JOB MIX

FORMULA
FOR DENSE
BITUMINOUS
MACADAM,
VG-3O
(R.k Brothers HM Plant)
(R.k Brothers HM Plant)
Model Economic Township, Jhajjar
Construction of infrastructure development works including road, Sewerage, Drainage, Water
Project supply, Treated water network, Cable Trench & Associated works in MET Industrial colony In Sector-
4 (Phase-1) at district Jhajjar, Harayana

Client METL
Consultant SMEC India Ltd.
Contractor Balajee Infrastructure & Constructions Pvt Ltd.
SUMMARY OF DENSE BITUMINOUS MACADAM

1)Source of Aggregate:- R.K Carrier, kothputli


2)Sample Location :- R.K Brothers HM Plant
3)Grade and Source of Bitumen:- VG-30 HPCL
4)Plant APOLLO ( 160 TPH)

Proportion of Hot Bin Aggregate


1) 30 - 22.5 mm 20.0%
2) 22.5 - 11.5 mm 19.0%
3) 11.5 - 4.75mm 21.0%
4) 4.75 mm Down 39.0%
5) Lime Filler 1.0%

5) Physical Properties of Aggregate/Binder/Fillers Achieved Value


1) Specific Gravity and Water Absorption of Aggregate/Binder/Filler :
Water
Bulk sp. App sp.
Materials Absorpti
Gravity Gravity
on
30 - 22.5 mm 1.19 2.725 2.717
22.5 - 11.5 mm 1.240 2.710 2.803
11.5 - 4.75 mm 1.320 2.673 2.771
4.75 mm Down 1.520 2.612 2.716
Lime Filler - 2.839 2.839
Bitumen VG 30 1.010
2] Aggregate Impact Value 18.72%
3] Combined Flakiness & Elongation Index 21.65%
6) Mix Properties as per graph :--
1] Bulk Specific Gravity of Compacted mix (Gmb) 2.667
2] Optimum Binder Content by wt. of Mix (OBC) 4.50%
3] Optimum Binder Content by wt. of Aggregate (OBC) 4.71%
4] Voids in the Compacted Mix (VIM) 3.86
5] Voids in Mineral Aggregate (VMA) 12.97
6] Voids filled with Bitumen (VFB) 70.29
7] Marshall Stability of the Mix at 600C 20.46
8] Flow of the Mix (mm) 3.1

Contractor's Representative Client's Representative


Jhajjar
ewerage, Drainage, Water
MET Industrial colony In Sector-

ADAM

Requirement as per
Specification

Max. 27%
Max. 35%

3 - 5%
11 - 13%
65 - 75%
Min. 9.0 Kn
2 - 4 mm

Client's Representative
Model Economic Township, Jhajjar

Construction of infrastructure development works including road,


Sewerage, Drainage, Water supply, Treated water network, Cable Trench
Project
& Associated works in MET Industrial colony In Sector-4 (Phase-1) at
district Jhajjar, Harayana
Client METL
Consultant SMEC India Ltd.
Contractor Balajee Infrastructure & Constructions Pvt Ltd.
Dense Bitumen Mecadam - Hot Mix Plant(Hot Bin) Properties
By Weight of Aggregate By Weight of Mix
S.NO. Aggregate Size
% Weight % Weight
1 HB 1 Aggregate Size ( 24.0 mm - 16.0 mm) 20 240 19.10 229.20
2 HB 2 Aggregate Size ( 24.0 mm - 16.0 mm) 19.00 228.00 18.15 217.74
3 HB 3 Aggregate Size (16.0 mm - 3.0mm) 21.00 252.00 20.06 240.66
4 HB 4 Aggregate Size ( 3.0 mm Down) 39.00 468.00 37.25 446.95
5 HB Captured Filler (Lime) 1.00 12.00 0.96 11.46
6 Bitumen Content ( VG- 30 ) 4.71 56.52 4.50 53.98
Total 104.71 1016.52 100.00 1200.00

