of all operations to ensure all safety
measures are taken.
All other parties are to comply with CONTRACTOR lead engineer instructions and no
person is to enter into the vicinity of the test area without written permission.
The Trunk line will be divided into two test sections as below:
HDD section (Above ground)
Whole pipeline included HDD section (underground)
The Trunk lines and Hydro-test pressure will be as per the Drawing Requirements. Process chart
will be attached after activity with all result for test and table of value of test pressure for strength
and leak test, duration, and volume of water required for the pipeline.
This document is the property of COMPANY. It must not be stored, reproduced or disclosed to others without written authorisation from the Company
SICCL-PRC-12-0025
SICCL-PRC-12-0025
HYDROTEST PROCEDURE
Revision : 00 Status : IFI
Document type : PLN Discipline : PJM Rev. Date : 13/02/24
Contractor document number : Page 6 of 14
All welding, repairs and NDT of tested section shall be completed and accepted.
Trunk line cleanings is completed by means of pigging
All in-line instruments shall be isolated.
All valves in the test section shall be in full open position.
Dewatering of trench shall be complete to allow visual inspection.
All temporary blinds shall be installed correctly in accordance with test sketch.
Test header shall be installed properly in accordance with test sketch.
Warning boards/signs and warning tape shall be set properly in order to avoid not-permitted
entering.
All underground pipelines have to be completely back filled.
Applications for testing have been approved by HHOG site representative(s).
Temporary provisions for testing have been prepared.
Hydro test equipment, chart recorder and other accessories to be approved by HHOG.
Hard copy of procedure shall to be available at site during the Hydro Test together with all
Calibration certificates.
Test section has been filled completed and air has been vented.
This document is the property of COMPANY. It must not be stored, reproduced or disclosed to others without written authorisation from the Company
SICCL-PRC-12-0025
SICCL-PRC-12-0025
HYDROTEST PROCEDURE
Revision : 00 Status : IFI
Document type : PLN Discipline : PJM Rev. Date : 13/02/24
Contractor document number : Page 7 of 14
Before filling the water into any section, it shall be filtered by 50 micron filters, then it shall be
chemical treated by Inhibitors such as Biocide and Oxygen Scavenger if required after the
approval of the CONTRACTOR.
As guidance the physical and chemical treatment for test water is required to prevent:
Corrosion of materials during the pressure test, or after resumption of operations, due to the
presence of this water. Oxygen scavengers (Sodium disulfite) shall be used to remove or decrease
the level of oxygen in the water. The water analysis will jutify the use or not of oxygen scavenger,
depending of the level of dissolved oxygen in the water.
Massive contamination of the tested pipelines by bacteria, which are likely to remain in the pipes
after dewatering. Biocide shall be used to help reducing the bacteria contained in the water,
specially if the test water is used for more than one week.
7.4.2. Filling
This document is the property of COMPANY. It must not be stored, reproduced or disclosed to others without written authorisation from the Company
SICCL-PRC-12-0025
SICCL-PRC-12-0025
HYDROTEST PROCEDURE
Revision : 00 Status : IFI
Document type : PLN Discipline : PJM Rev. Date : 13/02/24
Contractor document number : Page 8 of 14
After sending the first pig, pumping shall continue until the same amount of water introduced
before is pumped. Then, the second pig is launched into the pipeline at speed less than 1 m/s.
Pumping shall continue until both Pigs arrive at receiver end and the section is full.
This document is the property of COMPANY. It must not be stored, reproduced or disclosed to others without written authorisation from the Company
SICCL-PRC-12-0025
SICCL-PRC-12-0025
HYDROTEST PROCEDURE
Revision : 00 Status : IFI
Document type : PLN Discipline : PJM Rev. Date : 13/02/24
Contractor document number : Page 9 of 14
7.5. Pressurization
Hydro Test pressurizing graph from start till finish shall be as below:
Pressurizing shall be commenced after ensuring that all trapped air is removed in
accordance with ANSI/ASME B31.4 and B31.8.
For strength test pressure (according to the designed hydro test pressure) and related data extracted
from approved drawing. Pipeline section shall be tested at 1.25 times the design pressure for a
duration of 4 hours.
The pressurization shall be performed slowly and in steps to ensure getting the pressure readings
accurately.
