You are on page 1of 2

Construction Power - Electrical Checklist - Mahan Energen Ltd.

-- Annexure-A
Area Check list Date:

Items to check Yes No N/A Comments


Name of upstream panel feeder number , Panel rating in Ampere and further distribution
area name and panel feeder number shall be painted on Main Panel/Main DB available
or not?
Are all circuits identified?
Is access adequate of all four sides?
Are all panels standard make? In house fabricated panel are not acceptable.
Distribution
Proper shed ( with Three side covered with top shed ) available or not?
Panel/DB installed on appropriate location to avoid the water logging or not?
Proper light inside and outside of panel/DB available or not?
Is the next upstream point of isolation clearly identified?
Are all pushbutton & indicator lamps appropriately labelled?
Are indicator available and glowing condition visually at panel.

Is there is cable gland used and spare holes sealed properly ?


General Installation Is all equipment accessible?
Is the next upstream point of isolation clearly identified?
Are all socket outlets protected by a 30mA RCCB?

Are cables appropriately installed & terminated?


Are cables near hot surfaces?
Are cables appropriately supported?
Any signs of overheating?
General cabling
Are cable undergrounded 1 mtr. Deep and cable route marker placed @15mtr distance
span?

Are all unused / spare cables correctly terminated and / or taped and identified?

Are all portable eqipments inspections up to date and signed tag pasted on equipment?
Portable Appliances Are all portable appliance inspection periods correct?
(including extension
leads) Are all portable appliances in a good condition?
All portable switch board shall be equiped with RCCB,30mA and tagging available or
not?
Are appropriate fire extinguishers available?
Are fire extinguisher inspections up to date?
Emergency Response Are emergency light test up to date?
Is the appropriate emergency response equipment provided, available, and inspections
up to date?

Two earth pit available or not at main panel/DB?


Earthpit resistance value marked on earthpit or not? (Earthpit restance value record
should be maintained-once in two month)
Earth pit connected to main DB/Panel properly or not?
Are all earthing points clearly identified ?
Danger Sign board on panel available or not?
Earthing and safety Artificial Resuscitation chart available at main DB panel
point
Multimeter shall be used for checking of voltage. (Line Tester should not be use for
voltage checking)
Insulated tools shall be available at site for connection/disconnection/working in
electrical panel (Scredriver , plier, spanner (Ring/D)
Electrical Hand gloves available or not and in use or not?
Rubber mat in front of panel available ot not?

Are all people observed working safely?


Are they using appropriate tools for the job?
If working at a height, is appropriate (non-conducting) ladders used? If not, how is this
managed?
List of qualified electrician name , education , experience , wireman license is pasted on
People performing main panel/DB or not?
electrical work List of qualified electrician name , education , experience , wireman license status
submitted to adani or not?
Is the work area clean, dry and free from clutter?
If required, is a standby person available for the work, and are they competent to
perform their duties? Minimum two person should be deputed for any electrical related
work )

Adani Electrical Adani Electrical HOD


Signature : Contractor Safety officer Contractor Electrical Engineer Adani Safety Area Incharge