Professional Documents
Culture Documents
Turbine Generator System
Turbine Generator System
OPERATION MANUAL
TURBO GENERATOR OPERATION
(DOC. NO. PU/III/29)
COPY NO.
DESCRIPTION NAME
B.T. SESHA SAYEE
DESIGNATION SIGNATURE
PREPARED BY G.S. RAO
M. SUBBARAMAIAH
CH KOTESWARA RAO SO/F
REVISED BY
G SRINIVAS Dy PM (U)
REVIEWED BY V.V. UPADHYAYA PM (U)
APPROVED BY ARUN BOSE DGM (U)
Doc. No: PU/III/29
HWP (M) INDEX Chapter A
23.
Log Sheets PU/III/29, Chapter 13.5 100
24.
Governing Relations PU/III/29, Chapter 13.6 103
25.
Protection Relay Settings PU/III/29, Chapter 13.7 104
26.
Power Supplies PU/III/29, Chapter 13.8 106
27.
Turbine material of construction PU/III/29, Chapter 13.9 109
28.
Turbine and generator curves PU/III/29, Chapter 14.0 110
SN Acronym Description
o
1.
AC/DC JOP Alternating/Direct current Jacking Oil Pump
2.
ACWP/CCWP Auxiliary/Condenser cooling water pump
3.
AOP Auxiliary Oil Pump
4.
CHP Coal handling plant
5.
COT/DOT Clean/Dirty oil tank
6.
DAVR Digital Automatic Voltage Regulator
7.
EHTC Electro Hydraulic Turbine Control
8.
EOP Emergency Oil Pump
9.
ERV Electromatic Relief valve (for Boiler)
10.
ESV Emergency Stop Valve
11.
GCP/GCD Generator control Panel/Desk
12.
GOP Governing oil pump
13.
GRP Generator relay panel
14.
GSCVEF Gland Steam Condensate Vapor Extraction Fan
15.
GT Generator Transformer
16.
HP/LP High/Low Pressure
17.
IBV Integral bypass valve
18.
LDB Lighting Distribution Board
19.
MCR Main Control Room
20.
MD Maximum Demand
21.
MOP Main Oil Pump
22.
MOT Main Oil Tank
23.
MOV /LCV Motor Operated/Level Control Valve
24.
MSJAE/SAE Main steam jet/Starting air ejector
25.
OS Operating Station
26.
OTO Order To Operate
27.
OVEF Oil Vapor Extraction Fan
28.
PT/VT Potential/Voltage Transformer
29.
QC NRV Quick closing non-return valve
30.
SSG Station Switch Gear
31.
TCP/BCP Turbine/Boiler Control Panel
32.
UAT Unit Auxiliary Transformer
33.
USSG/UASG/UESG Unit Service/Auxiliary/Emergency Switch Gear
34.
VAR Volt Ampere Reactive
0 MASTER COPY
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
PREFACE
This Operation Manual has been prepared with an intention to provide sufficient
information to the Operation Personnel to guide them in operating the system as intended.
Though every effort has been made to include all details required for operation, it may be
noted that it is difficult to foresee each and every contingency that may arise during
operation of the system and no amount of written instruction can replace an EXPERIENCED
OPERATOR especially when coping-up with unforeseen operating condition.
Standard Order To Operate (OTO) given shall be used as a GUIDANCE for preparing
final OTOs which depends on conditions of the process existing at that time and also one
may have to ascertain the conditions from field.
Sd/-
(M. SUBBARAMAIAH)
I. INTRODUCTION
1.1 Steam Turbine-Generator of Captive Power Plant is single cylinder, condensing and
impulse-reaction turbine of type EK1800-2 supplied by M/s BHEL. TG is designed for a
normal output of 27 MWe and is capable of generating 30 MWe (Max). TG is
provided with HP extraction (controlled) and LP extraction (uncontrolled but
controlled externally) at 32 ata and 8 ata respectively. Extraction steam is used for
process requirements in Main Plant.
1.2 TG is also provided with Electro Hydraulic Turbine Controller (EHTC), Hydraulic
Governor (SR-IV), Turbine Stress Evaluator (TSE), Vacuum unloading gear and Load
shedding relay. Hydraulic governor acts as a back up to the EHTC.
1.3 Inlet steam conditions to TG are 101 kg/cm 2 (a) and 480oC. Maximum designed steam
flow through turbine is 241.5 T/hr. Under these conditions following are the output
values:
Generation : 30 MWe
HP Steam : 133 T/hr
LP Steam : 39 T/hr
Flow to condenser : 69 T/hr
Condenser vacuum : 0.107 kg/cm2 (a)
1.4 The generator is of air-cooled type and is equipped with static excitation system with
digital automatic voltage regulator (DAVR). Generation voltage is 11 kV.
