Professional Documents
Culture Documents
Multipurpose Building Construction Dipankar Pegu
Multipurpose Building Construction Dipankar Pegu
net/publication/342232803
CITATIONS READS
0 10,311
1 author:
Dipankar Pegu
Indian Institute of Foreign Trade
6 PUBLICATIONS 0 CITATIONS
SEE PROFILE
All content following this page was uploaded by Dipankar Pegu on 09 July 2021.
Page 1
ID Task Task Name Duration Start Finish Predecessors
Mode
28 Excavation 3 days Mon 07-09-20 Wed 09-09-20 26
29 Levelling of the remaining surface after 2 days Wed 09-09-20 Fri 11-09-20 28
excavation
30 Spraying Anti-Termite Treatment (In the 1 day Wed 09-09-20 Thu 10-09-20 29SS
excavated area)
31 Foundation 46 days Thu 10-09-20 Wed 28-10-20 30
32 Foundation work on excavated area (PCC, 4 days Thu 10-09-20 Tue 15-09-20
Main-bars, Distribution-bars)
33 Plinth (BEAM, COLUMN AND SLAB): 8 days Wed 14-10-20 Thu 22-10-20 32FS+28 days
[Reinforcement, shuttering,concrete work]
34 Back Filling 2 days Mon 26-10-20 Wed 28-10-20 33FS+4 days
35 COMPLETION OF SUB-STRUCTURE 0 days Fri 20-11-20 Fri 20-11-20 33FS+28 days
36 Super Structure 228 days Fri 20-11-20 Thu 15-07-21 35
37 Column-Beam- Floor Slab (Level 1) 7 days Fri 20-11-20 Fri 27-11-20
[Reinforcement, Shuttering, Concreting,
38 Brick Masonary and Wall Concreting 11 days Sat 26-12-20 Wed 06-01-21 37FS+28 days
39 Staircase (Conn. LVL1 & LVL2) 7 days Sat 02-01-21 Sat 09-01-21 38FS-4 days
40 Construction of Elevator Area 5 days Sat 26-12-20 Thu 31-12-20 38SS
41 Column-Beam- Floor Slab (Level 2) 7 days Sat 09-01-21 Sat 16-01-21 39
[Reinforcement, Shuttering, Concreting,
42 Brick Masonary and Wall Concreting 11 days Tue 16-02-21 Sat 27-02-21 41FS+28 days
43 Staircase (Conn. LVL2 & LVL3) 7 days Wed 24-02-21 Wed 03-03-21 42FS-4 days
44 Column-Beam- Floor Slab (Level 3) 7 days Wed 03-03-21 Wed 10-03-21 43
[Reinforcement, Shuttering, Concreting,
45 Brick Masonary and Wall Concreting 11 days Thu 08-04-21 Tue 20-04-21 44FS+28 days
46 Staircase (Conn. LVL3 & LVL4) 7 days Thu 15-04-21 Thu 22-04-21 45FS-4 days
47 Column-Beam- Floor Slab (Level 4) 7 days Thu 22-04-21 Thu 29-04-21 46
[Reinforcement, Shuttering, Concreting,
48 Brick Masonary and Wall Concreting 11 days Fri 28-05-21 Wed 09-06-21 47FS+28 days
49 Staircase (Conn. LVL3 & ROOF) 7 days Sat 05-06-21 Sat 12-06-21 48FS-4 days
Page 2
ID Task Task Name Duration Start Finish Predecessors
Mode
50 ROOFING RCC (INCLUDING CURING) 32 days Sat 12-06-21 Thu 15-07-21 49
51 COMPLETION OF CONCRETE WORK 0 days Thu 15-07-21 Thu 15-07-21 50
52 Hardware Work 53 days Sat 12-06-21 Fri 06-08-21 49
53 Window Panel Installation 7 days Sat 12-06-21 Sat 19-06-21
54 Door Installation 6 days Sat 19-06-21 Fri 25-06-21 53
55 Fire Extinguisher System Installation 2 days Fri 25-06-21 Mon 28-06-21 54
56 Water Proofing 4 days Thu 15-07-21 Tue 20-07-21 50
57 Electrical Work 6 days Tue 20-07-21 Mon 26-07-21 56
58 Plumbing Work 3 days Tue 20-07-21 Thu 22-07-21 56
59 Glass Installation Work (4 Showrooms) 2 days Mon 26-07-21 Wed 28-07-21 57
60 Rest Room Fittings Work 4 days Wed 28-07-21 Sat 31-07-21 59
61 Ventilation Work 5 days Mon 02-08-21 Fri 06-08-21 60
62 Interior Work 62 days Fri 06-08-21 Sat 09-10-21 61
63 Putty Work (All levels) 16 days Fri 06-08-21 Mon 23-08-21
64 Flooring (All levels) 23 days Wed 11-08-21 Fri 03-09-21 63SS+4 days
65 Paint (All levels) 20 days Fri 03-09-21 Fri 24-09-21 64
66 Special Wallpaper Work (Specific walls for 6 days Fri 24-09-21 Thu 30-09-21 65
design purpose)
67 Food Court Modular Installation 5 days Fri 03-09-21 Wed 08-09-21 65SS
68 Staircase Railing Installation 5 days Fri 03-09-21 Wed 08-09-21 65SS
69 False Ceiling Work (All levels) 20 days Wed 08-09-21 Wed 29-09-21 65SS+5 days
70 Centralised Air-Conditioning Work (All levels)13 days Tue 14-09-21 Mon 27-09-21 69SS+5 days
71 Modular Setups for Shops (20 Shops) 9 days Wed 29-09-21 Fri 08-10-21 69
72 Interior Design Implementation Work 19 days Mon 20-09-21 Sat 09-10-21 70SS+6 days
73 Exterior Finishing 64 days Fri 06-08-21 Tue 12-10-21 62SS
74 Putty Work (All levels) 16 days Fri 06-08-21 Mon 23-08-21
75 Paint (All levels) 25 days Mon 23-08-21 Fri 17-09-21 74
76 Exterior Designing (Few Sections) 10 days Fri 17-09-21 Tue 28-09-21 75
77 Parking Construction 13 days Tue 28-09-21 Tue 12-10-21 76
Page 3
View publication stats
Page 4