Package : Civil Work
CIVIL WORK
WTG FOUNDATION
Contents
1. Introduction ............................................................................................................................. 4
2. Pre-requisites ......................................................................................................................... 7
3. Method Statements and Flowcharts ...................................................................................... 9
4. Record Sheet .......................................................................................................................... 43
5. Checklist ................................................................................................................................ 46
6. Key Requirement of Health, Safety & Environment (HSE) ................................................. 50
7. Resource Required ................................................................................................................. 53
8. Frequently Asked Questions (FAQs) ..................................................................................... 55
VIVIID RENEWABLES PRIVATE LIMITED 1.0 / 0 1 .01.2024
Ver. No. / Date
Package : Civil Work
Prepared by Signature
Reviewed by Signature
Approved by Signature
VIVIID RENEWABLES PRIVATE LIMITED 1.0 / 0 1 .01.2024
Ver. No. / Date
Package : Civil Work
1. Introduction
1.1. Purpose
The Standard Operating Procedure (SOPs) has been developed to define a framework for the
Construction Management at project sites and to ensure control on schedule and execution of
activities for Domestic, International and Special Renewable Wind power project s. The prime
objective of this SOP is to implement the Planning, Scheduling, Execution and Monitoring aspects
for the Construction activities. This method statement covers the appropriate practices of WTG
Foundation.
Check and ensure the required tools & machineries at the site location.
Construction location where the WTG foundation works to be done should be cleaned & made
ready.
Approach road to be ready for transportation of Concrete, Reinforcement & Anchor Cage etc.
1.3. Definition
Micro Sitting Drawing: - The science of limiting array effects by suitable geometric
arrangements of machine layout is generally known as micro siting of wind turbine
Geotechnical Investigation of Soil: - The process in which the physical qualities of a site are
evaluated in order to determine if the site is suitable and safe for the proposed purpose.
Geotechnical investigation to get clear information about the soil properties and hydrological
conditions at the site, we get nature and engineering properties of the soil and rock formation
by this activity.
Excavation Work: - Work involving the removal of soil or rock from a site to form an open face,
hole or cavity using tools, machinery or explosives.
Plain Cement Concrete (PCC): - It is a mixture of cement, fine aggregate(sand) and coarse
aggregate without steel. PCC is an important component of a foundation which is laid on the
soil surface to avoid direct contact of reinforcement of concrete with soil and water.
Anchor Cage: - An anchor cage is a set of bolts, kept together by an inferior and superior steel
rings (or) the anchor cage is a system conceived to transfer the loads to the foundation more
effectively, anchoring the tower to the foundation.
Torqueing: -Torque is the application of force acting at a radial distance and tending to cause
rotation.
VIVIID RENEWABLES PRIVATE LIMITED 1.0 / 0 1 .01.2024
Ver. No. / Date
Package : Civil Work
Steel Reinforcement works: - Steel reinforcement is steel bars or mesh of steel wires used
in reinforced concrete and masonry structures to strengthen and hold the concrete in tension
Concrete Mix Design: - It is the process of selecting suitable ingredients of concrete and
determining their relative proportions with the object of producing concrete of certain
minimum strength and durability as economically as possible.
Concrete pouring: - Site-poured concrete is building material that is poured, moulded, and
cured onsite.
Curing: - Curing is the process of maintaining satisfactory moisture content and temperature in
freshly cast concrete
Backfilling: - It is the process of replacing or reusing the soil that is removed during building
construction to strengthen and support a structure’s foundation or any other structural
member.
Grouting: - Grouting is a process in which cement mortar or other same functional material like
epoxy filled in cracks or voids in any construction (or) Cement Grouting is the injection under
pressure of cement or grout to fill voids or fractures in the soil, rock unit
or concrete structure. Cement Grouting is a process by which cement is injected under
pressure to fill fractures and voids in concrete structures.
1.4. Abbreviations
CM Cement Mortar
GA General Arrangement
GI Galvanized Iron
IS International Standard
M Meter
NA Not Applicable
2. Pre-requisites
2.1. Material
List of Materials
2.2. Tool
List of Tools
Total Station
Required Document Ref. Doc. No. Required Record Sheet Ref. Doc. No,
Mandatory
Required
(PPE)
Reflector Jacket Hard Hat Hand Gloves Safety Shoes Safety Eye Wear
VIVIID RENEWABLES PRIVATE LIMITED 1.0 / 0 1 .01.2024
Ver. No. / Date
Package : Civil Work
Field soil investigation to be carried out by external agency for each WTG location., it is necessary
to carryout core drilling to depth of at least 3m in hard rock or 5m in soft rock / bed rock, and then
bore hole shall be terminated at this point.
Micro setting drawing with Co-ordinates will be received from AGEL and the same will be
rechecked.
The Centre of WTG location must be marked by using GPS instrument to external agency to
conduct soil test. Test shall carry out within 30m of the centre point of WTG. If drilling was not
successful, then additional drill may be carried out within the rad ius of 30 m of the centre
point of WTG.
