TASK NAME COST Materials Labour Machinaries/ Equipment Duration

ARCHITECTURAL WORKS RM 1,011,830.80 21 days

Bricklaying RM 295,008.60 18 days

External Wall RM 147,192.00 18 days


Brick, mortar and DPC damp proof course 1 skilled labour and 2 labour (helper) Trowel,brick hammer
Bricklaying including DPC RM 147,192.00 21 days
-
Internal Wall RM 147,816.60 14 days
Brick, mortar and DPC damp proof course 1 skilled labour and 2 labour (helper) Trowel,brick hammer
Bricklaying including DPC RM 147,816.60 16 days

Shower wall niche RM 8,400.00 3 days


Plywood 1 operator, 1 skilled labour Nail, hammer
Install formwork RM 2,800.00 4 days
Rebar End plier's cutter, chain block, stell hook, measuring tape
Install bar reinforcement RM 2,800.00 4 days
Cement 1 skilled labour and 2 labour (helper) Concrete Mixer Truck, shovel, wheelbarrow
Concreting RM 2,800.00 4 days

Reinforced concrete counter top RM 7,560.00 5 days


Plywood 2 labour Nail, hammer
Install formwork RM 2,520.00 6 days
Rebar 2 labour End plier's cutter, chain block, stell hook, measuring tape
Install bar reinforcement RM 2,520.00 6 days
Cement 1 skilled labour and 1 labour (helper) Concrete Mixer Truck, shovel, wheelbarrow
Concreting RM 2,520.00 6 days

Door RM 105,688.00 21 days


timber 2 labour Nail, hammer
Installation of lintol RM 12,560.00 5 days
hardwood timber 1 carpenter Nail, hammer,screwdriver
Supply and install door frame RM 15,750.00 8 days
harwood timber, key lock stainless steel 2 labour Nail, hammer,screwdriver
Supply and install door including lockset RM 77,378.00 25 days

Window RM 72,384.00 7 days


timber 2 labour Nail, hammer
Installation of lintol RM 4,560.00 5 days
hardwood timber 1 skilled labour (carpenter) Nail, hammer,screwdriver
Supply and install windows c/w accessories RM 67,824.00 8 days

Internal Finishes RM 522,790.20 14 days

Internal Ceiling Finishes RM 55,487.20 7 days


plasterboard 1 skilled labour plasterboard lifter, hoist, trolley, screwdriver,sander
Installing plasterboard RM 34,331.20 8 days
silicon sealant 2 labour Sealant finishers and sealant gun
Apply sealant RM 21,156.00 5 days

Internal Wall Finishes including wall niche RM 244,784.80 14 days


Cement, paint 1 skilled labour Trowel,scraper, paint brush
Plastering and painting RM 185,762.20 16 days
cement, tile 2 labour level screed, tile trowler, grout saws
Screeding and tiling RM 59,022.60 13 days

Reinforced concrete counter top RM 5,040.00 7 days


Cement, paint 1 skilled worker Trowel,scraper, paint brush
Plastering and painting RM 2,520.00 8 days
cement, tile 2 labour level screed, tile trowler, grout saws
Screeding and tiling RM 2,520.00 6 days

Sanitary Appliances RM 84,817.60 7 days


Sanitary item 1 skilled labour screwdriver
Install sanitary appliances RM 84,817.60 8 days

Internal Floor Finishes RM 132,660.60 14 days


cement, tile 1 skilled labour level screed, tile trowler, grout saws
Screeding and tiling RM 132,660.60 16 days

EXTERNAL WORKS WITHIN BOUNDARY RM 273,290.80 30 days

Bricklaying RM 115,682.97 21 days

Fencing RM 62,287.75 18 days


Bricks, Mortar, Rebar 2 labour (bricklayer) Brick Saw, Wheelbarrow, Shovel
Bricklaying including reinforcement RM 62,287.75 20 days

SESCO Compartment RM 16,936.96 21 days


Bricks, Mortar, Rebar 2 labour (bricklayer) Brick Saw, Wheelbarrow, Shovel
Bricklaying including reinforcement RM 16,936.96 25 days

Refuse Chamber & Mailbox Compartment RM 36,458.26 21 days


Bricks, Mortar, Rebar 2 labour (bricklayer) Brick Saw, Wheelbarrow, Shovel
Bricklaying including reinforcement RM 36,458.26 25 days