DETAILED ASSUMPTION LOGS

Project Name: 2 Storey Timber Resedential House Target End: 02/27/23


Project Manager: Acuzar, Judel Jhoanna Marie G. Assump Target End 02/27/23 Days of Work / Week 7 days
Date Stated: March 7, 2022 Allowable Days 31 Days

ISSUE YES OR NO
ASMP No. Date Started Assumption Actions Due Date Validation Assigned To Status INCLUDES ON WEEKLY
REPORT

1 07/08/2022 Mobilization Hire limited employee to minimize the budget 07/13/22 Acuzar, Judel Jhoanna Marie COMPLETE YES
2 07/13/22 Breaking and Removal of Substructures Hire limited employee to minimize the budget 07/20/22 Librado, Herlcian COMPLETE YES
3 07/20/22 Clearing and Grubbing Hire limited employee to minimize the budget 07/22/22 Dumalanta, Aiko COMPLETE YES
4 07/22/22 Excavation of Columns Hire limited employee to minimize the budget 07/29/22 Del Mundo, John Marcie COMPLETE YES
5 Application of Termite Control Fluid COMPLETE YES
6 07/29/22 Cutting and Assembly of Column Yakal Needing 2 Options Hired less Employee for Heavy Equipment or Hire 8-10 Employee 08/13/22 Trongco, Danica Mae COMPLETE YES
7 Placing of Column Yakal COMPLETE YES

Cannot be delayed, If a problem occurred in ASMP No. 005, request Overtime to the PM for Asmp
8 Cutting, Assembly , Placing of Girders or Beams , Joists and treamer COMPLETE YES
No. 006 [ Will be based on WPSR ]

Equipment and electricity are required to be completed this task in 3-4 days if no available
9 Cutting, Assembly of Placing Wall Plates C16 Timber COMPLETE YES
electricity , additional employees will be hired accoding to project budget.
08/13/22 08/28/22 Remigio, Glenn

Equipment and electricity are required to be completed this task in three days if no available
electricity , additional employees will be hired accoding to project budget. If ASMP Nos. 008 and
10 Cutting and and Assembly Placing of walls Mahogany, Big Leaf COMPLETE YES
009 are completed within 6 days, we will move on to ASMP No. 011 to add the budget time of 3
days.

Cannot be delayed, If a problem occurred in ASMP No. 005, request Overtime to the PM for Asmp
11 08/28/22 Installation of wood Falsework for 2nd floor joists 09/01/2022 Bagus, Glazzy COMPLETE YES
No. 006 [ Will be based on WPSR ]

Cannot be delayed, If a problem occurred in ASMP No. 005, request Overtime to the PM for Asmp
12 Cutting and Assembly of Column Yakal ( 2nd floor) Piol, John Phillip COMPLETE YES
No. 006 [ Will be based on WPSR ]

09/01/2022 09/16/22
Cannot be delayed, If a problem occurred in ASMP No. 005, request Overtime to the PM for Asmp
13 Placing of Column Yakal ( 2nd floor) Magusib, Princess COMPLETE YES
No. 006 [ Will be based on WPSR ]

Equipment and electricity are required to be completed this task in 3-4 days if no available
14 Cutting, Assembly , Placing of Girders or Beams , Joists and treamer ( 2nd floor) COMPLETE YES
electricity , additional employees will be hired accoding to project budget.
09/16/22 09/31/22 Catimpuhan, Christine

Equipment and electricity are required to be completed this task in 3-4 days if no available
15 Cutting, Assembly of Placing Wall Plates C16 Timber (2nd floor) COMPLETE YES
electricity , additional employees will be hired accoding to project budget.

Equipment and electricity are required to be completed this task in 3-4 days if no available
16 09/31/22 Cutting and Assembly Placing of walls Mahogany, Big Leaf (2nd floor) 10/03/2022 Del Mundo, John Marcie COMPLETE YES
electricity , additional employees will be hired accoding to project budget.

17 10/03/2022 Cutting, Assembly of flooring for 2nd floor joists Cutting of designed flooring can be done outside from the workplace, this could be done in 2days 10/08/2022 Capistrano, John COMPLETE YES

18 10/08/2022 Removal of wood Falsework for 2nd floor joists Hire limited employee to minimize the budget 10/13/22 Galindez, Roy COMPLETE YES

19 10/13/22 Cutting, Assembly and Placing of ground flooring, electrical roughins and plumbings Plumbings, electrical roughins should be double checked properly and inspected before installation 10/21/22 Remigio, Glenn COMPLETE YES

This ASMP No.020 should not be postponed as planned. And we must have an allowable schedule
20 10/21/22 Fabrication of Roof Trusses 10/31/22 COMPLETE YES
because we have not used allowable time on each ASMP Number.

21 Roofbeam False Works Work with assembled falsework rather than disposable falsework. COMPLETE YES

22 10/31/22 Cutting, Assembly and Placing of Roof Beams The ASMP No.0020 should be completed before or on the due date. 11/12/2022 Acuzar, Judel Jhoanna Marie COMPLETE YES

23 Cutting, Assembly and Placing of Roof Beam electrical rough-ins Plumbings, electrical roughins should be double checked properly and inspected before installation COMPLETE YES

24 11/12/2022 Errection of Roof Trusses The ASMP No.0026 should be completed before or on the due date. 11/17/22 Galindez, Roy COMPLETE YES
25 11/17/22 Placing of Electrical Rough-ins and Plumbing Hire limited employee to minimize the budget 11/22/22 Dumalanta, Aiko COMPLETE YES
26 11/22/22 Errection of Roof Trusses The ASMP No.0026 should be completed before or on the due date. 11/27/22 Reynado, Robbie COMPLETE YES
27 11/27/22 Leak Test for Water Line and Plumbing Line Hire limited employee to minimize the budget 11/30/22 Jacaban, Nathaniel COMPLETE YES
28 11/30/22 Plastering of Flooring, Ceiling, Walls Hire a limited number of employees to reduce costs. 12/20/22 Tatel, Gavereal COMPLETE YES

29 12/20/22 Roof Insulation and Colored Long Span Roofing Installation Hire a limited number of employees to reduce costs. 12/28/22 Perico, Nataniel COMPLETE YES

30 12/28/22 Paint Works Hire a limited number of employees to reduce costs. 01/19/23 Trongco, Danica Mae COMPLETE YES

31 01/19/23 Installation of Doors and Windows Hire a limited number of employees to reduce costs. .01/29/23 Catimpuhan, Christine COMPLETE YES

32 .01/29/23 Installation of Plumbing Fixtures and Electrical Fixtures This should be done when the electrical installation has been made 02/04/2023 Remigio, Glenn COMPLETE YES

33 02/04/2023 Testing of Electrical Connection Hire a limited number of employees to reduce costs. 02/05/2023 Remigio, Glenn COMPLETE YES

34 02/05/2023 Clearing and Cleaning Hire a limited number of employees to reduce costs. 02/06/2023 Acuzar, Judel Jhoanna Marie COMPLETE YES
35 02/06/2023 Demobilization TARGET END 02/07/2023 Acuzar, Judel Jhoanna Marie COMPLETE YES