Standard penetration test to be carried out in accordance with IS: 2131 – 1981 to find out N
value and disturbed & undisturbed samples need to be collected for laboratory investigation
which shall comply with IS 2720.
Safe bearing capacity at various depths shall be found and the detailed Geo technical
investigation report must be submitted by external agency.
VIVIID RENEWABLES PRIVATE LIMITED 1.0 / 0 1 .01.2024
Ver. No. / Date
Package : Civil Work
Initial road survey must be carried out by taking following points into consideration
After finalizing the survey, alignment has to be done by marking. Before taking up the road
works Natural Ground Level(NGL) / Existing Ground Levels should be noted for every 10m to
15m interval on all the three points’ i.e., Right, Centre & Left of the respective road. Also,
level marking should be done for Cutting / Filling to match the gradient. Suitable turning
radius to provide during road alignment
The thickness of the road section mainly depends upon the characteristics of the soil below.
Hence the sections need to be decided based on the soil investigation done and will vary
from site to site. As the general guideline, where the sub base is good enough to carry the
loads as mentioned in this documents, Minimum 150mm thick layer (or thickness as
mentioned in drawing) of approved soil after compaction to the required degree shall be laid
for temporary approach road.
3.2.4. Surface
The surface of the site roads will usually be unpaved. It should be properly compacted,
The maintenance of the road during the construction period – both related to bearing
capacity and the smoothness of the surface – must be executed sufficiently to allow
access for all trucks, cranes and ordinary cars without any hindrance.
The decision of AGEL Engineer-In-Charge is final in accepting the Surface of the road.
The contractor’s scope of work includes the execution of all permanent and interims
ditches as well as the watercourses needed to ensure sufficient drainage of the access
and site roads.
A typical earthen drain shall be as per drawing with proper slopes to facilitate the water
flow.
VIVIID RENEWABLES PRIVATE LIMITED 1.0 / 0 1 .01.2024
Ver. No. / Date
Package : Civil Work
Based on the terrain conditions & watercourses the drain has to be made either on one
side or both sides of the road.
During the entire project, the ditches and watercourses must be maintained by the civil
contractor.
Flowchart for Approach Road
VIVIID RENEWABLES PRIVATE LIMITED 1.0 / 0 1 .01.2024
Ver. No. / Date
Package : Civil Work
The Contractor appointed shall carry out all excavation works in accordance with the dimensions
and levels indicated on the foundation drawings. Excavation is carried out in accordance with the
guidelines given in IS:3764-1992 “Safety code for excavation work". Blasting, if required, is carried
out in strict accordance with IS: 4081-1986 "Safety code for blasting and related drilling
operations" and the latest state laws, regulations and rules. Blasting, at all-time will be carried out
under the supervision of fully qualified, experienced and licensed supervisors.
Before commencing earthwork, benchmark of location should be fixed for depth reference. In case
of high variation in the level of ground then it should be brought to notice of Construction Head.
Excavation may be carried out by excavator machine. Excavation shall be in all kinds of
soils and shall include careful removal of all materials of whatever nature, whether dry or
wet, to facilitate the construction work, exactly in accordance with lines, levels, grades,
curves etc. shown on the drawings.
Earthwork shall be done to the exact length, width, depth and profile as shown
irrelevant drawings.
No excavation for foundations shall be filled in or covered with concrete until Engineer’s
inspection & sanction issued to proceed with the works.
Stability of the excavation need to be taken care. Any dewatering, shoring, strutting and
timbering or cutting of extra width of trenches required for the work and safety of
workmen and equipment shall be done. Dewatering water shall be drained off in such a
way that it does not cause any damage to any property or any nuisance to neighbours /
others.
All bottom of excavation shall be lightly watered and thoroughly rammed before laying
PCC.
Excavated material required for filling (suitability will be checked by Engineer in charge)
shall be stacked or dumped where indicated by the Engineer in charge.
Boulders more than 100mm in size shall not be permitted for backfilling.
Surplus material from the stacks or dumps retained for filling and excavated unwanted
earth shall be removed and carted away from the site.
The method of measurement shall be generally in accordance with the IS: 1200 (Method
of measurement of building and civil engineering works) unless otherwise specified.
The contractor shall obtain all necessary licenses and permission covering the purchase
and use of explosives, and shall meticulously observe the requirements of Government
and local authorities.
The contractor shall provide a proper secure place for the storage of explosives to the
satisfaction of the Engineer in charge and they shall be handled only by men
experienced and trained in their use.
In case of blasting with dynamite or any other high explosives, the position of all of the
bore holes to be drilled shall be marked in circles with white paint / lime.
The bore holes shall be thoroughly cleaned before a cartridge is inserted.
Only cylindrical wooden tamping rods shall be used for tamping. Maximum of eight bore
holes shall be loaded and fired at one occasion.
The charges shall be fired successively and not simultaneously. Before firing, warning
shall be given.
Generally blasting operation shall be in accordance with the (IS 4081-1986 – Safety
code for blasting and related drilling operations).
VIVIID RENEWABLES PRIVATE LIMITED 1.0 / 0 1 .01.2024
Ver. No. / Date
Package : Civil Work
Before laying ensure correct level is received, excess excavation to be filled with lean concrete
or river sand.
