MULTIPURPOSE BUILDING CONSTRUCTION PLAN (Schedule/Task List)

Technical Report · June 2020

CITATIONS READS

0 10,311

1 author:

Dipankar Pegu
Indian Institute of Foreign Trade
6 PUBLICATIONS 0 CITATIONS

SEE PROFILE

All content following this page was uploaded by Dipankar Pegu on 09 July 2021.

The user has requested enhancement of the downloaded file.


ID Task Task Name Duration Start Finish Predecessors
Mode
1 Construction of Multipurpose Building (Shopping 496 days Mon 15-06-20 Fri 12-11-21
Mall)
2 Pre-Planning Phase 24 days Mon 15-06-20 Thu 09-07-20
3 Consultation and Evaluation (Engg., Arch., Fin.)10 days Mon 15-06-20 Wed 24-06-20
4 Feasibility Testing and Reporting 6 days Wed 24-06-20 Wed 01-07-20 3
5 Client-Consultants GD 2 days Wed 01-07-20 Thu 02-07-20 4
6 Appontment of Architect 6 days Fri 03-07-20 Thu 09-07-20 5
7 Stakeholder Analysis 3 days Fri 03-07-20 Mon 06-07-20 6SS
8 DETAILED PLANNING INITIATION 0 days Thu 09-07-20 Thu 09-07-20 6
9 Planning Stage 47 days Thu 09-07-20 Fri 28-08-20 8
10 Architectural Designing 32 days Thu 09-07-20 Tue 11-08-20
11 Structural Detailing 25 days Mon 20-07-20 Fri 14-08-20
12 Detailed Estimation 7 days Tue 11-08-20 Wed 19-08-20 10
13 Supply Chain (Human Resource, 6 days Thu 20-08-20 Wed 26-08-20 12
Raw-Materials, Machines, Equipment
14 Appointment of Contractor 5 days Thu 20-08-20 Tue 25-08-20 13SS
15 Appointment of Sub-Contractors 2 days Wed 26-08-20 Thu 27-08-20 14SS+1 day
16 Permission Documentations (Government) 8 days Thu 09-07-20 Fri 17-07-20 10SS
17 EXECUTION OF CONSTRUCTION PHASE (Starts)0 days Fri 28-08-20 Fri 28-08-20 13FS+2 days
18 Execution 394 days Fri 28-08-20 Tue 12-10-21 17
19 Site Clearing and Cleaning 3 days Fri 28-08-20 Mon 31-08-20
20 Levelling 2 days Mon 31-08-20 Wed 02-09-20 19
21 Marking on site as per drawings (Layout) 2 days Wed 02-09-20 Fri 04-09-20 20
22 Temporary setup of construction needs on site2 days Fri 04-09-20 Mon 07-09-20
23 Electrical Supply 2 days Fri 04-09-20 Mon 07-09-20 21
24 Water Supply 2 days Fri 04-09-20 Mon 07-09-20 21
25 Temporary Site Toilets (Portable Sintex) 1 day Fri 04-09-20 Sat 05-09-20 21
26 Portable Site Office 2 days Fri 04-09-20 Mon 07-09-20 21
27 Earth Work 5 days Mon 07-09-20 Fri 11-09-20 26

Page 1
ID Task Task Name Duration Start Finish Predecessors
Mode
28 Excavation 3 days Mon 07-09-20 Wed 09-09-20 26
29 Levelling of the remaining surface after 2 days Wed 09-09-20 Fri 11-09-20 28
excavation
30 Spraying Anti-Termite Treatment (In the 1 day Wed 09-09-20 Thu 10-09-20 29SS
excavated area)
31 Foundation 46 days Thu 10-09-20 Wed 28-10-20 30
32 Foundation work on excavated area (PCC, 4 days Thu 10-09-20 Tue 15-09-20
Main-bars, Distribution-bars)
33 Plinth (BEAM, COLUMN AND SLAB): 8 days Wed 14-10-20 Thu 22-10-20 32FS+28 days
[Reinforcement, shuttering,concrete work]
34 Back Filling 2 days Mon 26-10-20 Wed 28-10-20 33FS+4 days
35 COMPLETION OF SUB-STRUCTURE 0 days Fri 20-11-20 Fri 20-11-20 33FS+28 days
36 Super Structure 228 days Fri 20-11-20 Thu 15-07-21 35
37 Column-Beam- Floor Slab (Level 1) 7 days Fri 20-11-20 Fri 27-11-20
[Reinforcement, Shuttering, Concreting,
38 Brick Masonary and Wall Concreting 11 days Sat 26-12-20 Wed 06-01-21 37FS+28 days
39 Staircase (Conn. LVL1 & LVL2) 7 days Sat 02-01-21 Sat 09-01-21 38FS-4 days
40 Construction of Elevator Area 5 days Sat 26-12-20 Thu 31-12-20 38SS
41 Column-Beam- Floor Slab (Level 2) 7 days Sat 09-01-21 Sat 16-01-21 39
[Reinforcement, Shuttering, Concreting,
42 Brick Masonary and Wall Concreting 11 days Tue 16-02-21 Sat 27-02-21 41FS+28 days
43 Staircase (Conn. LVL2 & LVL3) 7 days Wed 24-02-21 Wed 03-03-21 42FS-4 days
44 Column-Beam- Floor Slab (Level 3) 7 days Wed 03-03-21 Wed 10-03-21 43
[Reinforcement, Shuttering, Concreting,
45 Brick Masonary and Wall Concreting 11 days Thu 08-04-21 Tue 20-04-21 44FS+28 days
46 Staircase (Conn. LVL3 & LVL4) 7 days Thu 15-04-21 Thu 22-04-21 45FS-4 days
47 Column-Beam- Floor Slab (Level 4) 7 days Thu 22-04-21 Thu 29-04-21 46
[Reinforcement, Shuttering, Concreting,
48 Brick Masonary and Wall Concreting 11 days Fri 28-05-21 Wed 09-06-21 47FS+28 days
49 Staircase (Conn. LVL3 & ROOF) 7 days Sat 05-06-21 Sat 12-06-21 48FS-4 days

