Revision Date: 2009/12/31 Form No.: S-075102-02FIG Approver: DPA
Ballasting / De-Ballasting Operation
Notice at Ballast Control Panel Figure
General Precaution to Avoid Damage to
Centrifugal Ballast Pump Think before operating valves and pumps, remind yourself of What You Are Doing!! 9 Operate valves gradually and sequentially (one by one) to minimize the effect of Pressure Surge (water hammering). 9 Ensure that suction line and pump casing are always filled up with liquid before starting pump or changing over pump suction. 9 Throttle the delivery valve of centrifugal pump sufficiently or shut it off (as appropriate) before changing over pump suction. 9 For safe operation of pump, monitor following ¾ suction and delivery pressure of pump ¾ Casing & bearing temp and vibration of pump ¾ Current drawn by pump. ¾ Tank Sounding 9 If suction and delivery pressure of pump are unsteady, lower the pump rpm and/or throttle delivery valve gradually, till pressure becomes steady.
9 Be aware, failure to comply with above can result in Heavy