For details regarding testing procedures of the above, refer Operation Manual
on `Procedures for functional tests’.
2.4 TG can be operated with steam drawn from any Steam Generator.
2.5 CO2 Fire Extinguishing System for Generators
Automatic CO2 Extinguishing System with provisions of Electrical and Manual
Operation is provided for fighting generator fires in Captive Power Plant, Heavy
Water Plant (M).
Two batteries of CO2 cylinders each of capacity 4 x 45 kg, are provided. The
batteries are designated as `Main’ and `Standby’. Each CO 2 cylinder is seamless,
solid drawn holding the liquid CO2 under 750-800 psi at about 34 oC. A selector
switch is provided on the CO 2 Main Control Panel to select either `Main’ or
`Standby’ CO2 battery to discharge in the event calling for CO2 release.
Generator CO2 system trouble’ annunciation appears when generator cooling air
outlet temperature reaches 80oC.
Carryout Order to Operate No.7 to ensure that the CO 2 extinguishing system for
the concerned Generator is in poised state.
IV. PROTECTIONS
4.0 Turbine Protections
NOTE: Electrical and Mechanical trip settings are at the same level for Lube Oil
Header pressure low- low, condenser vacuum low- low, Axial displacement
high-high, controlled extraction pressure high-high whereas for over speed,
electrical trip setting is 3270 rpm and mechanical trip setting is 3300 rpm.
Class-A group will comprise all those faults which are severe in nature
and needs complete shut down of both turbine and generators
simultaneously and instantly. These are,
I. Generator Protections
NOTE: Fast change over of Unit Board to Station board will not take place when TG trips
after actuation of Class-C protection. Otherwise fast change over takes place on
class A protections. Class-B protection facilitates overlapping/parallel change over
where T4 closes on class-B lock out and subsequently sensing T 4 close, I1 gets
opened.
4.2.11 Check whether the over speed governor tester oil pressure is developing by
operating the over speed tester and keep it in released position.
4.2.12 Check for correct and smooth functioning of the hydraulic actuators of NRVs
by operating the drain speeder and keep them in closed position.
4.2.13 Vacuum unloading gear is not being in service. So, ensure oil line isolation
valve to this device is in closed condition.
4.2.14 Fill hot well with make up DM water and keep CEP in service. Check auto
change over of CEPs and keep one CEP in service and other on auto.
Turbine startup in general are classified into three categories viz. Cold startup,
warm startup and hot startup depending upon the length of shut down of TG/
turbine casing metal temperatures. Procedure for cold startup of the TG is
given below.
4.3.1D Pull vacuum in the condenser with Starting Air Ejector Admit gland
steam when vacuum in the condenser is 200 mmHg
After obtaining around 500 mmHg of vacuum, take Main Steam
Jet Air Ejector into service and cut off SAE (if vacuum starts falling,
check for air leakages, otherwise wait till TG attains rated rpm then cut off
SAE).
Keep gland steam pressure controller and steam Jet Air Ejector
pressure controllers on Auto as per the procedures given in respective
operation manuals.
4.3.1E After achieving 350oC before ESV, open main steam inlet valve
to TG.
4.3.1F For rolling of TG ensure the following:
1. TG is on barring gear.
2. Lube oil inlet temperature to bearing is in between 38oC to 40oC.
3. Main steam inlet temperature is more than 430oC.
4. The following turbovisory instrument readings are within limits.
a) casing expansion
b) shaft eccentricity
c) axial displacement
d) vibrations of shaft
e) vibrations of bearing housing
f) bearing metal temperatures.
4.3.1H Open emergency stop valve through starting device Open the
starting device till HP and LP control valves begin to open and turbine
starts rolling. Record the HP & LP secondary oil pressures and
corresponding valve lift and ensure that they are matching with the chart
given in governing relations(chapter 12.6). Turbine stress evaluator is not
commissioned. So, it is not in line. Roll the turbine as per start up curves.
Rolling will start through starting device only if it is on hydraulic
control, i.e. either EHTC outlet valves are closed or EHTC signal (speed
reference) is more than actual speed required.
4.3.1J Bring TG speed gradually to 1000 rpm. Refer Table-2.2 for rate of rise of
speed and soaking period to be maintained during rolling.
4.3.1K Soak the turbine at 1000 rpm for 30 min. Ensure casing expansion,
differential expansion, shaft eccentricity, axial displacement, shaft
vibrations and lube oil return temperatures from bearings are within
limits. Record the values.
