Slow progress of work

1. Repair blocked conduit in shear wall (second floor)


2. Repair blocked conduit in shear wall (third floor)
3. Inspection conduit pipe in shear wall (fourth floor)
4. Install conduit pipe (LV service) in bricklaying (C1, C2,C3,C4,C20,C21) ( Staircase 2
area , staircase 3 area , lobby area , electrical riser , ELV riser, Mechanical riser , Fire
Fighting riser) (4th floor) ( already delay the plastering work)
5. Install AC drain pipe, copper pipe (C21) (4th floor)
6. Recorrect copper pipe in shear wall (C7, C8, C15) (first floor)
7. Install temporary supply (Lighting point and socket point) (Level 4 & Level 5)
immediately was complained by archi worker didn’t have enough socket to be used (still
waiting cable)
8. Repairing the temporary supply (always short circuit) ( Level 1& Level 2 ) ( Lighting )
( staircase 3 and lobby area) was complained by worker very dim