TASK NAME COST Materials Labour Machinaries/ Equipment Duration
ARCHITECTURAL WORKS RM 1,011,830.80 21 days
Bricklaying RM 295,008.60 18 days
External Wall RM 147,192.00 18 days
Brick, mortar and DPC damp proof course 1 skilled labour and 2 labour (helper) Trowel,brick hammer Bricklaying including DPC RM 147,192.00 21 days - Internal Wall RM 147,816.60 14 days Brick, mortar and DPC damp proof course 1 skilled labour and 2 labour (helper) Trowel,brick hammer Bricklaying including DPC RM 147,816.60 16 days
Shower wall niche RM 8,400.00 3 days
Plywood 1 operator, 1 skilled labour Nail, hammer Install formwork RM 2,800.00 4 days Rebar End plier's cutter, chain block, stell hook, measuring tape Install bar reinforcement RM 2,800.00 4 days Cement 1 skilled labour and 2 labour (helper) Concrete Mixer Truck, shovel, wheelbarrow Concreting RM 2,800.00 4 days
Reinforced concrete counter top RM 7,560.00 5 days
Plywood 2 labour Nail, hammer Install formwork RM 2,520.00 6 days Rebar 2 labour End plier's cutter, chain block, stell hook, measuring tape Install bar reinforcement RM 2,520.00 6 days Cement 1 skilled labour and 1 labour (helper) Concrete Mixer Truck, shovel, wheelbarrow Concreting RM 2,520.00 6 days
Door RM 105,688.00 21 days
timber 2 labour Nail, hammer Installation of lintol RM 12,560.00 5 days hardwood timber 1 carpenter Nail, hammer,screwdriver Supply and install door frame RM 15,750.00 8 days harwood timber, key lock stainless steel 2 labour Nail, hammer,screwdriver Supply and install door including lockset RM 77,378.00 25 days
Window RM 72,384.00 7 days
timber 2 labour Nail, hammer Installation of lintol RM 4,560.00 5 days hardwood timber 1 skilled labour (carpenter) Nail, hammer,screwdriver Supply and install windows c/w accessories RM 67,824.00 8 days
Internal Finishes RM 522,790.20 14 days
Internal Ceiling Finishes RM 55,487.20 7 days
plasterboard 1 skilled labour plasterboard lifter, hoist, trolley, screwdriver,sander Installing plasterboard RM 34,331.20 8 days silicon sealant 2 labour Sealant finishers and sealant gun Apply sealant RM 21,156.00 5 days
Internal Wall Finishes including wall niche RM 244,784.80 14 days
Cement, paint 1 skilled labour Trowel,scraper, paint brush Plastering and painting RM 185,762.20 16 days cement, tile 2 labour level screed, tile trowler, grout saws Screeding and tiling RM 59,022.60 13 days
Reinforced concrete counter top RM 5,040.00 7 days
Cement, paint 1 skilled worker Trowel,scraper, paint brush Plastering and painting RM 2,520.00 8 days cement, tile 2 labour level screed, tile trowler, grout saws Screeding and tiling RM 2,520.00 6 days
Sanitary Appliances RM 84,817.60 7 days
Sanitary item 1 skilled labour screwdriver Install sanitary appliances RM 84,817.60 8 days
Internal Floor Finishes RM 132,660.60 14 days
cement, tile 1 skilled labour level screed, tile trowler, grout saws Screeding and tiling RM 132,660.60 16 days
EXTERNAL WORKS WITHIN BOUNDARY RM 273,290.80 30 days
Bricklaying RM 115,682.97 21 days
Fencing RM 62,287.75 18 days
Bricks, Mortar, Rebar 2 labour (bricklayer) Brick Saw, Wheelbarrow, Shovel Bricklaying including reinforcement RM 62,287.75 20 days
SESCO Compartment RM 16,936.96 21 days
Bricks, Mortar, Rebar 2 labour (bricklayer) Brick Saw, Wheelbarrow, Shovel Bricklaying including reinforcement RM 16,936.96 25 days
Refuse Chamber & Mailbox Compartment RM 36,458.26 21 days
Bricks, Mortar, Rebar 2 labour (bricklayer) Brick Saw, Wheelbarrow, Shovel Bricklaying including reinforcement RM 36,458.26 25 days