4.3.1L Raise TG speed further through starting device (on hydraulic)/speed
reference (On EHTC). Cross critical speed very quickly/instantly and bring
TG speed to 2200 rpm.
4.3.1M Soak the turbine at 2200 rpm for 30 min. Monitor turbovisory instrument
readings continuously for any abnormality.
4.3.1O At a speed of around 2550 rpm governor will take control and hence is
not possible to raise TG speed further. Open the starting device fully.
Note down the governor take over speed and note down the starting
device position at that speed.
4.3.1P Now, raise TG speed to 3000 rpm with speeder gear (on hydraulic)/speed
reference (On EHTC).
4.3.1Q At 3000 rpm conduct oil injection test for over speed governor. Note
down the pressure at which over speed bolt is acting. Carry out actual
over speed test if TG is being started after annual overhaul. (Refer
functional test procedure for details).
4.3.1S Ensure Main Oil Pump (MOP) has taken over at rated speed by
observing the current of AOP. (Current drawn by AOP will decrease
once MOP takes over) Note down the MOP take over speed. Stop
AOP and keep it on `Auto’. (Not applicable pl see note below).
NOTE: As MOP is removed, AOP will be in service continuously, other
AOP must be on auto
4.3.1V Take one set of readings of all parameters as per log sheets of TG and
check whether they are within limits.
4.4.1 When TG is at 3000 rpm check that the following parameters are
within limits.
1. Condenser vacuum
2. Lube oil temperature
3. Main steam inlet temperature
4. Lube oil header pressure
5. TG bearing vibrations.
6. Axial thrust
7. Turbine casing expansion (both in field and in MCR)
8. Turbine differential expansion
9. Thrust pad element temperatures
10. TG running noise
11. Generator air inlet temperature
12. Turbine bearing metal temperatures
13. Primary oil pressure
4.4.2 Close the field breaker of the Generator as per the procedure given in
Generator Excitation System manual. Adjust AUTO POT to reach 11KV
on Generator Terminals.
Note: DAVR has two AUTO and one MANUAL channel. All the three
channels tracking and healthiness to be checked and to be kept on
any AUTO channel.
4.4.5 Match Generator voltage and frequency with that of 33 KV bus. After
obtaining synchro check permissive as indicated by synchro check
relay lamp and synchroscope, close the Generator breaker.
TABLE – 4.1
Minimum Steam Parameters required for rolling of TG
Type of start-up Steam Pressure Steam Temperature (oC)
TABLE – 4.2
Rolling of TG
TG speed Cold start-up Warm start-up Hot start-up
(rpm) Time (Min) Time (Min) Time (Min)
0 to 1000 10 10 10
1000 (soaking) 30 15 -
2200 (soaking) 30 10 10
3000 (soaking) 20 10 05
TABLE – 4.3
Loading of TG
Load Cold start-up Warm start-up Hot start-up
Block load is the load to be picked up immediately after synchronizing the TG with grid/
other TGs.
VI. OPERATION OF TG
5.1 Loading and unloading
Match inlet steam conditions existing prior to the trip (in case of hot
start-up) follow cold start-up, warm start-up or hot start-up
procedure depending upon the length of shutdown period.
1. With zero extractions, TG load shall not be raised more than 16.0
MWe for normal condenser vacuum conditions.
2. Maximum extractions operation is governed by Fig. 5.2
Refer “procedures for functional tests” for carrying out above tests.
TABLE – 5.1
5.4.4 Do not allow hot rotor to come to stand still position. Ensure hand
barring if barring gear motor is not available for operation.
5.4.5 Does not supply gland steam to turbine unless TG is on barring gear.
5.4.6 Do not hold TG at/near critical speed while raising the speed of the
TG.
5.4.8 If after turbine trip, MW does not come to zero, it may be because of
steam coming from inlet/ extractions due to passing of ESV/
governing valves/HP or LP extraction QCNRVs, close the isolation
valves in those lines and allow the generator to trip on low
forward/reverse power.
5.4.9 Do not change the trip set points of TG, unless authorized by
competent authority.
5.4.11 Subsequent to the tripping of steam generators, do not wait for the
turbine to trip on steam temperature low-low protection. Hand trip
the machine immediately.
6.1.4 Changeover 6.6 KV Unit Board Supply from UAT to 6.6 KV station bus.
6.1.5 Reduce TG loads to 1.5MWe and makeup hot well level by opening
hot well make up valve.
6.1.6 Hand trip the turbine and ensure TG has tripped on low forward
power/reverse power.
6.1.7 In case, TG does not trip on low forward power/reverse power, trip
the same from MCR, after applying the remedies suggested in the
trouble shooting section (Item-1).