Temperature Requirements for VG-30

S.NO. Stage of Work Indicated Temperature©

1 Binder Temperature 150-165

2 Aggregate Temperature 150-170

3 Mixed Material Temperature 150 - 165

4 Laying Temperature Min 140

5 Rolling Temperature Min 90

Contractor's Representative Client's Representative


Model Economic Township, Jhajjar

Construction of infrastructure development works including road,


Sewerage, Drainage, Water supply, Treated water network, Cable
Project
Trench & Associated works in MET Industrial colony In Sector-4 (Phase-
1) at district Jhajjar, Harayana
Client METL
Consultant SMEC India Ltd
Contractor Balajee Infrastructure & Constructions Pvt Ltd
Location/Source of Aggregate : R.K Brothers HM Plant
Grade and Source of Bitumen: VG - 30, HPCL Bathinda
Proportion of Hot Bin Aggregate:
1 (30-22.5 mm) HB1 Aggregate 20%
2 22.5-11.5 mm HB2 Aggregate 19%
3 11.5-4.75 mm HB3 Aggregate 21%
4 Dust HB 4 Aggregate 39%
5 Lime Filler 1%
JOB MIX FORMULA
JMF Limits (%) Specified Limits (%)
I.S Sieve Size JMF Permissible
(mm) % Variation
Passing Lower Upper Lower Upper Mid Limit

37.5 100 ±8% 100 100 100 100 100


26.50 100.00 ±8% 100.00 100.00 90 100 95
19.00 92.18 ±8% 85.18 95.00 71 95 83
13.20 65.06 ±7% 59.06 71.06 56 80 68
4.75 39.39 ±6% 34.39 44.39 38 54 46
2.36 30.58 ±5% 26.58 42.00 28 42 35
0.300 13.12 ±4% 10.12 16.12 7 21 14
0.075 2.27 ±2% 0.27 4.27 2 8 5

Remarks:-

Contractor's Representative Client's Representative


NARROW RANGE OF ACCEPTABLE ASPHALT CO
Pass
High
Low

All Criteria
Passes 4.50 %

VMA Min 11-13 %

VFB 65 - 75 %

Voids 3-6%
stability Min 9.0 Kn

Bitumen Min 4.5% 3.50 4.00 4.50 5.00 5.50

Contractor's Representative
EPTABLE ASPHALT CONTENT

Client's Representative
Model Economic Township, Jhajjar
Construction of infrastructure development works including road, Sewerage, Drainage, Water s
Project water network, Cable Trench & Associated works in MET Industrial colony In Sector-4 (Phase-1)
Jhajjar, Harayana
Client METL
Contractor SMEC India Ltd.
Contractor Balajee Infrastructure & Constructions Pvt Ltd.
Worksheet for Volumetric Analysis of Compacted Paving Mixture
A) Aggregate Mix proportion
30 - 22.5 mm 20 %
22.5 - 11.5 mm 19 %
11.5 - 4.75 mm 21 %
4.75 mm down 39 %
Lime Filler 1 %

B) Specific gravity of aggregates

Size of Bulk SP Apparent Water


Remarks
Aggregate gravity SP gravity absorption

30 - 22.5 mm 2.725 2.817 1.19


22.5 - 11.5 mm 2.710 2.803 1.240
11.5 - 4.75 mm 2.673 2.771 1.320
4.75 mm down 2.612 2.716 1.520
Lime Filler 2.839 2.839 -

C) Bulk Specific gravity of mixed aggregate (Gsb)


100
Gsb = = 2.667
20/2.786+19/2.717+21/2.677+39/2.612+1/2.839

Appraent Specific gravity of mixed aggregate (Gsa)


100
Gsa = = 2.765
20/2.828+19/2.812+21/2.775+39/2.716+1/2.839

Maximum Specific gravity of mix (GMM) Bitumen 4.5 %


GMM value 2.528
SP gravity of bitumen (Gb) 1.010

Effecitve Specific gravity of mixed aggregates (Gse)

Pmm - pb 100 - 4.5


Gse = 2.721
Gse = 2.721
pmm/Gmm - pb / gb (100/2.528)- (4.5/1.01)

Contractor's Representative Client's Representative


ajjar
erage, Drainage, Water supply, Treated
ony In Sector-4 (Phase-1) at district

ng Mixture
Representative
Model Economic Towns
Construction of infrastructure development works including road, Sewerage, D
Project
Industrial colony In Sector-4 (Phase-1) at district Jhajjar, Harayana
Client METL
Contractor SMEC India Ltd
Site Balajee Infratech & Construction Pvt Ltd
MARSHALL STABILITY AND FLOW
Asphalt Institue Manual MS-2 , ASTM
Effective Sp. Gr. of total Agg.(Gse): 2.721
Bulk Sp. Gr. of total Agg.(Gsb): 2.667 Bitumen Type:
Sp. Gr. of Bitumen: 1.010 Nos. of compaction blows:

% Agg by total Sp. Gr. Of Wt. of specimen (gm)


wt. of mix mix (GMM)
%Bitumen In air In water SSD
Volume of Specimen
S.No. by total wt.
(C - B)
of mix (((100)/
100 - (1) ((3)/Gse)+ (A) (B) (C)
((2)/Gb))))