The works shall consist of providing and placing concrete for plain concrete works in
conformity with the drawings or in accordance with the written instructions of the Site
Engineer. The details of material specifications shall be as stated under the Reinforced
Concrete works.
The bottom of excavated surface shall be lightly watered and thoroughly rammed before laying
the PCC
Proper shuttering shall be provided for required dimension as per drawing for PCC.
Materials used for PCC (Cement, Sand, Aggregate & Water) shall comply with Field Quality
Plan.
The offset of PCC shall be the same as the thickness of PCC or as specified in the drawing.
Curing for minimum 3 days shall be carried out after placing the PCC.
After PCC is done the levels for the top of PCC shall be recorded in the prescribed formats &
shall be verified by AGEL site engineer.
The contractor shall be able to produce the record of supplying the concrete for PCC in form of
batch prints of the batching plant. In case of concrete is done with mechanical mixers the
cement bags and other material used for the PCC shall be recorded.
The measurement of the PCC will be done only as per the drawing for the payment purpose.
Any excess PCC on account of extra excavation or for filling the undulations will not be
payable & deemed to be covered in the rate given in the contract.
Backfilling work to done in maximum layer of 300 mm and same should be compacted with
rollers.
Prior to the setting of the lower reinforcement of the foundation, the position of the 6 lower
plates will be marked on the leaning concrete.
The leveling legs will be set on the marks done. Afterwards, the lower reinforcement will be set.
The plates of the leveling legs will be fixed to the leaning concrete
The rebar interfering with the leveling legs or the nuts, will need to be slig htly moved, so that
their position can be adapted to the final position of the leveling legs.
Once the lower reinforcement has been assembled, the lower flange will be introduced on the
leveling legs.
The unloading of the flanges will be done by a crane provided by slings (textile). In no case will
the lifting be done using chains or any other metallic mean that could damage the flanges.
Before the leveling, it will be checked that the lower flange is placed at a distance as per
drawing of the leaning concrete (the bolt can be marked before the leveling to make the
process easier).
A first leveling of the lower flange will be done, using three of the leveling legs (those forming
120º). (Leveling tolerance: +/-0.5mm). Once leveled, the other three legs will be tightened.
Before introducing the bolts, they will be marked with two lines that will indicate the final
position of the lower face of each nut (lower nut and upper nut).
Additionally, to marking the bolts, the holes will be numbered on the lower fl ange, to identify
the position of the guide bolts.
Once numbered, the main bolts will be introduced, in the closest positions to the leveling legs,
but separated two holes from them. These bolts will be tightened to the lower flange.
Afterwards, the guide bolts will be introduced (they have been previously marked too). There
will be 12 bolts in total or as per WEC supplier (which will be positioned between the main
bolts). These bolts will serve as a template when assembling the first section of the tower.
These bolts are slightly higher (about 1cm) in order to work as the mentioned template.
Once positioned and tightened the main and guide bolts, the upper flange (or upper template)
will be set. This template will stand on the nuts of the main bolts previously positioned.
Once the template is on position, it will be leveled. For this we need to set the template in the
correct position, with the help of the previously painted marks.
Leveling of the upper template. For the leveling of the upper template, the main bolts and the
guide bolts will be used (Leveling tolerance of +/-1 mm or as per drawing requirement).
Once the main bolts have been leveled, their position will be fixed introducing another nut over
the flange (under the flange the other nut is positioned).
After the upper flange is leveled, the verticality of the bolts will be verified using a bubble level.
After the horizontality of the flange and the verticality of the bolts have been checked, the rest
of the bolts will be introduced. Except from the guide bolts, all the bolts need to stand out the
same distance (Tolerance: +/- 2 mm or as per drawing requirement). To help the introduction of
the bolts, the nuts will have to be pushed back the maximum, to the limit where the thread
ends.
VIVIID RENEWABLES PRIVATE LIMITED 1.0 / 0 1 .01.2024
Ver. No. / Date
Package : Civil Work
The wrench torque is necessary now. Minimum 400Nm (or as per drawing) force shall be
applied to the nuts positioned under the lower flange. The wrench torque’s mouth needs to be
special, in order to host the length of bolt standing out of the washer.
After introducing all the bolts, one more step needs to be done. Because of the length of the
bolts, they may curve on the free upper part. To avoid this and guarantee a perfect coincidence
with the coming tower flange, another template will be positioned on the bolts, holding its free
extreme. In the absence of second flange the top template can be placed 150mm (or as per
drawing) below the top of studs and it should be leveled before casting.
VIVIID RENEWABLES PRIVATE LIMITED 1.0 / 0 1 .01.2024
Ver. No. / Date
Package : Civil Work
The drawings / bar bending schedules shall be thoroughly studied prior to the
commencement of fabrication& installation.
Fabrication shall be accurately done to the dimensions, spacing and ensuring minimum
cover as called for on structural drawings.
All reinforcement bars shall be made straight if it is in bent condition before cutting /
bending.
Bars shall be bent gradually by machine or other approved means without the use of
heat.
