Oil - Flushing - Procedure of Coal - Mill - PLTU - ASAM-ASAM
Oil - Flushing - Procedure of Coal - Mill - PLTU - ASAM-ASAM
A. Project Descriptions
1. Scope of Work & Supply Descriptions
a. Install piping system, hydrotest & chemical cleaning if Responsible by PT. Wika
required
b. Cleaning Hydraulic tank Responsible by PT. Wika
h. Oil Cleanliness Test (NAS 1638 Standard Test) Responsible by PT. Maxima
i. Dismantle by pass hoses and re-connected hoses or pipes Responsible by PT. Wika
to the hydraulic system ready for commissioning
j. Provide Oil flushing daily report and Cleanliness Test Responsible by PT. Maxima
Report
1. Preparation
- Place Oil Flushing unit close to the hydraulic system
- Place flushing Oil drums close to oil flushing unit
- Install by hoses at hydraulic valves and pistons as shown at drawing defined by PT. Maxima
(contact Person at site : Mr. Rio & Mr. Probo)
- Install Sampling point at return line