(1) (2) (3) (4) (5) (6)


1 1186.0 695.0 1189.0 494.0
2 3.50 96.50 2.532 1190.0 697.0 1192.0 495.0
3 1196.0 701.0 1191.0 490.0
Average
4 1193.0 703.0 1195.0 492.0
5 4.00 96.00 2.524 1191.0 701.0 1191.5 490.5
6 1190.0 699.0 1191.0 492.0
Average
7 1207.0 710.0 1209.0 499.0
8 4.50 95.50 2.528 1195.0 704.0 1196.0 492.0
9 1196.0 707.0 1196.5 489.5
Average
10 1214.0 711.0 1215.0 504.0
11 5.00 95.00 2.512 1195.0 704.0 1196.0 492.0
12 1197.0 705.0 1198.0 493.0
Average
13 1183.0 691.0 1184.0 493.0
14 5.50 94.50 2.500 1204.0 709.0 1205.0 496.0
15 1200.0 703.0 1201.0 498.0
Average
Remarks:

Contractor's Representative
MARSHALL CURVES

BT. Content (%) 3.50


Density (g/cc) 2.415
Stability (kN) 1922.09
Flow (mm) 2.20
Air Voids (%) 4.61
VMA (%) 12.61
VFB (%) 63.63

Contractor's Representative
nomic Township, Jhajjar
including road, Sewerage, Drainage, Water supply, Treated water network, Cable Trench & Associated works in MET
hajjar, Harayana

RSHALL STABILITY AND FLOW TEST


alt Institue Manual MS-2 , ASTM D 1559
Date of sampling: 26/2/2022
VG 30 Date of testing: 27/2/2022
Sampled & Tested
75 blows on each side Jointly
by:
Stability factor: 3.7690
% Air voids
Bulk Sp. Gr. of % VMA %VFB Stability(KN)
(Va)
Compacted mix
Load
Volumetric
(Dial
100- Dial Correction
{((4)-(7))/ Gauge Corrected
{(7)x(3)/ {(9-8)/9}100 Gauge Factor (As
(A)/(6) 4}100 Reading x Load
Gsb} Reading per table 5.1
Stability
of MS-2)
Factor)
(7) (8) (9) (10) (11)
2.401 5.18 13.13 60.5 524.0 1974.96 0.96 1895.96
2.404 5.05 13.01 61.2 497.0 1873.19 1.04 1948.12
2.441 3.60 11.68 69.2 510.0 1922.19 1 1922.19
2.415 4.61 12.61 63.6 Average 1922.09
2.425 3.93 12.72 69.1 512.0 1929.73 1 1929.73
2.428 3.80 12.60 69.9 501.0 1888.27 1.04 1963.80
2.419 4.17 12.94 67.8 486.0 1831.73 1.09 1996.59
2.424 3.97 12.75 68.9 Average 1963.37
2.419 4.32 13.39 67.7 491.0 1850.58 1.14 2109.66
2.429 3.92 13.03 69.9 463.0 1745.05 1.19 2076.61
2.443 3.35 12.51 73.2 498.0 1876.96 1.04 1952.04
2.430 3.86 12.97 70.3 Average 2046.10
2.409 4.11 14.20 71.0 532.0 2005.11 0.96 1924.90
2.429 3.31 13.48 75.5 515.0 1941.04 1 1941.04
2.428 3.34 13.51 75.3 605.0 2280.25 0.78 1778.59
2.422 3.59 13.73 73.9 Average 1881.51
2.400 4.02 14.98 73.2 624.0 2351.86 0.76 1787.41
2.427 2.90 13.99 79.2 588.0 2216.17 0.81 1795.10
2.410 3.61 14.62 75.3 620.0 2336.78 0.76 1775.95
2.412 3.51 14.53 75.9 Average 1786.15
Client's Representative
MARSHALL CURVES

4.00 4.50 5.00 5.50


2.424 2.430 2.422 2.412
1963.37 2046.10 1881.51 1786.15
2.60 3.10 3.37 3.60
3.97 3.86 3.59 3.51
12.75 12.97 13.73 14.53
68.90 70.29 73.92 75.90

Client's Representative
ted works in MET

6/2/2022
7/2/2022
Jointly

Flow
(mm)

(12)
2.1
2.2
2.3
2.20
2.7
2.6
2.5
2.60
3.1
3.3
2.9
3.10
3.2
3.5
3.4
3.37
3.6
3.5
3.7
3.60
Physical Properties of Aggregates
Kotputli
30-22.5 mm 22.5-11.5 mm 11.5-4..75mm 4.75mm down Combined
Aggregate Impact Value 18.72 18.72
EI and FI 25.65
Water Absorption 1.19 1.24 1.32 1.52 -
Specific Gravity 2.725 2.71 2.673 2.612 -