Bars incorrectly bent once shall not be used without the approval of the Engineer.
Unless otherwise specified or shown on the drawings, all laps shall be 50 times the
diameter of bar.
All steel reinforcement shall be accurately placed in position shown on the drawing tied
with 18 gauges GI, (MS wire) steel wire or any tempered wires can be used
Welding shall be carried out only when specifically shown on the drawings in
accordance with IS: 2751 (or as per drawing) Reinforcement shall have cover as shown
on the structural drawings and where not specified the thickness of cover shall be a
minimum of 50mm.
Cover blocks shall be either square or rectangular in plan with or without binding wire
embedded in them will be tied to the reinforcement.
To provide necessary cover for reinforcement at any section, only single cover blocks
shall be used.
Unless specified otherwise, actual concrete cover should not deviate from the required
nominal cover by ±10mm.
RCC work shall consist of making and placing concrete for reinforced concrete works in conformity
with the drawings or in accordance with the written instructions of the Site Engineer. All materials,
workmanship and testing shall comply with the latest revisions of the relevant Indian Standards,
Codes of Practices referred to in these specifications and notes given on the dra wings. Unless
otherwise stated in these specifications, the IS: 456-2000 "Code of practice for Plain and
Reinforced Concrete", and the standards referred to in this code of practice are applicable to
reinforced concrete work.
The proportions of ingredients for concrete shall be such that in addition to complying with the
strength requirement, the concrete shall have adequate workability and proper consistency to
permit it to be worked readily into the forms and around reinforcement, under the conditions of
placement to be employed without excessive segregation or bleeding.
Only the Design Mix concrete accordance to RCC drawing shall be used for RCC. The
contractor shall perform trial mixes and preliminary tests of each class of concrete. The
selection criteria will be compressive strength, workability and surface finish and shall
follow the procedures given by WTG manufacturer or as outlined in IS: 456 -2000.
Control tests shall be carried out before undertaking the works accordin g to the
composition selected for the purpose of the concrete works.
The mix design report shall be submitted for review & approval.
The trail mix for the submitted design mix along with all the required testing shall be
carried out at site. The foundation concrete will be allowed only after getting
satisfactory result of the trail mix. Quality department will approve the same.
The concrete is mixed preferably in an automatic Batch Plant of sufficient capacity. The
mixing is carried out according to IS:4926-1976 (reaffirmed 1990) & IS:4925. The batch
prints of each load produced at batching plant shall be available for verification. The batch
prints shall be submitted to for each cum poured after the concreting is completed.
All materials for controlled concrete shall be batched as per approved design mix in
suitable weigh-batcher of adequate capacity and approved design.
The concrete can be sourced from Ready mixed concrete plant, if possible;
Thorough mixing of the concrete is essential and mixers shall be capable of combining
the materials into a uniform mixture, uniform colour and of discharging this mixture
without segregation.
The mixers should always be operated at the speed and time recommended by their
manufactures & as recommended in concrete mix design report. Water cement ratio
should be maintained during mixing of concrete,
Mixers for concrete may be stationary mixers of either tilting or non-tilting type, or truck
mixers of approved design.
The mixers shall be maintained in satisfactory operating condition, and mixer drums
shall be kept free of hardened concrete.
Concrete thus mixed shall be transported to the foundation location by means of transit
mixers of sufficient capacity & numbers.
The primary products of concrete will be stored and transported without damage of
mixing, contamination or any significant change to its characteristics.
The time passed since the preparation of concrete in the fac tory and casting in
foundation must not exceed 1.5 hours in any case
Water must not be added to the concrete to make casting easier in any case. Retarding
admixture shall be added to increase the setting of the concrete without any damage to
the quality of concrete as per design mix recommendation.
Concrete shall be conveyed from the place of mixing to the place of final deposit as
rapidly as practicable by methods, which will prevent segregation or loss of any of the
ingredients.
If segregation does occur during transport, the concrete shall be remixed before being
placed
Concrete is placed in position with concrete pump/ directly by means of proper chutes
in layer in such a way that no segregation, honeycombi ng bleeding of concrete will be
occurred. Sufficient numbers of mechanical vibrators with proper size needles shall be
used while pouring the concrete in place.
Before the concrete is actually placed in position, the insides of the forms should be
inspected to see that they have been cleaned and oiled, care being taken to see that the
reinforcements do not get contaminated.
Concrete pump shall be used to deliver concrete of the required consistency and
plasticity without segregation or loss of slump.
Method of placing shall be such as to prevent segregation and as far as practicable the
placing shall be continuous.
For general guidance, the maximum permissible free fall of concrete may be 1.50m.
For pump able concrete the slump of concrete should be 100mm, unless specified in
design mix report
At least one slump test shall be made at work place for every truck / batch. More
frequent tests shall be made if there is a distinct change in job conditions.
Pouring of concrete will start in a circular way from the edges of the foundation and in
layers with a thickness of 30cm approximately.
Concrete will have to surround the foundation embed section to a height such that the
bottom flange is covered lightly.
