13. SBC (Safe Bearing Capacity) : Soil report will be given by the Department.
of soil
14. The column and locations shown in arch drawings are tentative only and can be changed
as per structural requirement. However the layout plan will remain the same. Crumple joints /
expansion joints shall be given as per structural design requirement in accordance with BIS
codes.
15. The consultant shall be liable to extend prompt assistance in clarifying any doubts on
design / drawing and shall provide extra details or supplementary drawings, if required, at no
extra cost to the department during tendering and execution of the work. Modifications if any
required on account of the conditions / users requirements shall be attended to by the
consultant during execution of the project without any extra cost.
16. The scope of work besides the servicers / utilities mentioned under scope of work above
shall deem to include any contingent work though not specifically mentioned but are found
indispensable for full and final execution of the project as per technically sound engineering
practice. No extra fee is payable on this account.
17. Structural drawings and design once submitted will be the property of Chief Engineer
Chennai Zone Chennai and the consultant will have no claim or rights thereafter on the same.
This HQ reserves the right to adopt the drawings in any other Govt work in future.