DBM Mix Properties

%age Bitumen MDD Stability Flow Air voids VMA VFB As per Graph Values on 4.5% Bitumen Content
3.5 2.415 1922.09 2.2 4.61 12.61 63.6 Marshal Density 2.430
4 2.424 1963.37 2.6 3.97 12.75 68.9 Marshal Stability 2046
4.5 2.43 2046.1 3.1 3.86 12.97 70.3 Air Voids 3.86
5 2.422 1881.51 3.37 3.59 13.73 73.9 Flow Value 3.10
5.5 2.412 1786.15 3.6 3.51 14.53 75.9 VMA 12.97
VFB 70.30
GMM 2.528

Marshal Density Marshal stability VMA


2.435 2100 15
2.43 2050 14.5
2.425 2000
1950 14
2.42 1900 13.5
2.415 1850 13
2.41 1800
12.5
1750
2.405 12
1700
2.4 1650 11.5
2 3 4 5 6 7 8 3 3.5 4 4.5 5 5.5 6 3 3.5 4 4.5 5 5.5 6

Air Voids Flow VFB


5 4 80
4.5 3.5
4 75
3
3.5 70
3 2.5
2.5 2 65
2 1.5 60
1.5
1 1 55
0.5 3 3.5 4 4.5 5 5.5 6
0.5
0 0
3 3.5 4 4.5 5 5.5 6 3 3.5 4 4.5 5 5.5 6
3.5 70
3 2.5
2.5 2 65
2 1.5 60
1.5
1 1 55
0.5 3 3.5 4 4.5 5 5.5 6
0.5
0 0
3 3.5 4 4.5 5 5.5 6 3 3.5 4 4.5 5 5.5 6
A

5 5 5.5 6

5 5.5 6
5 5.5 6
Gradation Analysis For DBM mix

Sieve Hot Bin - 1 R.K Carrier Hot bin -2 Hot Bin - 3 from R.K Carrier
sizes
(mm)

30 -22.5mm 22.5 -11.5mm 11.5 - 4.75mm


Sample 1 Sample 2 Average Sample 1 Sample 2 Average Sample 1 Sample 2 Average
37.5 100 100 100 100 100 100 100 100 100
26.5 100 100 100 100 100 100 100 100 100
19 82.92 84.46 83.69 75.44 76.55 75.995 100 100 100
13.2 22.05 20.71 21.38 100 100 100
4.75 33.18 36.92 35.05
2.36 2.84 3.31 3.075
0.3
0.075

Combined grading for DBM 20mm 34%+10mm 28%+Dust 36% + Fille


100
90
80
70
60
50
40
30
20
10
0
0.01 0.1 1

Combined grading Max. Limit Min. Limit


s For DBM mix
Combined
with 20mm
34%+10mm Max. Min.
Hot bin -4 from R.K Carrier
28%+ dust Limit (%) Limit (%)
36% + Filler Combined
2% Gradation
Checked
4.75 mm Down
Filler
Sample 1 Sample 2 Average
100 100 100 100 100.00 100 100 100 100
100 100 100 100 100.00 90 100 100 100
100 100 100 100 92.18 71 95 91.56 92.18
100 100 100 100 65.06 56 80 70.42 65.06
100 100 100 100 47.36 38 54 47.28 39.39
91.27 91.45 91.36 100 37.28 28 42 38.16 30.58
40.77 37.55 39.16 100 16.19 7 21 17.91 13.12
9.82 10.38 10.1 92 3.94 2 8 4.97 2.27

28%+Dust 36% + Filler 2%

10 100

Max. Limit Min. Limit


Model Economic Township, Jhajjar
Maximum Specific Gravity of Bituminous Mixture (GMM )
(As per ASTM D-2041)
Construction of infrastructure development works including road, Sewerage, Drainage, Water supply, T
Project
network, Cable Trench & Associated works in MET Industrial colony In Sector-4 (Phase-1) at district Jha

Client METL
Contractor SMEC India Ltd
Contractor Balajee Infratech & Constructions Pvt Ltd.
Proposed
DBM Date of sampling
Used
30mm-22.5mm -20%, 22.5mm-11.50mm -19%,
Proportion
11.5mm- 4.75mm - 21%, 4.75mm Down-39%, Date of testing
of Agg. Lime-1%

Location/
R.K Brothers HM PLANT, Tested by
Source

Observation & Calculation:- (all weights measured in gram)

Sl.No. Sample No. 1

Percentage of Bitumen by total weight of


A 3.50
mix (Pb)

B Wt. of Bottle 2313

C Wt. of Bottle + water 9789.0

D Wt. of Bottle + sample D=(C-B) 3854.5

E Wt. of Sample(E) 1541.5

F Wt. of Bottle + water + sample 11330.5

G Temperature of water 0C 25

H Vaccume pressure Hg mm 30
Wt. of Bottle + water + sample after
I 10720.3
Reducing Air voids

J Voulume of Materials = E-(I-C) 610.200

Max. specific Gravity of Mix Materials =


K 2.526
E/J (Gmm)

L Average 2.532

Remarks………………………………………………………………………………………………………………….