Pour the concrete inside the foundation section in homogeneous way filling around
50%.
VIVIID RENEWABLES PRIVATE LIMITED 1.0 / 0 1 .01.2024
Ver. No. / Date
Package : Civil Work
Again pour the concrete in a circular way around the foundation section in layers with a
thickness of about 30cm and then pour balance portion inside the foundation section
The concrete can be poured directly by chutes of transit mixer if the freefall height is
restricted to less than 1.5m.
Vibrators shall be used with the utmost care and handled only by the most experienced
workmen.
The contractor must provide a full redundancy of all vibration equipment during the
period of concrete pouring.
The min diameter of the vibrator needle for raft concrete is 60mm. However smaller
diameter vibrator needle also can be used for the congested reinforcement areas
around embedment’s
Sufficient distance from the pouring head has to be maintained so that the vibrator is
utilized only to compact the concrete and not to spread it.
Except for shallow or inaccessible concrete, the vibrator shall be penetrated vertically
and at regular distance intervals, not an angle and not haphazard intervals.
Vibrator should not be used for the purpose of spreading the concrete.
The cube casting procedures is as follows as per IS: 516 – 1959 or as per approved plan.
The mould shall be cleaned and free from any hardened concrete.
Mould oil shall be applied in the joints between the sections of mould, contact surfaces
of the bottom of the mould and the base plate in order to ensure that no water escapes
during filling and to prevent adhesion of concrete.
The concrete has to be collected directly from the weight batcher / pump / transit mixer.
The concrete shall be filled in to the mould layer by layer of approximately 50mm deep.
Each layer shall be compacted either by 16mm tamping rod or table vibrator.
The strokes shall penetrate in to the underlying layer and the bottom layer shall be
rodded throughout its depth.
The sides of the mould shall be stored in a place free from vibration.
The specimens shall be marked with location number, date, and identification number
VIVIID RENEWABLES PRIVATE LIMITED 1.0 / 0 1 .01.2024
Ver. No. / Date
Package : Civil Work
The mould shuttering shall be removed after 24hrs and the cubes shall be immediately
submerged in clean fresh water till testing.
All the cubes have to be tested on site established lab facility or in the AGEL approved
external laboratory.
After fixing the slump cone, 3 layers of concrete shall be poured with each layer of 25
strokes with 16mm tamping rods.
Acceptable slump limit is +/- 25mm or 1/3 of specified slump value whichever less as per
design mix slump requirement is.
Temperature of concrete should also be recorded for every batch in case controlled
concrete application
A random sampling procedure shall be adopted to ensure that the sampling should be
spread over the entire period of concreting. The minimum test specimen of sampling of
concrete of each grade shall be in accordance with the following as per IS 456 -2000.
1 to 5
6 to 15
16 to 30
31 to 50
51 & Above
However, the number of cubes required for shall be as per the WTG manufacturer
requirement which shall be discussed with AGEL Quality representative.
VIVIID RENEWABLES PRIVATE LIMITED 1.0 / 0 1 .01.2024
Ver. No. / Date
Package : Civil Work
3.8. Curing
All concrete surfaces shall be maintained in moist condition and be protected against harmful
effects of weather, for at least for 10 days of placing.
After 12 hours of completion of concreting, the exposed concrete surface shall be kept
constantly wet for at least 10 days for OPC cement & 14 days for PPC cement. It shall be cured
by maintaining the concrete in a damp condition for a period of 10 days after placing the
concrete.
After de shuttering, honeycombs in the concrete if any have to be rectified by removing the
loose material and the surface shall be prepared wet or apply cement slurry in the
honeycombed area and finish with CM 1:3 and shall proceed for further works.
Cement slurry in foundation section above the concrete surface shall be cleaned thoroughly
immediate after concreting.
The pipe conduit openings shall be ensured to be free from debris or blockages & shall be
neatly finished. The both ends shall be closed by means of end caps so as to avoid entry of
foreign material/insects into the same.
The vertical side of the concrete shuttering shall be removed after 24hrs from the finishing
time of concrete pouring and shall be covered by wet gunny bags tied with ropes all around.
The sides of the foundation shall be backfilled in layers’ thickness and water has to be applied
in that area to keep the foundation side face in moist condition.
Extreme care should be taken to ensure that all surfaces are kept in a moist condition and no
local area shall be allowed to dry out intermittently.
As an alternate to water curing, the epoxy resin curing paint of the approved make can be
applied to exposed foundation surfaces. However, the efficiency of the curing paint shall be
established by doing the testing on cubes at site & approval shall be taken for the same.
3.9. Backfilling
Backfilling of foundation shall be carried out as shown on the drawings or directed by the Site
Engineer with suitable materials.
The soil to be used for backfilling shall be tested for the MDD (Max dry density) & OMC
(Optimum moisture content).
Filling materials shall be spread, levelled and thoroughly compacted in layers not more than 30
cm thick or as per design. Each layer shall be separately compacted to achieve the required
state of compaction.
The backfilling shall be carried out after completing the minimum curing period.
The backfilling shall be done normally after 10 days of foundation concrete completion; in case
of necessity it shall be done after 7 days from the casting date of foundation.