During the pressurization, pressure and temperature readings shall be recorded and
maintained for 15 minutes at 40%, 70% and 100% of strength test pressure.
After reaching the strength test pressure, the pump will be stopped and isolated from the pipeline.
The test pressure and temperature shall be stabilized for 4 hours with measurements taken of the
pressure every 30 minutes.
The 24 hours Leak Tightness Test will be performed immediately after satisfactory completion of
Strength Test and shall not be less than 1.1 times the design pressure as per ASME B31.4.
The leak tightness test pressure will be held for a minimum period of 24 hours.
For the 24 hours’ period, the pressure and ambient temperature will be taken every hour.
Regarding the HDD Section, since this section is above ground, Only Strength test will be
performed for it (No Leak Test will be performed for HDD section).
This document is the property of COMPANY. It must not be stored, reproduced or disclosed to others without written authorisation from the Company
SICCL-PRC-12-0025
SICCL-PRC-12-0025
HYDROTEST PROCEDURE
Revision : 00 Status : IFI
Document type : PLN Discipline : PJM Rev. Date : 13/02/24
Contractor document number : Page 10 of 14
This document is the property of COMPANY. It must not be stored, reproduced or disclosed to others without written authorisation from the Company
SICCL-PRC-12-0025
SICCL-PRC-12-0025
HYDROTEST PROCEDURE
Revision : 00 Status : IFI
Document type : PLN Discipline : PJM Rev. Date : 13/02/24
Contractor document number : Page 11 of 14
Acceptance criteria:
𝑷𝒕−𝑷𝒕+𝟑𝟎
.100 <= 0.5%
𝑷𝒕
The Leak test will be completed and accepted if one of the following scenarios occurs:
The pressure changes due to a water temperature changes shall be calculated through the
following formula:
𝛾−2∗(1+𝑣)∗𝛼
∆𝑃 = 𝐾. ∆𝑇 = 𝐷
∗(1−𝑣2)+
1 ∗ ∆𝑇
Where: 𝐸𝑡 𝐵
This document is the property of COMPANY. It must not be stored, reproduced or disclosed to others without written authorisation from the Company
SICCL-PRC-12-0025
SICCL-PRC-12-0025
HYDROTEST PROCEDURE
Revision : 00 Status : IFI
Document type : PLN Discipline : PJM Rev. Date : 13/02/24
Contractor document number : Page 12 of 14
If a leak is suspected, CONTRACTOR will reduce the pressure to less than 80 percent of the test
pressure before carrying out a visual examination. If it is not possible to locate the suspected leak
by visual examination, CONTRACTOR will use a method which enables the locating of leaks at
test pressure without endangering the personnel carrying out this activity. When the leak has been
found, it will be repaired in accordance with the appropriate guidelines.
When the repair has been accepted by HHOG representatives, then the pressure test shall be
performed as described in clause 7.5.
This document is the property of COMPANY. It must not be stored, reproduced or disclosed to others without written authorisation from the Company
SICCL-PRC-12-0025
SICCL-PRC-12-0025
SCAFFOLDING PROCEDURE
Revision : 00 Status : IFI
Document type : PLN Discipline : PJM Rev. Date : 13/02/23
Contractor document number : Page 13 of 14
Dewatering consists of force draining the test water using the pigs in the test header pushed by
compressed air in reverse direction in downhill direction.
The locations for de-watering of the pipeline tested sections will be chosen to be in suitable
locations where discharge will be into drains or other suitable locations capable of taking the
water volumes required. These locations shall be approved by HHOG prior to test. Care shall
be taken so that water is disposed of without causing excessive erosion or flooding in the soil
around the right of way.
Once the dewatering is complete, free water left in the pipeline shall be removed by the use
of foam swabbing pigs, driven by compressed air.
This document is the property of COMPANY. It must not be stored, reproduced or disclosed to others without written authorisation from the Company
SICCL-PRC-12-0025
SICCL-PRC-12-0025
SCAFFOLDING PROCEDURE
Revision : 00 Status : IFI
Document type : PLN Discipline : PJM Rev. Date : 13/02/23
Contractor document number : Page 14 of 14
This document is the property of COMPANY. It must not be stored, reproduced or disclosed to others without written authorisation from the Company
SICCL-PRC-12-0025