Contractor's Representative Consultant's Representative


hip, Jhajjar
ture (GMM )

werage, Drainage, Water supply, Treated water


Sector-4 (Phase-1) at district Jhajjar, Harayana

27/2/2022

27/2/2022

Jointly

3.50

2313.0

9789.0

3851.5

1538.5

11327.5

25.0

30.0
10721.3

606.200

2.538

2.532

…………………………………..

Client's Representative
Model Economic Township, Jhajjar
Maximum Specific Gravity of Bituminous Mixture (GMM )
(As per ASTM D-2041)
Construction of infrastructure development works including road, Sewerage, Drainage, Water supply,
Project Treated water network, Cable Trench & Associated works in MET Industrial colony In Sector-4 (Phase-1
district Jhajjar, Harayana
Client METL
Contractor SMEC India Ltd
Contractor Balajee Infratech & Constructions Pvt Ltd.
Proposed
DBM Date of sampling
Used
30mm-22.5mm -20%, 22.5mm-11.50mm -19%,
Proportion
11.5mm- 4.75mm - 21%, 4.75mm Down-39%, Date of testing
of Agg. Lime-1%
Location/
R.K Brothers HM PLANT, Tested by
Source
Observation & Calculation:- (all weights measured in gram)

Sl.No. Sample No. 1


Percentage of Bitumen by total weight of
A 4.00
mix (Pb)

B Wt. of Bottle 2313

C Wt. of Bottle + water 9789.0

D Wt. of Bottle + sample D=(C-B) 3859.5

E Wt. of Sample(E) 1546.5

F Wt. of Bottle + water + sample 11335.5

G Temperature of water 0C 25

H Vaccume pressure Hg mm 30

Wt. of Bottle + water + sample after


I 10720.3
Reducing Air voids
J Voulume of Materials = E-(I-C) 615.200

Max. specific Gravity of Mix Materials =


K 2.514
E/J (Gmm)

L Average 2.524

Remarks………………………………………………………………………………………………………………….

Contractor's Representative Consultant's Representative


ip, Jhajjar
ture (GMM )

Sewerage, Drainage, Water supply,


ndustrial colony In Sector-4 (Phase-1) at

27/2/2022

27/2/2022

Jointly

4.00

2313.0

9789.0

3853.0

1540.0

11329.0

25.0

30.0

10721.3
607.700

2.534

2.524

………………………………………..

Client's Representative
Model Economic Township, Jhajjar
Maximum Specific Gravity of Bituminous Mixture (GMM )
(As per ASTM D-2041)
Construction of infrastructure development works including road, Sewerage, Drainage, Water supply, T
Project
network, Cable Trench & Associated works in MET Industrial colony In Sector-4 (Phase-1) at district Jha

Client METL
Contractor SMEC India Ltd
Contractor Balajee Infratech & Constructions Pvt Ltd.

Proposed
DBM Date of sampling
Used

Proportion 30mm-22.5mm -20%, 22.5mm-11.50mm -19%,


11.5mm- 4.75mm - 21%, 4.75mm Down-39%, Date of testing
of Agg. Lime-1%

Location/
R.K Brothers HM PLANT, Tested by
Source
Observation & Calculation:- (all weights measured in gram)

Sl.No. Sample No. 1


Percentage of Bitumen by total weight of
A 4.50
mix (Pb)

B Wt. of Bottle 2313

C Wt. of Bottle + water 9789.0

D Wt. of Bottle + sample D=(C-B) 3855.5

E Wt. of Sample(E) 1542.5

F Wt. of Bottle + water + sample 11331.5

G Temperature of water 0C 25

H Vaccume pressure Hg mm 30
Wt. of Bottle + water + sample after
I 10720.3
Reducing Air voids

J Voulume of Materials = E-(I-C) 611.200

Max. specific Gravity of Mix Materials =


K 2.524
E/J (Gmm)

L Average 2.528

Remarks………………………………………………………………………………………………………………….