6.1.8 Ensure emergency stop valve, HP control valves and LP control valves
have closed in the field.
6.1.9 Ensure Generator breaker and Generator Field Breaker have tripped.
Keep Generator breaker in test position.
6.1.11 Ensure Auto start of AOP-I/II when `MOP discharge pressure low’
annunciation appears and note down the corresponding speed of TG.
Presently not applicable as MOP is removed.
6.1.13 After TG has come to rest, engage barring gear and start barring gear
motor.
6.1.14 Note down the time taken for bringing TG shaft to rest.
Revised by: Reviewed by: Approved by:
Revision No: 5.0 Date: 30.12.2019 Page 36 of 123
Doc. No: PU/III/29
HWP (M) SHUT DOWN Chapter 7
6.1.15 Open drain valves on Main steam inlet line, 32 ata extraction line, 8
ata extraction line and Turbine casing drain valve.
6.1.17 When condenser vacuum falls to 200 mmHg isolate gland steam
system to TG.
6.1.18 Keep TG on barring gear for about 72 hrs. (If barring gear motor is not
available for operation, rotate TG rotor by hand each time by 180 o (i.e.
half turn) at an interval of 3 to 4 minutes during the first three hours
after shutting down. After-wards at longer intervals of about 10 min).
6.1.19 Adjust cooling water to oil cooler so as to maintain a bearing oil inlet
temperature of about 35oC.
6.1.20 Stop CEP after 4 hrs of turbine shutdown and switch off the modules
of CEPs. Keep the local push button in locked condition and open hot
well drain after closing make up. Continuous running of CEP not
needed for exhaust hood spray after shifting spray tapping from 0.3 m
elevation to 4.8 m elevation at the U/S of erstwhile hot well LCV.
Header is to be back charged.
6.1.21 Stop barring gear and auxiliary lube oil pump after 72 hrs of shutdown
or when casing temperature comes down to less than 100oC.
6.1.22 Isolate cooling water to oil cooler.
6.1.23 Isolate cooling water to Generator Air Cooler.
6.1.24 Isolate condenser-cooling water when LP exhaust hood temperature
comes below 40oC- 50 oC and open condenser vents and drains. If
condenser C W inlet and outlet valves are passing, drains may be kept
closed but intermittent periodic draining to be ensured.
6.2.2 In case of sudden tripping of one TG, when plant is running at full
load, ie.. 2 Boilers, 2 Turbines and 2 Exchange Units, following actions
are to be taken.
1) Open ERV’s of running boilers and start standby BFP of any unit.
2) Ask M.P to cut out 3 `A’ sections.
6.3.4 Cooling water to oil coolers and Generator air cooler is in isolated
condition.
6.3.6 Gland sealing System and condenser air extraction system are in
isolated condition.
6.3.7 Speeder gear and starting device hand wheels are in closed position.
6.3.10 CEP modules are in OFF condition. Local Push Buttons are in pressed
condition.
6.3.11 Hot well LCV down stream & bypass valves are in closed condition.
Hot well drain valve is in open condition and fill valve is in closed
condition.
6.3.14 Ensure availability of fire fighting equipment & fire hydrant system.
6.3.16 Ensure minimum oil stock of 50% in COT to take care of emergency
requirement. Inform to Mech. Maintenance if the stock is less.
Window
No.(TCP)
Sl.No Description Set Point Operator Action
Window
No.(TCP)
Sl.No Description Set Point Operator Action
Window
No.(TCP)
Sl.No Description Set Point Operator Action
a) Control the steam temperature
especially during cold start-up. Too
06. Turbine T-11 + 5 mm
high steam temperature should be
differential
avoided. Superheat of 50oC is
expansion Hi
optimum.
(Positive)
b) Allow turbine to soak for longer
time.
c) Load the turbine very slowly or if
possible hold the load.
d) In case of excessive positive
turbine differential expansion,
tripping of turbine will help.
e) High gland steam temperature is
also responsible. So control gland
steam pressure and temperature
within the limits.
08. Turbine axial R-11 0.8mm a) Ensure that turbine has tripped
displacement and vacuum breaking valve opens
hi-hi by itself. Otherwise open the
vacuum breaking valve manually
and cut off ejectors to speed-up
coasting down.
b) Investigate the reason and take
corrective action.
Window
No.(TCP)
Sl.No Description Set Point Operator Action
10. TG bearing S-12 100oC a) Check and maintain correct lube oil
metal Temp. flow, pressure and temperature to
high (and fuse bearings.
fail) (Note: b) Periodically analyze lube oil for
Blowing of moisture and other impurities.