The sides of the foundation have to be cleared of all debris, mortar, boulders if any, concrete
lump etc.,
De shuttering for vertical faces of concrete shall be done after 12 hours of casting, sides of raft
concrete up to raft top surface of raft shall be backfilled immediately after de shuttering.
Backfilling above raft surface shall be done in layers, thickness not exceeding 300mm.
Each layer has to be properly consolidated / watered and 95% compaction to be done with 10-
12MT roller. The dry weight of fill shall be minimum 18T/cum to 20T/cum or as specified in the
drawings.
Compaction factor to be checked by using Proctor compaction test for each layer. The
compaction testing shall be offered for witness by site engineer & shall be recorded in the
prescribed standard format.
The final level of the backfilling shall be as per foundation drawing after the final curing
period.
It shall be ensured that the exposed earth flats are not disturbed during the backfilling. &the
open ends of the pipe conduits shall be closed properly & care is taken so that the ends are not
damaged & the locations of the same shall be marked for the easy identification during the
electrical activities.
VIVIID RENEWABLES PRIVATE LIMITED 1.0 / 0 1 .01.2024
Ver. No. / Date
Package : Civil Work
3.10. Grouting
After Curing period backfilling should be done as per procedure for easy access of
grouting.
Remove all uneven/ loose concrete, excessive length of PVC sleeve above the concrete
level.
Before fixing the level plates clean the concrete surface without dust by using
compressor.
Find out the highest level point of concrete surface in the Anchor bolt circumference.
From the highest level point, Mark other 5 points of levelling plates forming 60 degrees
from each other.
Fix the levelling plate at first point by using Rich cement mortar Minimum height should
be maintained as per the drawing. Check the horizontal level by using spirit level.
After marking of six levelling plates points, Apply Duct tape or geo textile tape over geo
textile cloths / gunny bags on Anchor bolt above the Grouting height to avoid any
touches between anchor bolt and grouting. The same material will be used to cover the
PVC pipe sleeve to stop the grouting material entry inside the pipe.
After covering the Anchor bolts with the above material, all other Levelling plates also
fixed with the same level of Point one. All six points rechecked for level.
GI sheet form work/ MS plate made for Grouting with Minimum gap equal to height of
grouting from flange both inside and outside.
Before grouting Moist the area is important, by using water jet/ compressor the surface
is cleaned for dust and surface is moisturized before one hour.
Nito bond STD shall be used as an adhesive bonding agent between concrete surface
and Grouting surface just an hour before grouting.
Mixing will be batch by batch, each batch may be containing of 2-3 bags.
VIVIID RENEWABLES PRIVATE LIMITED 1.0 / 0 1 .01.2024
Ver. No. / Date
Package : Civil Work
Mixing will be done up to reach the recommended consistency. Water dosage will be
strictly followed as per product recommendations
Mix the grout until it reaches the desired consistency for pouring. Do not add additional
water to improve the consistency of the mortar. Both the necessary mixing time and the
amount of water are specified by the manufacturer.
The pouring of the grout will have to be carried out in such a way that there are no
voids.
Once pouring is completed, Curing will be started immediately after one hour by using
gunny bags with water.
CIP-PROJ-WIND-
SOP : WTG Foundation Document Id
SOP-01
Title : Method Statements & Flowcharts Page 39 of 58
Flowchart for Grouting
VIVIID RENEWABLES PRIVATE LIMITED 1.0 / 0 1 .01.2024
Ver. No. / Date
Package : Civil Work
The works shall consist of providing and placing concrete for plain concrete works in
conformity with the drawings or in accordance with the written instructions of the Site
Engineer. The details of material specifications shall be as stated under the Reinforced
Concrete works.
The bottom of excavated surface shall be lightly watered and thoroughly rammed before laying
the PCC.
Either brickwork or shutters shall be provided for required dimension as per drawing for PCC.
PCC has to be laid as per the given specification in the drawing and procedures for concrete
work has to be strictly followed
Materials used for PCC (Cement, Sand, Aggregate & Water) shall comply with Field Quality
Plan.
The offset of PCC shall be the same as the thickness of PCC or as specified in the drawing.
Curing for minimum 3 days shall be carried out after placing the PCC.
After PCC is done the levels for the top of PCC shall be recorded in the prescribed formats &
shall be verified by site engineer.
The contractor shall produce the record of supplying the concrete for PCC in form of batch
prints of the batching plant. In case of concrete is done with mechanical mixers the cement
bags used for the PCC shall be recorded.
The measurement of the PCC will be done only as per the drawing for the payment purpose.
Any excess PCC on account of extra excavation or for filling the undulations will not be
payable & deemed to be covered in the rate given in the contract.
All surfaces must be clean and free from debris, lose or flaking material, standing water, oil,
grease and organic growth.
Concrete surfaces must be free from laitance and any traces of shuttering, release oils and
curing compounds.
The entire contents of the hardener and base containers must be mixed together thoroughly,
until a uniform consistency, a fully homogeneous trowel able mortar, is achieved.