Contractor's Representative Consultant's Representative


ip, Jhajjar
ture (GMM )

erage, Drainage, Water supply, Treated water


ector-4 (Phase-1) at district Jhajjar, Harayana

27/2/2022

27/2/2022

Jointly

4.50

2313.0

9789.0

3854.0

1541.0

11330.0

25.0

30.0
10721.3

608.700

2.532

2.528

…………………………………..

Client's Representative
Model Economic Township, Jhajjar
Maximum Specific Gravity of Bituminous Mixture (GMM )
(As per ASTM D-2041)
Construction of infrastructure development works including road, Sewerage, Drainage, Water supply, T
Project water network, Cable Trench & Associated works in MET Industrial colony In Sector-4 (Phase-1) at distri
Harayana
Client METL
Contractor SMEC India Ltd
Contractor Balajee Infratech & Constructions Pvt Ltd.

Proposed
DBM Date of sampling
Used

Proportion 30mm-22.5mm -20%, 22.5mm-11.50mm -


19%, 11.5mm- 4.75mm - 21%, 4.75mm Date of testing
of Agg. Down-39%, Lime-1%

Location/
R.K Brothers HM PLANT, Tested by
Source

Observation & Calculation:- (all weights measured in gram)

Sl.No. Sample No. 1


Percentage of Bitumen by total weight of
A 5.00
mix (Pb)

B Wt. of Bottle 2313

C Wt. of Bottle + water 9789.0

D Wt. of Bottle + sample D=(C-B) 3863.5

E Wt. of Sample(E) 1550.5

F Wt. of Bottle + water + sample 11339.5

G Temperature of water 0C 25

H Vaccume pressure Hg mm 30
Wt. of Bottle + water + sample after
I 10720.3
Reducing Air voids

J Voulume of Materials = E-(I-C) 619.200

Max. specific Gravity of Mix Materials =


K 2.504
E/J (Gmm)

L Average 2.512

Remarks………………………………………………………………………………………………………………….

Contractor's Representative Consultant's Representative


hip, Jhajjar
xture (GMM )

werage, Drainage, Water supply, Treated


olony In Sector-4 (Phase-1) at district Jhajjar,

27/2/2022

27/2/2022

Jointly

5.00

2313.0

9789.0

3859.0

1546.0

11335.0

25.0

30.0
10721.3

613.700

2.519

2.512

……………………………………..

Client's Representative
Model Economic Township, Jhajjar
Maximum Specific Gravity of Bituminous Mixture (GMM )
(As per ASTM D-2041)
Construction of infrastructure development works including road, Sewerage, Drainage, Water supply, T
Project
network, Cable Trench & Associated works in MET Industrial colony In Sector-4 (Phase-1) at district Jha

Client METL
Contractor SMEC India Ltd
Contractor Balajee Infratech & Constructions Pvt Ltd.

Proposed
DBM Date of sampling
Used

30mm-22.5mm -20%, 22.5mm-11.50mm -19%,


Proportion
11.5mm- 4.75mm - 21%, 4.75mm Down-39%, Lime- Date of testing
of Agg. 1%

Location/
R.K Brothers HM PLANT, Tested by
Source
Observation & Calculation:- (all weights measured in gram)

Sl.No. Sample No. 1


Percentage of Bitumen by total weight of mix
A 5.50
(Pb)

B Wt. of Bottle 2313

C Wt. of Bottle + water 9789.0

D Wt. of Bottle + sample D=(C-B) 3868.0

E Wt. of Sample(E) 1555.0

F Wt. of Bottle + water + sample 11344.0

G Temperature of water 0C 25

H Vaccume pressure Hg mm 30

Wt. of Bottle + water + sample after Reducing


I 10720.3
Air voids
J Voulume of Materials = E-(I-C) 623.700

Max. specific Gravity of Mix Materials = E/J


K 2.493
(Gmm)

L Average 2.500

Remarks………………………………………………………………………………………………………………….

Contractor's Representative Consultant's Representative


p, Jhajjar
re (GMM )

ge, Drainage, Water supply, Treated water


or-4 (Phase-1) at district Jhajjar, Harayana

27/2/2022

27/2/2022

Jointly

5.50

2313.0

9789.0

3864.0

1551.0

11340.0

25.0

30.0

10721.3
618.700

2.507

2.500

……………………………..