UPS supply c) Check axial shift, if thrust-bearing
fuse to the temperatures are high.
turbovisory d) If bearing vibrations are high and if
panel’s temp. bearing temperature continues to
monitoring remain high, reduce load to see if
unit was situation improves, otherwise trip
leading to the unit after ruling out instrument
tripping of malfunctioning.
unit TG; e) If it is the case of power supply
which is now problem to bearing temperature
announced as monitor, take steps to restore the
above. This is supply with the help of I/M.
only an alarm)
Window
No.(TCP)
Sl.No Description Set Point Operator Action
15. Controlled S-21 27 ata a) Auto set point may be low. Select
extraction the correct set point.
pressure low b) Turbine may be running on low
loads. Load the turbine further.
c) HP steam demand may be high.
Improve the header pressure
through PRDS.
d) HP steam demand may be
fluctuating. Take up the issue with
S.S. of MP.
e) Governor may be hunting. Trip the
turbine and initiate DR to M/M.
19. Turbine inlet R-13 430oC a) Ensure that turbine has tripped, if
steam temp. not, trip the same manually.
low-low b) Close main steam isolation valve to
turbine.
c) Open all the drains on Main steam
line.
20. Trip coil not S-7 a) Inform I/M and get the problem
healthy rectified.
b) If problem is not rectified, reduce
the load on TG and trip the same.
Initiate DR.
21. Trip circuit TCD a) Inform I/M and get the problem
healthy on rectified.
GCD b) If problem is not rectified, reduce
disappeared the load on TG and trip the same.
Initiate DR.
Generator
Backup
09. T-5 Same as above Same as above.
Impedance
Relay
Trip(Stage-I)
Buchholz trip.
22. Generator Negative T-10 Leads to Class-B 86G3 1. Ensure that turbine has
Sequence Relay (RA4 in CRP) tripping of tripped. If not hand trip
Trip. (Stage-II). Turbine and the turbine.
(Stands for extreme subsequently 2. Ensure opening of Gen.
Negative sequence Generator Breaker Breaker on low forward
over current through Low Forward power relay. (this is backed
conditions) Power Relay trip action up by reverse power relay
when 86G3 operates trip).
the following occur- 3. Ensure that UASG supply
has changed over to SSG
a) Low forward power
supply. If not, normalize
interlock is made
UASG supply through the
through for the
station tie breaker.
purpose indicated
4. Ensure that GT breaker has
above.
opened.
b) Turbine trip relay is
5. Inform E/M at once.
energized.
As per the
correspondence vide:
IOM initiated date:
30/09/2009 by
Sri.M.R.V.Rajesh SO/F
responded by
Sri.A.N.V.Ratnam SO/F
on 01/10/2009 “VT1” is
used for “32 G1 reverse
power protection”
whereas “VT2” is used
exclusively for metering
in TG-I & TG-III . In TG-II
“VT2” is used for “actual
value” of DVR channel II
along with metering.
Also, leads to
changeover of excitation
from AUTO channel to
MANUAL channel.
t) GT differential
protection.
u) GT oil temp.
Protection.
v) GT winding temp.
Protection.
w) GT oil temp. high
alarm.
x) GT winding temp.
High alarm.
y) GT Mulsifire trip.
DC II failure leads to
failure of the other
protections.
1. Ensure that all the
radiator cooling air
36. Generator S-6 Occurs when one or
fans are in service
transformer more of the following
and all the radiators
trouble protections act:
are in service.
a) Buchholz Alarm 2. Ensure that the local
b) GT winding temp. readings correspond
high alarm (85oC) to alarm level.
c) GT oil temp. high 3. Reduce load to
alarm (80oC). normal and isolate
d) GT Oil level low known overload.
4. Inform E/M section.
5. Physically check the
transformer for any
visible oil leakages or
any other
abnormality
6. In the case of
Buchholz alarm
reduce load to the
minimum or
shutdown the
transformer without
interruption to
essential services,(if
standby TG is on the
bus bars).
39. Generator R-8 This alarm is generated 1. Note down the relay
lockout relay when any of the lockout with faulty coil. Check
Revised by: Reviewed by: Approved by:
Revision No: 5.0 Date: 30.12.2019 Page 63 of 123
Doc. No: PU/III/29
HWP (M) ANNUNCIATIONS AND ACTIONS Chapter 8
40. Class- A R-4 This alarm singly can Same as in Sl.No.1 Also,
LOCKOUT appear when 33KV GT ensure that the 33KV
TRIP. breaker failure, relay or zone of interest is isolated
LBB trip is generated. from all sides (incoming
This leads to effects as and outgoing including
mentioned in Sl.No.1 bus coupler).