Due to the easy workability of the product, the mixed product can be taken directly from the
mixing vessel or subdivided onto spot boards for individual applicators.
Apply the weather coat material with help of knife, scrapper or trowel
Need to ensure that application area is free from the dust and scrubs
All cracks shall be chased to a 5mm x 5mm grove and filled using the weather coating mixed
component or cement mortar or grouting material
Apply first coat with approved mixing component suggested by the manufacturers or as per
approved VIVIID technical specification.
Drying time for each coat is if the temperature is 35ºC to 40ºC and it varies depends on the
temperature. Ensure that the surface is thoroughly dried before applying each coat.
The painting materials are applied at rate not exceeding that recommended by paint
manufacturer for each coat.
VIVIID RENEWABLES PRIVATE LIMITED 1.0 / 0 1 .01.2024
Ver. No. / Date
Package : Civil Work
4. Checklist
Status of
Sr.
Activity checks description completion Ref. Doc. No.
No.
Yes No NA
1. Pre- Inspection
1 JSA & RA is carried out and records are available at site for daily review.
2 Tool Box Talk (TBT) is conducted daily.
3 Ensure team have valid work permit.
4 Drinking water is available.
5 Contractor’s supervisor present at site.
6 First Aid Box is available at site.
End to end barricading with pictograms and displays (No Smoking,
7
Emergency No., Work in Progress) are provided at site.
8 Fire Extinguishers of required capacities are available at site.
9 All personnel involved in the site activity are trained.
Proper PPEs (Hand Gloves, Ear Plug, Hard Hat, Safety Shoes, Goggle,
10
Reflective jacket, etc.) are used.
11 Cleanliness of the workplace during and after the job
12 All the materials stacked properly & walkways free from obstacles.
Emergency and rescue plan is explained before starting the work.
13
(check for awareness in the people on the site)
All equipment's are inspected before work commences and statutory
14 certificates & operator licence is available at site. (Full body harness
inspection report, Hydra, Lifting equipment's, JCB, DG Set etc.)
15 Is electrical power is taken from an approved source.
Standard Distribution Boards with Residual-current circuit breaker
16
(RCCB 30 mA) and MCB is provided.
17 Cables are laid properly to avoid slip, trip & fall.
18 Distribution board is provided with proper stand and canopy sheet.
19 Undamaged/tested electrical equipment at site are being used.
Industrial quality fittings /distribution boxes with continuous wire and
20
three pin plug covered in socket are available at site.
21 Only double insulated electric cable is used at site.
22 Check the availability of Micro Siting drawing & verify the co-ordinates
Check the availability of machineries & manpower to perform soil
23
investigation at WTG locations
24 Check whether the approach road layout is approved by client
Check the material to be used for construction of approach road is
25
approved by client (Murrum or WBM)
26 Is the laboratory setup completed prior to construction?
27 Check the location marking is done prior to soil excavation
Check whether the top soil is stripped & debris is removed prior to soil
28
excavation
Check the availability of machineries, manpower & survey tools to
29
perform excavation at WTG locations
Check whether the soil treatment/soil stabilization is required prior to
30
excavation works
Check whether the approval for construction material is done by client
31
(Cement, Sand, Aggregate, Water, Admixture, Reinforcement Steel,
Department : Construction Management - Wind Section No. : 07
VIVIID RENEWABLES PRIVATE LIMITED 1.0 / 0 1 .01.2024
Ver. No. / Date
Package : Civil Work
Sr.
Description for Key Requirements of HSE
No.
11 Ensure all firefighting equipment available.
12 Ensure that the Emergency Numbers are posted at site, and personnel are informed in the TBT.
For early morning works/ night works, ensure sufficient lighting arrangements/ lighting towers are in
13
place at the work areas as applicable.
14 More than 12 hours work should not be carried out.
15 Using of mobile phone strictly prohibited during work
16 Convex mirror to be fixed at Blind spot and Ensure that the Reverse horn and Beacon lights are working.
17 Ensure that the vehicle driver has valid driving license.
18 Ensure that cleaner is present with driver.
19 Before allowing for entry inside the site premises do alcohol test of driver & cleaner.
20 Instruct to driver to driver carefully within the speed limit as per site guideline.
21 Ensure that the pathways for the vehicle is defined and barricaded.
22 Do not feed or befriend with stray animals / wild life and make sure the team always stay together.
Ensure a cooperative arrangement whereby individuals are paired or teamed up and assume
23
responsibility for one another's welfare or safety.
24 Take a short break.
25 Ensure availability of ample quantity of fresh water.
26 Do not touch any plant/Tree or utilities without proper knowledge.
27 Do not touch any unidentified objects. immediately stop the activity, inform site in charge.
28 Ensure that all the vehicles are inspected for damaged hose or Oil leakage daily.
29 Ensure periodic maintenance is done for the vehicle and equipment's.
30 Ensure trained spill response team and Spill kit is available on the site.
31 Positive Isolation to be done If any Underground services is present.
32 Check the ground with metal/ Cable Detector for any underground services.
33 Check previous drawings for underground services.
Ensure no charged electrical cables or other service line is present underneath the excavate area, if not
34
sure make a trial pit.
