ID WBS Task Name Duration Start Finish January September May January September May January September

B E M B E M B E M B E M B E M B
1 1 KALU GANGA LEFT BANK DEVELOPMENT 56.2 mons Mon 1/1/18 Sat 8/13/22 56.2 mons
PROJECT 1/1 8/13
2 1.1 Construction of project offices 10 mons Mon 1/1/18 Sat 10 mons
10/27/18 1/1 10/27
15 1.2 Rehabilitation of access road 15 mons Sun 4/1/18 Mon 15 mons
6/24/19 4/1 6/24
19 1.3 Rehabilitation and improvements to 19 mons Wed Fri 3/6/20 19 mons
Singha wewa 8/15/18 8/15 3/6
23 1.4 Rehabilitation and improvements to 19 mons Sun Tue 5/5/20 19 mons
Sooriya wewa 10/14/18 10/14 5/5
27 1.5 Rehabilitation and improvements to 19 mons Mon Wed 19 mons
Kanthi wewa 10/1/18 4/22/20 10/1 4/22
31 1.6 Rehabilitation and improvements to 19 mons Tue 1/1/19 Thu 7/23/20 19 mons
Kuranku panchan 1/1 7/23
35 1.7 Rehabilitation and improvements to 19 mons Sat 3/2/19 Mon 19 mons
Vellanikulam 9/21/20 3/2 9/21
39 1.8 Rehabilitation and improvements to 14 mons Mon 4/1/19 Sun 5/24/20 14 mons
Pattiya noothu kulam 4/1 5/24
43 1.9 Construction of channel system and 19 mons Wed 5/1/19 Fri 11/20/20 19 mons
blocking out theeneri veli area 5/1 11/20
47 1.10 Construction of Kaluganga reservoir 39 mons Sat 6/1/19 Sat 8/13/22 39 mons
6/1 8/13
51 1.11 Improvements to Janaranjana wewa 21 mons Tue 10/1/19 Mon 21 mons
6/21/21 10/1 6/21
55 1.12 Construction of Link canal between 14 mons Fri 11/1/19 Thu 14 mons
Kaluganga and Singha wewa 12/24/20 11/1 12/24
59 1.13 Construction of Link canal between 8 mons Wed 1/1/20 Thu 8/27/20 8 mons
Janaranjana wewa and Singha wewa 1/1 8/27
63 1.14 Construction of link canal between 8 mons Mon Tue 9/8/20 8 mons
Sooriya wewa and Kanthi wewa 1/13/20 1/13 9/8
67 1.15 Construction of link canal between 24 mons Mon Sat 2/5/22 24 mons
Kanthi wewa and Kuranku panchan 2/17/20 2/17 2/5
71 1.16 Construction of link canal between 8 mons Sun 3/1/20 Mon 8 mons
Kuranku panchan and Vellani kulam 10/26/20 3/1 10/26
75 1.17 Construction of link canal between 8 mons Mon 6/1/20 Tue 1/26/21 8 mons
Vellan kulam and pattiyan wewa 6/1 1/26
79 1.18 Construction of feeder canal between 16 mons Mon Thu 8/12/21 16 mons
Mahaweli Diversion point to 4/20/20 4/20 8/12
Janaranjana

Page 1