Client's Representative
Model Economic Township, Jhajjar
Construction of Infrastructure development works
including Road, Sewerage, Drainage, Water Supply,
Treated water network, Cable Trench & associated wo
Name of Project :- in MET Industrial colony In Sector-4 (Phase-1) at Distri
Jhajjar, Harayana

Contractor :- BALAJEE INFRATECH & CONSTRUCTIONS PVT LTD


Consultants :- SMEC India Pvt.Ltd.
Client :- METL

Specific Gravity And Water Absorption


(Coarse Aggregates)
IS:2386 (Part-3)
Source of material :- Sample no:
Location of material :- Date of sampling: 15/2/2022
Sample description:- (30 - 22.5mm) Aggregate Date of testing: 17/2/2022
Determination no.
SL No. Description
1

Weight of Saturated surface dry aggregate in air


1 (gms) , A
2158.0

2 Weight of aggregate in water (gms), B 1375.0

3 Weight of oven dried aggregate in air (gms), C 2131.0

4 Bulk Specific gravity C / (A-B) 2.722


5 Apparent Specific gravity C / (C-B) 2.819
6 Water Absorption [(A-C) /C] X 100 1.27
A. Mean Value of Bulk Specific Gravity 2.725
B. Mean Value of Apparent Specific Gravity 2.817
C. Mean Value of Water Absorption = 1.19

Remarks _____________________________________________________________________________________________

Contractor's Representative Consultant' Representative


ar
frastructure development works
werage, Drainage, Water Supply,
work, Cable Trench & associated works
colony In Sector-4 (Phase-1) at District

CH & CONSTRUCTIONS PVT LTD


Ltd.

orption

15/2/2022
17/2/2022
Determination no.
2

2172.0

1385.0

2148.0

2.729
2.815
1.12
2.725
2.817
1.19

________________________________

METL's Representative
Model Economic Township, Jhajjar

Name of Project :-

Contractor :-
Consultants :-
Client :-

Specific Gravity And Water Absorption


(Coarse Aggregates)
IS:2386 (Part-3)
Source of material :-
Location of material :-
Sample description:- (22.5 - 11.5 mm)

SL No. Description

1 Weight of Saturated surface dry aggregate in air (gms) , A

2 Weight of aggregate in water (gms), B

3 Weight of oven dried aggregate in air (gms), C

4 Bulk Specific gravity C / (A-B)


5 Apparent Specific gravity C / (C-B)
6 Water Absorption [(A-C) /C] X 100
A. Mean Value of Bulk Specific Gravity =
B. Mean Value of Apparent Specific Gravity =
C. Mean Value of Water Absorption =

Remarks _____________________________________________________________________________________________

Contractor's Representative
omic Township, Jhajjar
Construction of Infrastructure development works including Road,
Sewerage, Drainage, Water Supply, Treated water network, Cable
Trench & associated works in MET Industrial colony In Sector-4 (Phase-
1) at District Jhajjar, Harayana

BALAJEE INFRATECH & CONSTRUCTIONS PVT LTD


SMEC India Pvt.Ltd.
METL

y And Water Absorption


arse Aggregates)
:2386 (Part-3)
Sample no: 1
Date of sampling: 15/2/2022
Date of testing: 17/2/2022
Determination no.
1 2

2176.0 2210.0

1384.0 1403.0

2149.0 2183.5

2.713 2.706
2.809 2.798
1.26 1.21
2.710
2.803
1.24

__________________________________________________

Consultant' Representative METL's Representative


Model Economic Township, Jhajjar
Name of Project :- Construction of Infrastructure development works
including Road, Sewerage, Drainage, Water Supply
Contractor :- BALAJEE INFRATECH & CONSTRUCTIONS PVT LTD
Consultants :- SMEC India Pvt.Ltd.
Client :- METL

Specific Gravity And Water Absorption


(Coarse Aggregates)
IS:2386 (Part-3)
Source of material :- Sample no: 1
Location of material :- Date of sampling: 15/2/2022
Sample description:- (22.5 - 11.5 mm) Date of testing: 17/2/2022
Determination no.
SL No. Description
1

1 Weight of Saturated surface dry aggregate in air (gms) , A 2332.0

2 Weight of aggregate in water (gms), B 1473.0

3 Weight of oven dried aggregate in air (gms), C 2301.0

4 Bulk Specific gravity C / (A-B) 2.679


5 Apparent Specific gravity C / (C-B) 2.779
6 Water Absorption [(A-C) /C] X 100 1.35
A. Mean Value of Bulk Specific Gravity = 2.673
B. Mean Value of Apparent Specific Gravity = 2.771
C. Mean Value of Water Absorption = 1.32

Remarks _____________________________________________________________________________________________

Contractor's Representative Consultant' Representative


r
nfrastructure development works
Sewerage, Drainage, Water Supply,
ECH & CONSTRUCTIONS PVT LTD
t.Ltd.