35 Inspection of excavation tools.
36 Ensure all area must be barricade to restrict un-authorized entry with display the safety signages.
37 Wash the effected body part with water immediately after concrete burns.
38 Use of anti-itching cream or lotion over itching body part.
Remove all combustible materials from the location of the cutting, grinding, and abrasion activities
39
taking place.
40 Should check electrical equipment, extension lead, Lead severed by angle grinder disk or saw blade.
41 RCCB should installed on mains supply or portable generator.
42 Ensure guard on moving part and compatible size of wheel for the equipment rating.
43 Ensure Dust Control is done by spraying water to avoid flying Dust.
44 Ensure to handle the material carefully.
45 Ensure that the moving part of M/c must be guarded.
Ensure the workers are having tight clothes and no dangling or lose clothing to avoid entanglement with
46
the vibrator.
Lifting gear/equipment inspected with help of inspection checklist and ensure TPI to be done by a
47
competent person.
Check wire rope, shackles, hooks and rings for cracks, corrosion, wears, mechanism faults etc. and
48
remove from service if faults are found.
Pre lifting plan should be prepared before start of lifting any materials by crane. It is to be ensured that
49
it should not cross the SWL of the crane.
VIVIID RENEWABLES PRIVATE LIMITED 1.0 / 0 1 .01.2024
Ver. No. / Date
Package : Civil Work
Sr.
Description for Key Requirements of HSE
No.
50 Ensure Outrigger Pad or Mat shall be used for the crane.
51 Ensure that two-point Tag Line or Guide-rope shall be used at the time of lifting of the equipment.
52 Ensure that no one is keeping hand directly on the Load.
53 Ensure no obstacles on pathway while unloading the equipment.
54 Not to stand under/near to the suspended load.
Ensure that the vehicular movement is to be restricted where the shifting or handling of material is
55
carried out.
56 Ensure the ground is levelled and graded to avoid toppling of vehicle.
During shifting of material if there is any HT electrical utilities proper & necessary precaution should be
57
taken such as Goal post/Bunting Pole should be ensured.
58 Material Should not be stacked below the Overhead HT electrical lines.
59 Use of stopper/ wheel chock is to be ensured.
60 Ensure that person should not take rest below the vehicle or shadow of vehicle.
Ensure all Drivers/ Operators have gone through Defensive Driving Training, Safety Induction and have
61
valid driving license.
62 Do not position any equipment close to the trench.
63 Ensure Supervisor to be available at site.
64 Ensure a competent signalman with proper Hi Viz fluorescent Jacket and Whittle is assigned.
65 Don’t allow the person to lift more than 30kg material to shifting from one place to other.
66 Two or more workers shall be deployed for handling of Material.
67 Proper coordination shall be maintained by workmen among them while manual handling of material.
Before deploying workmen for manual handling, their physical capabilities shall be taken in to
68
consideration by activity supervisor.
69 Prior to access the material the route needs to be clear.
70 Sharp edges of material can be removed by abrasive method before lifting.
71 Ensure for housekeeping shall be done at all times.
72 Ensure no one walks over the material to avoid Slip Trip and Fall.
73 A tools bag shall be carried while working at height
The equipment (tools, tackles, cables & sockets / terminals etc.) not being used must be disconnected
74
and stored separately.
75 Ensure proper wind up.
76 Ensure that working area shall be left clean and tidy before leaving the site.
77 PTW to be closed on completion of Job.
78 Cross verify the all isolation before leaving the site.
Ensure all shall wear mandatory PPEs with job specific PPEs like (Cut resistant/leather/Rubber hand
79
gloves, Face shield, Safety goggle, Nose Mask)
VIVIID RENEWABLES PRIVATE LIMITED 1.0 / 0 1 .01.2024
Ver. No. / Date
Package : Civil Work
6. Resource Required
Assuming the manpower calculation for 25 Nos. of WTG Foundation.
Assuming the 2 MW WTG wind foundation and capacity may vary from 1.5 MW to 2.5 MW.
Concrete quantity and cement quantity are totally depending on WTG type, OEM selection, Soil strata
and location of site.
Assuming, Cement quantity/WTG vary from 2800 Bags to 47 Bags and depend on WTG type/design
mix.
Assuming, reinforcement quantity/WTG vary from 34Tons to 55Tons and depend on WTG type/design
mix.
Foundation cost will be varying from 16 Lacs to 23 Lacs depend OEM selection and WTG type
As per industry standard practice, a total of 1 teams will be required for a 50 MW Wind Project.
WTG tower erection will be start after 7 days cube test/achieving compressive strength 70% or as per
OEM /WTG technical specifications.
The table below shows the table for Manpower and No. of Man-days calculations for the activity:
WTG
Foundation
VIVIID RENEWABLES PRIVATE LIMITED 1.0 / 0 1 .01.2024
Ver. No. / Date
Package : Civil Work
Don’t operate the Ajax/JCB etc. if you are not competent for it similarly not allow to other to do so.
Don’t deployed untrained worker for work.