NOTE:
1. Some relays are provided with DC/DC converters. Some of the converters have
healthiness indicating `amber’ coloured LEDs which should normally be glowing. Ensure
that whenever DC/DC converters have this LED, these LEDs are glowing.
Revised by: Reviewed by: Approved by:
Revision No: 5.0 Date: 30.12.2019 Page 64 of 123
Doc. No: PU/III/29
HWP (M) ANNUNCIATIONS AND ACTIONS Chapter 8
2. Generator over-voltage and over-fluxing relay alarm stages are used for DAVR limitation
also. E.g. When the `Start’ LED on over-fluxing relay is glowing any attempt of increasing
generator terminal voltage is nullified.
3. The following flags are normally in `operated’ condition: they are known as `supply
monitoring’ flags and prevent trip commands during generator stand still or excitation
buildup/de-excitation conditions:
a) Low Forward Power Relay(RXPE40) Flag.
b) RXIG21, RXEG21 of 64G1 (Stator earth fault relay)
c) RXEG21 of 40G (Loss of Excitation Relay)
d) RXEG21 (3 nos) of VT-1 (voltage balance scheme)
e) RXEG21 (3 nos) of VT-2 (voltage balance scheme)
4. When the `stator 100% Earth Fault’ alarm comes `ON’, it means that the fault is very
close to the neutral and does not affect the system directly. However, second Earth
Fault may prove disastrous.
5. CO2 is automatically released into the generator stator air space in the following events:
CO2 `released’ feed back will occur on sensing of pressure in the CO 2 piping of the unit
generator. This feed back is available on Generator Control Desk.
6. `CO2 system on test’ feed -back is available on GCD. This indicating lamp will glow when
unit CO2 system is put on test by the selector switch in CO2 control panel.
7. Class-A 86G1 lockout relay operates on CO2 release. Presently this is not incorporated.
8. CO2 can be released on emergency basis through emergency release push button on:
a) GCD and/or
b) CO2 main control panel.
c) TG operating floors push button box. On all these cases TG will trip on 86G1 lockout
relay operation. When the Electrical operation is not possible due to any reason, CO 2
can be released by operating the Pull cord system manually. (presently this facility is
not made available)
iv. 32 ata and 8 ata final de-superheating spray CVs go full `OPEN’.
v. 32/16 ata PCV and gland steam PCV will close, hence their bypass to
be opened urgently to maintain vacuum.
X. CONTROL SUPPLY
a. Control supply for turbovisory instruments is extended from 110V UPS. On
loss of control supply, turbovisory protections will not be effective, turbine
continues to be in service with the alarm on TCP (S.12) as turbo generator
bearing metal temperature high/Fuse fail.
b. On loss of 220V DC control supply to Trip Solenoid Valve, Turbine trips will
not be effective. Turbine trip coil healthy annunciation on TCD will disappear.
02. Turbine did not 1. Turbine Main Steam inlet 1. Open turbine main steam inlet
start rolling even valve is in closed valve after ensuring that HP
after HP and LP condition. and LP control valves are at
valves got 2. HP control valve stem min. position.
opened fully. might have broken. 2. Trip the turbine and initiate
D/R to M/M.
03.
MOT level 1. Solenoid valve at
1. Always isolate the centrifuge
dropping centrifuge inlet failed to
by closing the inlet manual
alarmingly. close when supply/ dis-
isolation valve. Initiate D/R to
charge pump is stopped
I/M.
and oil is getting drained
2. Check for oil traces in the fore-
through bowl overflow.
bay of CWPH. If oil is found
2. Turbine lube oil cooler
floating in the fore-bay change
tubes developed
over lube oil cooler, isolate
leakage/got punctured.
faulty lube oil cooler on
3. Severe lube oil leakage in
Revised by: Reviewed by: Approved by:
Revision No: 5.0 Date: 30.12.2019 Page 68 of 123
Doc. No: PU/III/29
HWP (M) TROUBLE SHOOTING Chapter 11
06.
Reduce turbine inlet steam
Wheel chamber Salt deposits on turbine
pressure.
pressure high blades.
Maintain steam purity.
(65kgf/cm2,Max)
Maintain drum level normal.
Overhaul the turbine at the
earliest.
07. Abnormal noise/ Impending failure of GOP Trip the turbine immediately and
vibrations at and their assembly. initiate DR to M/M.
turbine front
pedestal.
11. Sparking
observed from 1. Flash over due to 1. Shutdown the TG and initiate
Generator sight insulation failure. DR.
glasses. 2. Foreign object in the 2. Shutdown the TG and initiate
Generator. DR.
