This quotation provides rates for steel fabrication work for the foundations of a grain terminal project. It lists the rate of SAR 70 per cubic meter for fabricating steel for raft foundations only. Payment will be in cash and the client will provide transportation, accommodations, PPEs, and tools/equipment while the quoted rates exclude VAT.
This quotation provides rates for steel fabrication work for the foundations of a grain terminal project. It lists the rate of SAR 70 per cubic meter for fabricating steel for raft foundations only. Payment will be in cash and the client will provide transportation, accommodations, PPEs, and tools/equipment while the quoted rates exclude VAT.
This quotation provides rates for steel fabrication work for the foundations of a grain terminal project. It lists the rate of SAR 70 per cubic meter for fabricating steel for raft foundations only. Payment will be in cash and the client will provide transportation, accommodations, PPEs, and tools/equipment while the quoted rates exclude VAT.
Subject: - Fabrication of steel at RAS-AL-Khair Grain Terminal Project
Sr No Description Unit Rate/Unit (SAR)
1 Fabrication of steel for Raft Cubic Meter 70
foundations (only)
Terms & Conditions:
• Transportation, Food, Accommodation and PPEs to be provided by Red Wave Contracting. • Bill payment will be in cash. • The above given price is without VAT. • All other tools & equipment’s to finish the job on site will be provided by RED WAVE CCONTRACTING.