Page 2
ID Task Task Name Duration Start Finish Predecessors
Mode
50 ROOFING RCC (INCLUDING CURING) 32 days Sat 12-06-21 Thu 15-07-21 49
51 COMPLETION OF CONCRETE WORK 0 days Thu 15-07-21 Thu 15-07-21 50
52 Hardware Work 53 days Sat 12-06-21 Fri 06-08-21 49
53 Window Panel Installation 7 days Sat 12-06-21 Sat 19-06-21
54 Door Installation 6 days Sat 19-06-21 Fri 25-06-21 53
55 Fire Extinguisher System Installation 2 days Fri 25-06-21 Mon 28-06-21 54
56 Water Proofing 4 days Thu 15-07-21 Tue 20-07-21 50
57 Electrical Work 6 days Tue 20-07-21 Mon 26-07-21 56
58 Plumbing Work 3 days Tue 20-07-21 Thu 22-07-21 56
59 Glass Installation Work (4 Showrooms) 2 days Mon 26-07-21 Wed 28-07-21 57
60 Rest Room Fittings Work 4 days Wed 28-07-21 Sat 31-07-21 59
61 Ventilation Work 5 days Mon 02-08-21 Fri 06-08-21 60
62 Interior Work 62 days Fri 06-08-21 Sat 09-10-21 61
63 Putty Work (All levels) 16 days Fri 06-08-21 Mon 23-08-21
64 Flooring (All levels) 23 days Wed 11-08-21 Fri 03-09-21 63SS+4 days
65 Paint (All levels) 20 days Fri 03-09-21 Fri 24-09-21 64
66 Special Wallpaper Work (Specific walls for 6 days Fri 24-09-21 Thu 30-09-21 65
design purpose)
67 Food Court Modular Installation 5 days Fri 03-09-21 Wed 08-09-21 65SS
68 Staircase Railing Installation 5 days Fri 03-09-21 Wed 08-09-21 65SS
69 False Ceiling Work (All levels) 20 days Wed 08-09-21 Wed 29-09-21 65SS+5 days
70 Centralised Air-Conditioning Work (All levels)13 days Tue 14-09-21 Mon 27-09-21 69SS+5 days
71 Modular Setups for Shops (20 Shops) 9 days Wed 29-09-21 Fri 08-10-21 69
72 Interior Design Implementation Work 19 days Mon 20-09-21 Sat 09-10-21 70SS+6 days
73 Exterior Finishing 64 days Fri 06-08-21 Tue 12-10-21 62SS
74 Putty Work (All levels) 16 days Fri 06-08-21 Mon 23-08-21
75 Paint (All levels) 25 days Mon 23-08-21 Fri 17-09-21 74
76 Exterior Designing (Few Sections) 10 days Fri 17-09-21 Tue 28-09-21 75
77 Parking Construction 13 days Tue 28-09-21 Tue 12-10-21 76
Page 3
View publication stats

ID Task Task Name Duration Start Finish Predecessors


Mode
78 Miscellaneous Finishing Installation (CCTV 20 days Mon 20-09-21 Mon 11-10-21 72SS
Installation, Dustbin Installation, etc )
79 MAJOR WORK COMPLETED 0 days Sat 09-10-21 Sat 09-10-21 72
80 Performance and Monitoring 29 days Sat 09-10-21 Tue 09-11-21 79
81 Quality Checks 29 days Sat 09-10-21 Tue 09-11-21
82 Cleaning of entire site (Internal and External) 9 days Sat 09-10-21 Tue 19-10-21 81SS
83 Closer 3 days Tue 09-11-21 Thu 11-11-21 81
84 Final Documentation 3 days Tue 09-11-21 Thu 11-11-21
85 Clearing all bills 2 days Tue 09-11-21 Thu 11-11-21 84SS
86 Collection of data from the project 2 days Tue 09-11-21 Thu 11-11-21 84SS
87 HANDING OVER TO CLIENT 1 day Fri 12-11-21 Fri 12-11-21 83