12.
1. Ensure excitation system
1. Carbon brushes got
Heavy sparks voltage and currents are
worn- out.
observed from within limits.
Generator 2. Raise DR to change the brushes.
Excitation If sparks are excessive, trip the
carbon brushes. turbine.
3. Strictly adhere to PM schedule
for brushes checking and
replacement
13.
1. Sudden fall in HP steam 1. Immediately cut out extraction
HP extraction demand due to partial/ and try to save turbine from
pressure rising whole tripping of Main tripping.
suddenly. Plant.
16.
1. Condenser tube leak. 1. Reduce load and isolate one
Hot-well 2. Contamination of Make- half of condenser at a time to
conductivity up water. confirm tubes leak.
high. 2. Check for proper chemistry.
Increase TSP dosing and
initiate blow down
3. Take earliest shut down if tube
leak is confirmed.
17.
1. Sudden increase in load 1. Follow loading and
Parting plane on TG. unloading curves given by
steam leaks. 2. Entry of wet steam. BHEL.
2. Main steam inlet parameters
within limits.
a) –do- A 85 100 -
b) –do- B 85 100 -
c) -do- C 85 100 -
d) –do- D 85 100 -
e) –do- E 85 100 -
f) –do- F 85 100 -
g) –do- G 85 100 -
h) –do- H 85 100 -
ANNEXURES
Technical Details
12.1.1 TURBINE
2. Type : EK-1800-2
12.1.2 GENERATOR
3. Active output : 30 MW
ORDER TO OPERATE-2
12. 1-26-V308 Steam trap isolation valve on the drain line Open
downstream of LP extraction control valve.
ORDER TO OPERATE – 3
Aim: To take vacuum unloading device into service.
( Not to be taken in to service, as it is not commissioned)
09. Match the set point of PIC 5.14 with the actual
process reading.
ORDER TO OPERATE-4
ORDER TO OPERATE-5
ORDER TO OPERATE-6
ORDER TO OPERATE-7
Aim: To keep CO2 extinguishing system for the Generator in poised state
12.2.2 Ensure that the oil leaks from ESV, LP & HP servo motors, if any, are not falling on
hot surfaces of hot TG and its auxiliaries.
12.2.3 Governing system oil leaks, if any, should be collected in the tray provided there.
Remove the collected oil periodically.
12.2.4 If steam leaks from parting plane, are persisting continuously, barricade the area.
12.2.8 Ensure availability of fire water system for turbine main oil tank.
12.2.9 If HP and LP extractions are not in service/ valved in, ensure that their drain speeders
are in closed position and extraction isolation valves (MOVs) are in closed condition.
12.2.10 Check for any water hammering in 32 ata header and 8 ata header.
12.2.11 Check for any water hammering in HP & LP Return Condensate System.
12.2.12 Ensure that the slip-rings cover is in position and its viewing shutter closed.
12.2.13 Ensure that stop push button of barring gear motor is in locked condition before
engaging the turning gear.
Give utmost importance to housekeeping. Keep the floor free from oil and other
obstructions.
VALVE.
AOP-1
EOP
CEP-1
03. AUTO STARTING OF
CEP-2
CONDUCTIVITY OF HOT
02. WELL WATER AFTER
THOROUGH FLUSHING(AT
THE OUTLET OF HOT
WELL/ CEP DISCHARGE)
13.
OVER SPEED TESTER OPERATING LEVER
14. (SHOULD BE IN LIFTED CONDITION)
12.4.2 GENERATOR
Form No – 2(Local)
Remarks
Sl.No Description with
Signature
Status & date
01. LINE UP OF CEP ON RECIRCULATION
C. W TO CONDENSER
JOP’S
C.W TO GEN. AIR COOLER
02 TURBINE STARTUP VENT
03. MAIN STEAM LINE
DRAINS
04. TURBINE CASING
DRAINS
05. MOT LEVEL
06. P ACROSS LUBE OIL (SHOULD BE 1.5
FILTER KG/CM2
07. TURNING
GEAR(TIED/NOT TIED)
08. AVAILABILITY OF CO2 LINE UP
SYSTEM AUTO /MANUAL
09. GT FANS MANUAL OPERATION
A/ M SELECTOR
ALARM/ TRIP SETTING OF
OTI
ALARM/TRIP SETTING OF
WTI
10. UAT FANS MANUAL OPERATION
A/ M SELECTOR
ALARM/ TRIP SETTING OF
OTI
ALARM/TRIP SETTING OF
WTI
11. FIELD FLASHING SUPPLY 1.2R ,UESG TO BE “ON”
MODULES 4.8F 220V UB TO BE “ON”
12. JOP (DC) MODULE 2.5F 220V DC UB TO BE
“ON”.