rption

1
g: 15/2/2022
17/2/2022
Determination no.
2

2256.0

1421.0

2227.0

2.667
2.763
1.30
2.673
2.771
1.32
y

_______________________________

METL's Representative
Model Economic Township, Jhajjar
Construction of Infrastructure development works including Road, Sewerage, Drainage, Water Supply, T
water network, Cable Trench & associated works in MET Industrial colony In Sector-4 (Phase-1) at Distri
Nam e of Project Jhajjar, Harayana

Contractor BALAJEE INFRATECH & CONSTRUCTIONS PVT LTD


Consultants SMEC India Pvt.Ltd.
Client METL

Specific Gravity And Water Absorption


(Fine Aggregates)
IS:2386 (Part-3)
Source of material Sample no: 1
Location of material : Date of sampling: 15/2/2022
Sample description: Dust Date of testing: 17//2/2022
Determination no.
SL No. Description
1

1 Weight of saturated surface dry material, A(g) 620.5

2 Weight of pycnometer + filled with water only , B (g) 1523.0

3 Weight of pycnometer + Material + Filled with water , C(g) 1908.0

4 Weight of oven dry material, D(g) 611.0

5 Specific Gravity D / (A - (C - B)) 2.594


6 Apparent Specific Gravity D/ (D - (C - B)) 2.704
7 Water absorption, % 100*(A - D) / D) 1.55
A. Mean Value of Bulk Specific Gravity = 2.612
B. Mean Value of Apparent Specific Gravity = 2.720
C. Mean Value of Water Absorption = 1.52

Remarks ______________________________________________________________________

Contractor's Representative Consulatant's Representative


e, Drainage, Water Supply, Treated
n Sector-4 (Phase-1) at District

tion

1
ling: 15/2/2022
g: 17//2/2022
Determination no.
2

615.0

1517.5

1902.0

606.0

2.629
2.736
1.49
2.612
2.720
1.52

METL's Representative
Model Economic Township, Jhajjar
SPECIFIC GRAVITY OF ROCK FILLER
Construction of infrastructure development works including road, Sewerage, Drainage, Wate
Project Treated water network, Cable Trench & Associated works in MET Industrial colony In Sector-4
1) at district Jhajjar, Harayana
Client METL
Contractor SMEC India Ltd
Contractor Balajee Infratech & Constructions Pvt Ltd
Laboratory Job No. Date Sampled 18/2/2022
Type of Material Hydrated Lime Sampled By Jointly
Source STARKE ROCKSAND CRUSHER (RACHALUR) Date Tested 18/2/2022
Location BICPL HMP, HOT BIN SAMPLE Tested By Jointly
Proposed Use Bituminous Works

Observation & Calculation :- ( All weights measured in grams)


Specific Gravity Bottle Method :
Description 1 2
Wt. of Specific gravity Bottle,Sample and (gm) 96.18 95.84
Kerosene (A) gravity bottle with
Wt. of Specific (gm) 85.29 85.29
Kerosene (B)
Wt. of Sample (C) (gm) 16.8 16.45
Specific Gravity = (C/(C-(A-B)) 2.843 2.788
Average 2.839

Remarks :-

Contractor's Representative Client's Representative


ar

erage, Drainage, Water supply,


trial colony In Sector-4 (Phase-

18/2/2022
Jointly
18/2/2022
Jointly

3
94.65
85.29
14.32
2.887
839

Client's Representative
Model Economic Township, Jhajjar
Construction of infrastructure development works including road, Sewerage,
Drainage, Water supply, Treated water network, Cable Trench & Associated
Project
works in MET Industrial colony In Sector-4 (Phase-1) at district Jhajjar,
Harayana
Client METL
Consultant SMEC India Ltd
Contractor Balajee Infratech & Constructions Pvt Ltd
Type of Material VG-30 Date Sampled 23/2/2022
Source HPCL Sampled By Jointly
Location Mehta HM PLANT Date Tested 24/2/2022
Proposed Use Bituminous Works Tested By Jointly
SPECIFIC GRAVITY OF BITUMEN
Observation & Calculation :- ( All weights measured in grams)
Specific Gravity Bottle Method :
Description 1 2 3
Wt. of Specific gravity Bottle,Sample
(gm) 84.04 83.76 84.01
and Water
Wt. of (A) gravity bottle with water
Specific (gm) 83.68 83.42 83.64
(B)
Wt. of Sample (C) (gm) 35.00 34.00 34.00
Specific Gravity = (C/(C-(A-B)) 1.010 1.010 1.011
Average 1.010

Remarks :-

Contractor's Representative Client's Representative