Professional Documents
Culture Documents
Implementation
Workshop Summary
BI#: 10-01413
Project Title: Install Flare Gas Recovery System at
Khursaniyah Gas Plant
Project Phase: DBSP Phase
Prepared by: Abdulmajeed Almoumen
VMPSC Facilitator
3/12/2024
Project Classification: C
Event Date: Tuesday | March 12, 2024
Venue: KBR Office, Al Khobar
The primary objective of this project is to install a flare gas recovery system at
Khursaniyah Gas Plant (KGP) to comply with Saudi Aramco standards towards
protecting the environment.
Presently, Khursaniyah Gas Plant (KGP) has an average routine flaring rate of 2
MMSCFD, resulting in Greenhouse Gas (GHG) being emitted into the
atmosphere.
KGP Flare Gas Recovery System (FGRS) project has been identified as part of a
company-wide flare minimization plan to achieve zero flaring by 2030. This
project is part of the Corporate Environmental Master Plan.
Install FGRS to recover the flare gas from the High Pressure (HP) flare, Low
Pressure (LP) flare, Acid Gas (AG) flare and Cold Flare (CF) Systems.
A common flare gas recovery header (24”) will be added by connecting all the
flare lines and routing to the existing Atmospheric Compressor.
For more details refer to GES+ SOW and Project Scoping Paper.
The LLI workshop was conducted on the 12th of March 2024 for BI-10-01413 Install Flare
Gas Recovery system at Khursaniyah Gas Plant at DBSP Phase. The session reviewed
lessons applicable based on cost and schedule impact. The workshop involved examining
the project scope using different areas of focus, emphasizing items with significant
impact and urgency, to develop preventive actions and avoidance strategies. The team
captured applicable lessons in the implementation worksheet (Appendix A).
Number of Lessons
Areas of Focus based on Impact Severity Selected
Management 01
Contracting 02
Interface Planning 01
Field Verification 02
Mechanical 01
Piping 01
Electrical 02
Additional Lessons 13
A total of 33 lessons and design deficiencies extracted from similar projects were
shared and discussed during the workshop (Appendix A) and assigned action plans and
target dates.
This report shall serve as a starting point for implementing preventive actions and
avoidance strategies/recommendations highlighted. Conducting periodic Lesson Learned
round-table meetings will also contribute greatly to the success of your efforts.
IPT Leads shall develop preventive actions for each LL topic listed in
Attachment 1.
Responsible person from concerned organization shall be assigned as owner
of the selected lesson(s)
LL owner shall assure actions are measurable, precise and feasible within the
project phase
All selected LL shall be implemented/executed within the proposed dates.
Ineffective
KBR (Tanveer
planning and KBR shall prepare the level
Khan)/ SAPMT
1 1.6 management of Pitfall 1.6 M H II EPC schedule for SA 14/04/2024 Ongoing
(Abdullah Al-
interfaces among review and approval
Ghamdi)
all parties
2.0 Contracting
KBR (Tanveer
Underutilizing
khurais- KBR shall prepare the 3D Khan)/ SAPMT
11 8.6 benefits of 3D L L 01/02/2025 Ongoing
051 model during the PP phase (Abdullah Al-
model
Ghamdi)
13
Phase Impact Urgency Action Items
S D P D P C P H M L H M L
B P D R O E O I E O
Pitfall / T S O N C I D G D
Pitfall / Lesson Lesson P C S G W W Target
What Responsible
Link U / H Completio Status
(List of action Plans) Person
S H n Date
D
U
Y
Ensure Clarity in
Refer to the project specific
Definition of Tie-in
14 8.25 hnrp-172 below points(17.03 to
& Modification
17.09)
Work Scopes
14
Phase Impact Urgency Action Items
S D P D P C P H M L H M L
B P D R O E O I E O
Pitfall / T S O N C I D G D
Pitfall / Lesson Lesson P C S G W W Target
What Responsible
Link U / H Completio Status
(List of action Plans) Person
S H n Date
D
U
Y
maintenance
access and (Abdullah Al-
equipment
removal of Ghamdi)
equipment
12.0 Piping
KBR (Tanveer
3D Model
hwgpd- KBR shall prepare the 3D Khan)/ SAPMT
18 12.5 Development and L L 01/02/2025 Ongoing
011 model during the PP phase (Abdullah Al-
Interface Issues
Ghamdi)
13.0 Electrical
Insufficient
coordination with
Power Systems KBR shall ensure proper
(PS) during coordination with Power KBR (Tanveer
design and Systems (PS) during DBSP Khan)/ SAPMT
19 13.1 Pitfall 13.1 L L 01/06/2024 Ongoing
procurement phase to review and (Abdullah Al-
phases to review approve electrical design Ghamdi)
and approve issues
electrical design
issues
KBR shall verify the existing
KBR (Tanveer
Design battery rooms size based
Khan)/ SAPMT
20 13.15 Considerations for insp-029 L L on the final size of UPS, 01/06/2024 Ongoing
(Abdullah Al-
Battery Rooms and in case if UPS is
Ghamdi)
upgraded to higher size.
