Snag list

Sr. No. Snag Points Date Status


Sliding door sensor did not work propery staff need to go very close to
1 02‐01‐2024 Did not respond
it. Some time its not work even close to the door
2 MPS Meachine for sliding door. Dmans taken for repair work 02‐01‐2024 Did not respond
3 Tissue holder shifting in Female Toilet 01‐01‐2024
Work station area completed and board
4 Steel patti on door and in carpet area 01‐01‐2024
room work is pending
5 Remove cover of fire fighting sprinklers 02‐01‐2024 Did not respond
6 Board Room Table cleaning 01‐01‐2024
Chetan Vasani will take the glass by
7 Crack Glass partition change in chairman cabin 04‐01‐2024
Thursday
8 Leakage Problem in Directors Toilet near mirror 02‐01‐2024
Drasit will send manpower on 02/01/2024
We have to do air balancing work again in
9 AC Balancing as per MEP Drawing. ‐
summer
Rajkumar saying that it will take time of 3
10 passanger Lift indicator changes to alpha numeric ‐
month to change the indicator
Had word with faisal he will install curtain
11 Blinds installation in lounge area 03‐01‐2024
in lounge area on Wednesday
12 Electrical DB nomanclature 05‐01‐2024
13 Lighting DB check and inform To MEP 04‐01‐2024