Form No – 2(Local)
Remarks
Sl.No Description with
Signature
Status & date
15. G.T. BREAKER SPRING CHARGING OK.
DC SUPPLY “ON”.
16 PIN PLUG INSERTED.
SERVICE/TEST POSITION
TRIP HEALTHY BULB `ON’
16. UAT BREAKER SPRING CHARGING OK
DC SUPPLY “ON”.
16 PIN PLUG INSERTED.
SERVICE/TEST POSITION
TRIP HEALTHY BULB `ON’
17. G.T & UAT OIL LEVELS SHOULD BE NORMAL
Form No – 2(Local)
dssdsdfdfd
frequency 10 sec
Continued on next page…
13 40 G Loss of Excitation
20 50,51 For UAT , (a) and (a) High set (50 ) Based on transformer withstand
UAT (b) same as above Iset= 13 A characteristics
(b) IDMT O/C
Iset= 1.64, TMS=0.4, In=1
Sl
Description Module No
No
1 EOP 2.3 F
2 DC JOP 2.5 F
3 BHEL instruments and protection panel 3.3 F
4 Generator protection panel feeder 1 4.3 F
5 Generator protection panel feeder 2 4.5 F
6 BHEL Excitation system (Field flashing and DVR supply) 4.8 F
7 GCP Feeder 1 1.6 R
8 GCP feeder 2 1.8 R
Note: 1.4 R, on 220 V DC unit board-1, feeding to CO2 flooding system (All units) kept off, as
CO2 flooding system is to be actuated from field only.
Sl
Description Module No
No
1 TGIP I/O module and excitation supply (each unit) 1.5F, 2.5F
2 BHEL EHTC Panel supply (each unit) 1.3F, 2.3F
3 TCP annunciation supply (each unit) 3.5R
4 GCP annunciation supply (each unit) 2.3R
5 NT I/O module and excitation supply (U#1) 5.3F, 2.5R
6 NT I/O module and excitation supply (U#2 & U#3) 3.3F, 4.3F
7 MP I/O module and excitation supply (U#1) 4.5F, 4.8R
8 MP I/O module and excitation supply (U#2 & U#3) 6.8F, 6.3R
9 Import/Export controller supply 2.3F on U#1
10 CO2 flooding system (all units ) 1.5F station board
These module nos. are only for guidelines and quick access. Pl cross check with the
breaker list and respective maintenance agency before carrying out any isolations.
Sl
Description Module No
No
1 Nova Tune (NT) CPU Feeder 2
2 Master piece (MP) 1 & 2 CPU Feeder 3
3 Generator Control Desk Feeder 4
4 Generator relay panel, thyristors etc,.. Feeder 5
5 Turbovisory panel Feeder 8
6 TCP, BCP, Hydra step etc,.. Feeder 9
7 TGIP CPU Feeder 10
Sl
Description Module No
No
1 AOP 1A, 2A, & 3A 8.8 F
2 AOP 1B, 2B, & 3B 9.8 F
3 Turning Gear Motor 1.6 R
4 OVEF 1A, 2A, & 3A 1.8 R
5 OVEF 1B, 2B, & 3B 2.4 R
6 Speeder Gear 2.6 R
7 AC JOP (U-1 and U-2) 10.5 R
8 AC JOP (U-3) 10.3 R
9 Starting Device 13.5 R
10 GT and UAT marshalling box 3.8 F
11 Generator field flashing 1.2 R
12 GCD, GCP, and GRP 12.8 F
Sl
Description Module No
No
1 UAT Fan control cubical feeder 1 1.2 F
2 UAT Fan control cubical feeder 2 13.2 F
3 GSCVEF-1A, 2A, and 3A 1.4 F
4 GSCVEF-1B, 2BA, and 3B 16.6 R
5 CEP 1A, 2A, and 3A discharge valve 1.6 F
6 CEP 1B, 2B, and 3B discharge valve 1.8 F
7 CEP 1A, and 3A 5.5 R
8 CEP 2A 12.8 F
9 CEP 1B, and 3B 12.5 R
10 CEP 2B 13.8 F
11 HP Extraction MOV 15.4 F
12 LP Extraction MOV 15.6 F
13 Vacuum breaking valve 16.4 F
14 Main steam I/L Valve (AS004, 5, and 6) 16.6 F
15 GT Fan control cubical feeder-1 1.2 R
16 GT Fan control cubical feeder-2 2.2 R