15
Phase Impact Urgency Action Items
S D P D P C P H M L H M L
B P D R O E O I E O
Pitfall / T S O N C I D G D
Pitfall / Lesson Lesson P C S G W W Target
What Responsible
Link U / H Completio Status
(List of action Plans) Person
S H n Date
D
U
Y
17.0 Additional Lessons
Check for proper
equipment KBR shall check, verify and KBR (Nazar/
location to reserve the location of the Irfan)/ SAPMT
21 17.01 - L L 01/06/2024 Ongoing
minimize later equipment (valves and (Abdullah Al-
revisions during Piperack) Ghamdi)
design
Securing EPD
KBR shall expedite the KBR (Tanveer
and NCEC
issue of the EIA study and Khan)/ SAPMT
22 17.02 approval for EIA - H H 01/06/2024 Ongoing
obtain approval from EPD (Abdullah Al-
during DBSP
and NCEC. Ghamdi)
(Pre-FEED).
KBR (Shaik/
Interfaces (DCS, KBR shall finalize the
AbdullahAl-
ESD, UPS, MCC) interfaces requirements
23 17.03 - M M Ashikh)/ SAPMT 01/06/2024 Ongoing
with the existing with the existing plant
(Abdullah Al-
plant control system.
Ghamdi)
KBR shall prepare the KBR (Tanveer
Initiate interface interface management plan Khan)/ SAPMT
24 17.04 - L L 01/06/2024 Ongoing
management plan identifying all the interfaces (Abdullah Al-
with the existing facilities. Ghamdi)
28 17.08 Tie-in & Potential - M M The project should provide KBR 01/06/2024 Ongoing
Challenges for the a utility station in the new (Nazar/Irfan)/
following items: facility. SAPMT
• Utility Station – (Abdullah Al-
Flare Area Ghamdi), FP
(Abdullah
17
Phase Impact Urgency Action Items
S D P D P C P H M L H M L
B P D R O E O I E O
Pitfall / T S O N C I D G D
Pitfall / Lesson Lesson P C S G W W Target
What Responsible
Link U / H Completio Status
(List of action Plans) Person
S H n Date
D
U
Y
Alogaily)
KBR
Tie-in & Potential (Nazar/Irfan)/
Challenges for the The project should provide SAPMT
29 17.09 following items: - M M a bypass for FGRS main (Abdullah Al- 01/06/2024 Ongoing
• Instrument Air isolation valve. Ghamdi), FP
capacity. (Abdullah
Alogaily)
KBR shall check and verify
Draining of the if the is any condensation in
KBR
flare headers the system, then KBR shall
(Nazar/Irfan)/
between K.O provide a mechanism for
SAPMT
drums in flare draining potential
30 17.10 - M M (Abdullah Al- 01/06/2024 Ongoing
area and condensed liquid in the flare
Ghamdi), FP
Receiving headers between K.O
(Abdullah
Atmospheric drums in flare area and
Alogaily)
compressors. Receiving Atmospheric
compressors.
Quantify the additional
demand of N2 and
KBR
Instrument air and analyze
(Nazar/Irfan)/
the current existing air
N2 and SAPMT
compressors/N2 production
31 17.11 Instrument air M M (Abdullah Al- 01/06/2024 Ongoing
membranes where there is
demand Ghamdi), FP
a potential need to expand
(Abdullah
the existing
Alogaily)
system production for N2
and IA.
18
Phase Impact Urgency Action Items
S D P D P C P H M L H M L
B P D R O E O I E O
Pitfall / T S O N C I D G D
Pitfall / Lesson Lesson P C S G W W Target
What Responsible
Link U / H Completio Status
(List of action Plans) Person
S H n Date
D
U
Y
KBR (Nazar)/
Exact materials KBR shall prepare the
SAPMT
32 17.12 specification for - M M materials specification for 01/06/2024 Ongoing
(Abdullah Al-
the tie-in’s points the tie-in’s points.
Ghamdi)
19
5. Appendix B: Workshop Participants