CRS Compliance Resolution Sheet Date 02.03.

2024

Project Name 100 Ltr Reflux Reaction Distillation Unit Project Number GI2209925
Attendees Mr. Abhishek Patel, Mr. Vinay (TPI) Participants 2
Discussions FAT– PO No. 150506

Points Discussed Remarks


1 Conductivity Test of Stirrer to be conducted - Cleared (Stirrer is electrical conductive throughout (Tested by ETC)) As per mail received on 02/03/2024
2 Vacuum Test 60mm hg/hr drop observed, - to be improvised further - To be resolved on site As per mail received on 02/03/2024
3 Insulation Change with insulation material suitable for Operating temp. range - Cleared ( Insulation Suitable for range required from -40 to 250 degree) As per mail received on
4 GLR lifting gap lug gap to be resolved - Cleared ( Gap Filled up, Observed OK)
5 Both Side Earthing is to be provided - Cleared (Earthing lud provided on both side of GLR leg)
6 Welding and paint finish is to be done - Cleared (Anticorosive paint is applied on GLR & Skid / Welding work fininshing is done on skid)
7 Modification in addition line – possibility of reduction in no. of joints - Balance (Further reduction in joint was not possible as pipe is fouling valve direction)
8 Name Plate to be fixed Straight - Cleared (Name plate fixed straight)
9 Cable tray to be provided in SS-304 MOC - Cleared ( SS tray with cover provided with proper wiring)
10 Isolation valve above addition line - Cleared (Angle valve will be provided)
11 Receiver Vessel bottom drain valve ground clearance to be increased till 900 mm. - Cleared (Receiver bottom drain height maintained 900mm from floor level)
12 Thermo-pocket and Dip Pipe Thickness to be increased as it vibrates at higher rpm. i.e 200 rpm- Cleared (Thermo Pocket & Dip Pipe thickness increased & tested at 230rpm(No
13 Stirrer Blade Diameter to be reduced – Confirmation will be given by RHPL, currently blade dia. is 340 and reactor inside dia. 486 - Cleared (Reduced from 350mm to 240mm as per
14 VFD tuning for rpm. Deflection observed in VFD drive reading and actual rotation. - Cleared (VFD tuning is done accurate,Observed reading on Tachometer and VFD rpm are same)
15 MS GLR reactor Pressure test pending - Cleared (Pressure test of GLR jacket and body done, Observed ok) As per mail received on 02/03/2024
16 Chuck Support mounting to be completed - Cleared (Supports provided on chuck)
17 20 ltr receiver vessel alignment to be done. - Cleared (Alignment of receiver vessel observed to be ok)
18 Vibration observed at 250rpm – to be resolved - Cleared (Minimal Vibration Observed, proper foundation for skid to be provided at site after installation)
19 Insulation test certificate to be provided. - Cleared. (attached in file)

Prepared by Abhishek Patel (GAPSPL) Inspected by : Mr. Vinay Yadav (TPI)