SUMMARY OF MATERIALS FOR CONCRETE WORKS

SCOPE OF WORK 40KG FINE SAND COURSE EARTH FILL


CEMENT AGGREGATE

Bags Cu. m Cu. m Cu. m

COLUMN C1= 27 bags C1= 1.477 Cu. M C1= 2.955 Cu. M


C2= 34 bags C2= 1.899 Cu. M C2= 3.799 Cu. M
C1 x 7
C2 x 9 C-total= 61 bags C-total= 3.376 C-total= 6.754
Cu. M Cu. M

FOOTING 41 bags 2.254 Cu. M 4.507 Cu. M

TIE BEAM 32 bags 1.769 Cu. M 3.54 Cu. M

CONCRETE BEAM 42 bags 2.327 Cu. M 4.654 Cu. M

CONCRETE ROOF 38 bags 2.136 Cu. M 4.271 Cu. M


BEAM

FLOOR SLAB
- GROUND 57 bags 3.796 Cu. M 7.592 Cu. M
FLOOR 111 bags 7.407 Cu. M 14.814 Cu. M
- 2ND FLOOR

STAIRS 28 bags 1.779 Cu. M 3.164 Cu. M

KITCHEN 28 bags 1.543 Cu. M 3.087 Cu. M

SEPTIC TANK 18 bags 1.160 Cu. M 2.454 Cu. M

CATCH BASIN 3 bags 0.202 Cu. M 0.403 Cu. M

TOTAL
433 bags 26.36 Cu. M 52.462 Cu. M
SUMMARY OF MATERIALS FOR MASONRY WORKS

SCOPE OF WORK CEMENT 40KG FINE SAND

EXTERIOR WALL:
258.952 sqm

CLASS B CHB

Total: 3236.9/ 3237 pcs “6”

INTERIOR WALL:
144.97sqm

CLASS B CHB

Total: 1812.125/ 1812 pcs “4”

MORTAR
277 bags 22.953 Cu. M
EXTERIOR: 15 x 20 x 40
258.952 sqm
79 bags 6.626 Cu. M
INTERIOR: 10 x 20 x 40
144.97sqm TOTAL= 356 bags TOTAL= 29.579 Cu. M

PLASTERING: 16 MM CLASS B 81 bags x 2 6.78 Cu. M x 2

TWA: 403.922 sqm 162 bags 13.56 Cu. M

TOTAL
518 bags 43.139 Cu. M
SUMMARY OF MATERIALS FOR STEELWORKS

No. of Tie #16 G.I. Tie


6 x 16 dia.
SCOPE OF WORK 6 x 10 6 x 12 dia. wire Wire
bars
dia. bars bars

Pcs. Pcs. Pcs. Pcs. Kg.

CHB
REINFORCEMENT 187 9.69
BARS

FOOTING
REINFORCEMENT
31 152.4 2.875

COLUMN 140

LATERAL TIE 87 608 27. 53

TOTAL 305 140 760.4 40.095

BILL OF QUANTITY

SCOPE OF WORK QUANTITY UNIT UNIT PRICE SUB-


TOTALL

SITE WORKS

EARTH FILL 139.111 Cu. M 1100/Cu. M


P153,022.1
CONCRETE WORKS

CEMENT 40KG 433 bags 255/bag P110,415

SAND 26.36 Cu. M 1700/Cu. M P44,812

GRAVEL 52.462 Cu. M 1400/Cu. M P73,446.8

P228,673.8

MASONRY WORKS

EXT: 3237 EXT: “6” “6” = 17/pc EXT: P55,029


CONCRETE HOLLOW INT: 1812 INT: “4” “4” = 15/pc INT: P27,180
BLOCKS
TOTAL:
P82,209

356 bags 255/bag P90,780


MORTAR
29.579 Cu. M 1700/Cu. M P50,284.3

162 bags 255/bag P41,310


PLASTER
13.56 Cu. M 1700/Cu. M P23,052

P287,635.3

TOTAL
P669,331.2